| Plan Review Notes For Permit 16070062 |
| Permit Number |
16070062 |
|
| Review Stop |
E |
| Sequence Number |
1 |
|
| Notes |
| Date |
Text |
| 2016-07-07 15:03:05 | REVIEW 2014 5TH FBC ED. NEC 2011 | | | MARIO VALDES | | | ELECTRICAL PLAN EXAMINER | | | 561-805-6713 | | | [email protected] | | | | | | - CLARIFY HOW A 60 AMP SUB PANEL IS BEING FED FROM THE | | | EXISTING SERVICE WITH # 10 AWG IS GONA BE SUFFICIENT | | | FOR A 3000 VA POOL PUMP AND A 10000 VA POOL HEATER ? | | | REFLECT EXISTING SERVICE RISER DIAGRAM TO VERIFY LOAD | | | DISTRUBUTION NEC 215.5 | | | | | | - CORRECT LOAD CALCULATION IN ACCORDANCE WITH NEC | | | 220.82/83 OPTIONAL METHOD IF THAT IS THE INTENT AND | | | TAKE A LOOK AT THE AC DEMANDS. | | | | | | - PROVIDE A # 8 AWG EQUIPMENT GROUNDING CONDUCTOR | | | INSIDE THE RACEWAY FOR THE LIGHT NICHE BONDING. | | | ENCAPSULATE THE FORMING SHELL LUG TERMINAL WITH A | | | LISTED COMPOUND FOR DETERIORATION OF CONNECTION. NEC | | | 680.23(B)(1)(2) | | | | | | - SHOW BONDING DETAIL FOR SHED IF REQUIRED PER NEC | | | 680.26(7) FIXED METAL PARTS WITHIN 5' |
|