| Date |
Text |
| 2017-07-27 12:05:55 | REVISED 8/3/17 |
| | IF ALL OTHER TRADES PASS, A PROVISO IS POSSIBLE UPON |
| | REQUEST |
| | |
| | [email protected] |
| | 561-805-6724 |
| | |
| | BUILDING PLAN REVIEW |
| | W. P. B. PERMIT: 16061443 |
| | ADD: 718 S. DIXIE HWY. / CANOPY BY HILTON 14 STORY |
| | THRESHOLD BUILDING |
| | CONT: TBD/ TO BE DETERMINED |
| | TEL: 561-718-5987 / MARGARET LEON |
| | E-MAIL: MLEONDADLP.COM |
| | |
| | 2014 FLORIDA BUILDING CODE W 2014 WEST PALM BEACH |
| | AMENDMENTS TO THE FLORIDA BUILDING CODE, CHAPTER 1, |
| | ADMINISTRATION |
| | |
| | 4TH REVIEW |
| | DATE: 7/27/17 |
| | ACTION: DENIED |
| | |
| | 5B) SEMI-COMPLIED. SHEET 5 OF 6 THERE IS NO CONTRACTOR |
| | SIGNATURE NOR NOTARY WORK COMPLETED (SI AGREEMENT). WPB |
| | AMENDMENT 109.3.6.2 W.P.B, THIS IS REQUIRED PRIOR TO |
| | PERMIT ISSUANCE. |
| | |
| | 5E) 3RD REQUEST. THE CONTRACTOR WILL PRODUCE A JOB |
| | SUMMARY OR HISTORY FOR THIS TYPE OF CONSTRUCTION. |
| | THRESHOLD INSPECTION FORMS , GUIDELINES AND POLICIES |
| | FOR PROJECTS WERE E-MAILED TO: |
| | [email protected], PLEASE NOTE THIS E-MAIL ADDRESS CAME |
| | BACK UNDELIVERABLE. 07/14/2016 11:35 AM. |
| | [email protected] |
| | |
| | 42) COMMENT FROM PREVIOUS LIST (REVIEW #3): THE SHEET |
| | M2.02 IN STAIRWELL # 2 NOTE # 7 INDICATES DUCT IN THE |
| | STAIRWELL TO HAVE A 2 HOUR FIRE RATING. TO USE |
| | FLAMEBAR. SHEET A6.01A DETAIL 01 DOES NOT SHOW A DUCT |
| | GOING THROUGH THE STAIRWELL. SHEET A6.03 DETAILS 03 & |
| | 04 ARE CUT SECTIONS THROUGH THE STAIRWELL 2 BUT AGAIN |
| | NO DUCTS ARE SHOWN PENETRATING THE STAIRWELL ENCLOSURE. |
| | 2014 FBC-B 1022.5 PENETRATIONS. PENETRATIONS INTO AND |
| | OPENINGS THROUGH INTERIOR EXIT STAIRWAYS AND RAMPS ARE |
| | PROHIBITED EXCEPT FOR REQUIRED EXIT DOORS, EQUIPMENT |
| | AND DUCTWORK NECESSARY FOR INDEPENDENT VENTILATION OR |
| | PRESSURIZATION, SPRINKLER PIPING, STANDPIPES, |
| | ELECTRICAL RACEWAY FOR FIRE DEPARTMENT COMMUNICATION |
| | SYSTEMS AND ELECTRICAL RACEWAY SERVING THE INTERIOR |
| | EXIT STAIRWAY AND RAMP AND TERMINATING AT A STEEL BOX |
| | NOT EXCEEDING 16 SQUARE INCHES (0.010 M2). SUCH |
| | PENETRATIONS SHALL BE PROTECTED IN ACCORDANCE WITH |
| | SECTION 714. THERE SHALL BE NO PENETRATIONS OR |
| | COMMUNICATING OPENINGS, WHETHER PROTECTED OR NOT, |
| | BETWEEN ADJACENT INTERIOR EXIT STAIRWAYS AND RAMPS. |
| | |
| | 4TH REVIEW - RESPONSE LETTER STATES: "WE ARE PROVIDING |
| | A 2 HOUR RATED ENCLOSURE THAT ALLOWS MECHANICAL DUCTS |
| | TO RUN THRU IT WHILE ISOLATING THEM FROM THE STAIR." |
| | |
| | THE DETAIL 06 IS LABELED U415, BUT NOT CLEAR WHICH |
| | OPTION (OF UL U415) IS PROPOSED (SEE UL DIRECTORY; |
| | MULTIPLE OPTIONS AVAILABLE). THE TOP SHOWS 1/2" FIRE |
| | SEALANT; SHOULDN'T THIS BE A 2 HOUR HEAD OF WALL DETAIL |
| | IF USING THE STAIR LANDING AS A PART OF THE |
| | "ENCLOSURE"? RESPONSE LETTER STATES THAT THE 2 HOUR |
| | RATED ENCLOSURE ISOLATES THE DUCTS FROM THE STAIR, BUT |
| | IT APPEARS THAT YOU PROPOSE TO USE THE BOTTOM OF A |
| | STAIR LANDING AS A PART OF THE DUCT ENCLOSURE (DOES NOT |
| | APPEAR "ISOLATED"). PROPOSED CONSTRUCTION NOT CLEAR; IS |
| | THIS TO BE CONSTRUCTED AS A SHAFT, FBC B 713? IF |
| | PORTIONS OF THE STAIR ITSELF ARE UTILIZED FOR THIS |
| | ENCLOSURE, HOW HAS HEAT TRANSFER BEEN ADDRESSED? IT |
