| 2016-06-24 17:20:37 | ****CORRECTIONS**** |
| | ***REVISED ON 7/13/16 TO INCLUDE SPECIFIC FBC107 |
| | PROVISIONS, TEXT OF THE FBC107 CODE REFERENCES*** |
| | |
| | SAMANTHA HILL |
| | BUILDING PLANS EXAMINER |
| | [email protected] |
| | 561-805-6724 |
| | |
| | 1. THREE COMPLETE ORIGINAL SETS OF PLANS (PERMIT |
| | DOCUMENTS) REQUIRED, FBC 107. |
| | |
| | 2. THE PRODUCT APPROVAL IS INCOMPLETE. PROVIDE THE |
| | PAGES OF THE PRODUCT APPROVAL APPLICABLE TO ALL |
| | SYSTEMS, FBC 1609. PAGES SPECIFIC TO ASSEMBLIES NOT |
| | APPLICABLE TO THE ONE SELECTED ARE NOT REQUIRED. |
| | |
| | 3. PRODUCT APPROVALS ARE TO BE REVIEWED BY DESIGNER OF |
| | RECORD PRIOR TO SUBMITTAL, FBC 107. |
| | |
| | SEE FBC 107.1, 107.2.1.2, 107.2.1.4, 107.3.1, 107.3.4, |
| | 107.3.4.2. |
| | |
| | 107.1 GENERAL. SUBMITTAL DOCUMENTS CONSISTING OF |
| | CONSTRUCTION DOCUMENTS, STATEMENT OF SPECIAL |
| | INSPECTIONS, GEOTECHNICAL REPORT AND OTHER DATA SHALL |
| | BE SUBMITTED IN TWO OR MORE SETS WITH EACH |
| | PERMIT APPLICATION. |
| | |
| | 107.2.1.2 FOR ROOF ASSEMBLIES REQUIRED BY THE CODE, THE |
| | CONSTRUCTION DOCUMENTS SHALL |
| | ILLUSTRATE, DESCRIBE AND DELINEATE THE TYPE OF ROOFING |
| | SYSTEM, MATERIALS, FASTENING |
| | REQUIREMENTS, FLASHING REQUIREMENTS AND WIND RESISTANCE |
| | RATING THAT ARE REQUIRED TO BE |
| | INSTALLED. PRODUCT EVALUATION AND INSTALLATION SHALL |
| | INDICATE COMPLIANCE WITH THE WIND |
| | CRITERIA REQUIRED FOR THE SPECIFIC SITE OR A STATEMENT |
| | BY AN ARCHITECT OR ENGINEER FOR THE |
| | SPECIFIC SITE MUST BE SUBMITTED WITH THE CONSTRUCTION |
| | DOCUMENTS. |
| | |
| | 107.2.1.4 QUALITY OF BUILDING PLANS. BUILDING PLANS |
| | SHALL BE DRAWN TO A MINIMUM 1/8 INCH |
| | SCALE UPON SUBSTANTIAL PAPER, CLOTH OR OTHER ACCEPTABLE |
| | MEDIUM. THE BUILDING OFFICIAL MAY |
| | ESTABLISH THROUGH DEPARTMENTAL POLICY, OTHER STANDARDS |
| | FOR PLANS AND SPECIFICATIONS, IN |
| | ORDER TO PROVIDE CONFORMITY TO ITS RECORD RETENTION |
| | PROGRAM. |
| | |
| | 107.3.1 APPROVAL OF CONSTRUCTION DOCUMENTS. WHEN THE |
| | BUILDING OFFICIAL ISSUES A PERMIT, THE |
| | CONSTRUCTION DOCUMENTS SHALL BE NOTED, IN WRITING OR BY |
| | STAMP, AS ?REVIEWED FOR CODE |
| | COMPLIANCE.? ONE SET OF CONSTRUCTION DOCUMENTS SO |
| | REVIEWED SHALL BE RETAINED BY THE BUILDING |
| | OFFICIAL. THE OTHER SET SHALL BE RETURNED TO THE |
| | APPLICANT, SHALL BE KEPT AT THE SITE OF WORK AND |
| | SHALL BE OPEN TO INSPECTION BY THE BUILDING OFFICIAL OR |
| | A DULY AUTHORIZED REPRESENTATIVE. |
| | |
| | 107.3.4 . . . THE REGISTERED DESIGN PROFESSIONAL IN |
| | RESPONSIBLE CHARGE |
| | SHALL BE RESPONSIBLE FOR REVIEWING AND COORDINATING |
| | SUBMITTAL DOCUMENTS PREPARED BY OTHERS, INCLUDING |
| | PHASED AND DEFERRED SUBMITTAL ITEMS, |
| | FOR COMPATIBILITY WITH THE DESIGN OF THE BUILDING. |
| | THOSE PRODUCTS WHICH ARE REGULATED BY |
| | DCA RULE 9N-3SHALL BE REVIEWED AND APPROVED IN WRITING |
| | BY THE DESIGNER OF RECORD PRIOR |
| | TO SUBMITTAL FOR JURISDICTIONAL APPROVAL. |
| | |
| | 107.3.4.2 DEFERRED SUBMITTALS. FOR THE PURPOSES OF THIS |
| | SECTION, DEFERRED SUBMITTALS ARE |
| | DEFINED AS THOSE PORTIONS OF THE DESIGN THAT ARE NOT |
| | SUBMITTED AT THE TIME OF THE |
| | APPLICATION AND THAT ARE TO BE SUBMITTED TO THE |
| | BUILDING OFFICIAL WITHIN A SPECIFIED PERIOD. |
| | DEFERRAL OF ANY SUBMITTAL ITEMS SHALL HAVE THE PRIOR |
| | APPROVAL OF THE BUILDING OFFICIAL. THE |
| | REGISTERED DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE |
| | SHALL LIST THE DEFERRED SUBMITTALS ON |
| | THE CONSTRUCTION DOCUMENTS FOR REVIEW BY THE BUILDING |
| | OFFICIAL. |
| | DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE |
| | SUBMITTED TO THE REGISTERED DESIGN |
| | PROFESSIONAL IN RESPONSIBLE CHARGE WHO SHALL REVIEW |
| | THEM AND FORWARD THEM TO THE |
| | BUILDING OFFICIAL WITH A NOTATION INDICATING THAT THE |
| | DEFERRED SUBMITTAL DOCUMENTS HAVE |
| | BEEN REVIEWED AND FOUND TO BE IN GENERAL CONFORMANCE TO |
| | THE DESIGN OF THE BUILDING. THE |
| | DEFERRED SUBMITTAL ITEMS SHALL NOT BE INSTALLED UNTIL |
| | THE DEFERRED SUBMITTAL DOCUMENTS HAVE |
| | BEEN APPROVED BY THE BUILDING OFFICIAL. |
| | |
| | |