| 2016-08-02 12:39:50 | 1ST REVIEW FBC-2014 MECHANICAL, ENERGY CONSERVATION |
| | CODES |
| | PERMIT #16070193 |
| | 8/2/16 |
| | |
| | 1) PROVIDE AC COOLING AND HEATING CALCULATIONS FOR |
| | RTU'S 1, 2, 3, & 4- SECTION 403.2.1 FBC-14 ENERGY |
| | CONSERVATION. |
| | |
| | 2) PROVIDE ENERGY CALCULATIONS- SECTIONS C101.2 & |
| | C401.2 FBC-14 ENERGY CONSERVATION. |
| | |
| | 3) SHEET M1.1: OUTDOOR AIR AND EXHAUST VENTILATION |
| | CALCULATIONS ARE REQUIRED PER TABLE 403.3 HOWEVER THE |
| | ENGINEER IS INDICATING A DESIGN BASED ON THE |
| | VENTILATION RATE PROCEDURE PER FBC-14 AND ASHRAE 62.1. |
| | SEE SECTIONS 6.2.1- 6.2.7 ASHRAE 62.1 AND PROVIDE |
| | CALCULATIONS AND EQUATION 6-1 ON THE PLANS. PLEASE NOTE |
| | PER SECTION 6.1, EXHAUST VENTILATION MUST STILL BE |
| | PROVIDED WHERE REQUIRED. |
| | |
| | 4) M2.1 DETAIL BAY: PROVIDE AN EXHAUST VENTILATION |
| | CALCULATION PER TABLE 6-4 ASHRAE 62.1 AND TABLE 403.3 |
| | FBC-14 MECHANICAL. PLEASE NOTE PER TABLE 403.3 FOOTNOTE |
| | B, RECIRCULATION OF AIR FROM THE DETAIL BAY TO THE |
| | STORAGE AND TOILET ROOMS IS PROHIBITED- PLEASE CORRECT |
| | THE PLAN. |
| | |
| | 5) M1.2, M2.1, & M4.1: THE EXHAUST FAN SCHEDULE |
| | SPECIFIES EF-3 TO BE INTERLOCKED WITH HAZARDOUS GASES |
| | SENSORS. SHOW THE LOCATIONS OF THE SENSORS AND PROVIDE |
| | A SUBMITTAL WITH APPROVAL SIGNATURE BY THE EOR. |
| | A) M4.1: INDICATE WHICH RTU'S AND WHICH EXHAUST FANS |
| | WILL BE LINKED TO THE SENSORS. |
| | |
| | 6) M2.1: PROVIDE AN EXHAUST SYSTEM AND CALCULATION FOR |
| | THE JANITOR'S CLOSET- TABLE 6-4 ASHRAE 62.1. |
| | |
| | 7) M2.1: ALTHOUGH THE VEHICLE SHOWROOM AREA HAS BEEN |
| | CLASSIFIED AS S-1 STORAGE UNDER A PROPOSED ALTERNATIVE |
| | DESIGN METHOD, THE MECHANICAL PLANS ARE NOT SHOWING A |
| | MEANS OF EXHAUST VENTILATION WHICH IS TYPICALLY |
| | REQUIRED FOR PRIVATE OR PUBLIC VEHICLE STORAGE. PLEASE |
| | PROVIDE A SYSTEM DESIGNED IN ACCORDANCE WITH THE RATES |
| | AND PROCEDURES REQUIRED UNDER SECTION 404.1 ENCLOSED |
| | PARKING GARAGES. |
| | |
| | 8) PROVIDE A MECHANICAL ROOF PLAN SHOWING THE LOCATIONS |
| | OF ALL ROOFTOP EQUIPMENT AND REQUIRED CLEARANCE |
| | DISTANCES FROM EXHAUST OUTLETS TO AIR INTAKES- SECTION |
| | 501.3.1 |
| | |
| | 9) PROVIDE WIND LOAD ENGINEERING FOR ATTACHMENT OF ALL |
| | ROOFTOP MECHANICAL EQUIPMENT INCLUDING THE RTU'S, |
| | EXHAUST FANS, AND THEIR RESPECTIVE CURBS- SECTION |
| | 301.15. |
| | |
| | 10) PROVIDE SHUTOFF DAMPER CONTROLS FOR THE OUTDOOR AIR |
| | INTAKES AS REQUIRED BY SECTION C403.2.4.4 FBC-14 ENERGY |
| | CONSERVATION. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 561-805-6719 |
| | [email protected] |
| | |