| | APPEARS THAT A FIRE IN THE SHAFT COULD RESULT IN LOSS |
| | OF THE ABILITY TO USE THE STAIR DUE TO HEAT. IT DOES |
| | NOT APPEAR THAT THE RATING IS TO THE INSIDE AS WELL AS |
| | THE OUTSIDE; IT APPEARS THAT THE RISK IS GREATER FROM |
| | THE INSIDE (FIRE RISK FROM DUCT TO INSIDE OF STAIR). |
| | |
| | PRIOR TO RESUBMITTING, SEND A DETAIL VIA EMAIL FOR |
| | PRELIMINARY REVIEW. |
| | |
| | 43) FROM PREVIOUS LIST, COMMENT #12 UNDER MECHANICAL |
| | REVIEW #3. THE SHAFT ENCLOSING THE OAR-1 DUCT SHALL BE |
| | CONTINUOUS THROUGH THE ELEVATOR LOBBY AND GARAGE PER |
| | FBC B 707.5, 711.4 & 713.5. |
| | |
| | 4TH REVIEW, RESPONSE IS THAT DUCT IS 2 HOUR RATED AND |
| | CONTINUOUS, INCLUDING OFFSETS. IT APPEARS THAT RATHER |
| | THAN PROVIDING A RATED SHAFT, FLAMEBAR IS PROPOSED. |
| | PLEASE ADVISE WHERE THIS IS PERMITTED IN THE CODE. IF |
| | THIS IS ALTERNATIVE MATERIALS AND METHODS, THIS MUST BE |
| | APPROVED BY BUILDING OFFICIAL. |
| | |
| | IF REQUESTING VIA ALTERNATIVE MATERIALS AND METHODS FBC |
| | 104.11 - THIS SHOULD BE REQUESTED, IN WRITING VIA A |
| | SIGNED AND SEALED LETTER: "AN ALTERNATIVE MATERIAL, |
| | DESIGN OR METHOD OF CONSTRUCTION SHALL BE APPROVED |
| | WHERE THE BUILDING OFFICIAL FINDS THAT THE PROPOSED |
| | DESIGN IS SATISFACTORY AND COMPLIES WITH THE INTENT OF |
| | THE PROVISIONS OF THIS CODE, AND THAT THE MATERIAL, |
| | METHOD OR WORK OFFERED IS, FOR THE PURPOSE INTENDED, AT |
| | LEAST THE EQUIVALENT OF THAT PRESCRIBED IN THIS CODE IN |
| | QUALITY, STRENGTH, EFFECTIVENESS, FIRE RESISTANCE, |
| | DURABILITY AND SAFETY." |
| | |
| | ALL INFORMATION - PRODUCT DATA SHEETS, ENGINEERING |
| | ANALYSIS, TEST REPORTS, ETC. AS APPLICABLE SHOULD BE |
| | SUBMITTED WITH THE LETTER. |
| | |
| | 44) BEFORE A PERMIT TO CONSTRUCT, MAY BE ISSUED, IMPACT |
| | FEES MUST BE PAID TO PALM BEACH COUNTY. THE ACTUAL |
| | PERMIT SET OF PLANS MUST BE STAMPED BY THAT OFFICE, AND |
| | A COPY OF THE PAID RECEIPT ATTACHED TO THE PERMIT |
| | APPLICATION. PLEASE CALL (561)233-5025 FOR MORE |
| | INFORMATION. |
| | |
| | 45) WHEN RESUBMITTING PLANS PLEASE INDICATE THE |
| | REVISION & REMOVE ANY VOIDED SHEETS & REPLACE ANY PAGES |
| | AS NECESSARY. A TRANSMITTAL LETTER LISTING THE ORIGINAL |
| | REVIEW COMMENT NUMBER, WITH A DESCRIPTION OF THE |
| | REVISION MADE, IDENTIFYING THE SHEET OR SPECIFICATION |
| | PAGE WHERE THE CHANGES CAN BE FOUND WILL HELP TO |
| | EXPEDITE YOUR PERMIT. THANK YOU FOR YOUR ANTICIPATED |
| | COOPERATION. |
| | |
| | NEW COMMENTS: |
| | |
| | ** THERE IS A DISCREPANCY IN PROPOSED FFE BETWEEN |
| | CIVILS AND ARCHITECTURAL PAGES. SHEET C3 (AND OTHER |
| | PAGES) SPECIFY A FFE OF 15.50 NGVD29. SHEET A1.11 |
| | SPECIFIES A FFE OF 13.75 NGVD29 (1.75' DISCREPANCY). AN |
| | EMAIL WAS SENT TO APPLICANT FOR CLARIFICATION. THIS |
| | POTENTIALLY AFFECTS CONNECTION TO CITY SYSTEMS (WATER, |
| | SEWER, ETC.) AND ACCESSIBILITY (ACCESSIBLE ROUTE), FBC |
| | 2014 ACCESSIBILITY. |
| | |
| | PLEASE EITHER EXPLAIN THE DISCREPANCY OR SEND, VIA |
| | EMAIL, HOW THIS WILL BE ADDRESSED (PROVISO ITEM, |
| | REVISION MAY BE REQUIRED). |
| | |
| | ** FBC B TABLE 1607.1, ROOF SURFACES SUBJECT TO |
| | MAINTENANCE WORKERS, 300# LIVE LOAD REQUIRED, S1.01. |
| | THIS CAN BE A PROVISO ITEM UPON REQUEST (OR CLARIFY, |