| 2018-06-05 15:21:37 | RESIDENTIAL (R3) REVISION, 8TH BUILDING REVIEW |
| | CHECKLIST. |
| | CODE: 2010 FBC. |
| | |
| | ORIGINAL COMMENT: |
| | 1- GAF FLAT ROOF NOA 13-1022.15 SPECIFIED ON DRAWING |
| | S-2 AND SELECTED INSULATED ASSEMBLY ON PAGE 6 OF 16: |
| | PROVIDE SIGNED AND SEALED RAS 117 CALCULATIONS AS |
| | REQUIRED BY GENERAL LIMITATION #7 TO MEET THE DESIGN |
| | PRESSURES OF SEC. R301.1 AT PERIMETER AND CORNER AREAS. |
| | FBC-RESIDENTIAL 2010. |
| | NOTE: SEE GENERAL LIMITATION #7 ON LAST PAGE OF NOA |
| | SUBMITTED FOR RAS 117 CALCULATIONS REQUIREMENTS. |
| | |
| | RESPONSE: |
| | A) INFORMATION IN RAS 117 CALCULATIONS SUBMITTED DON'T |
| | MATCH ENGINEER OF RECORD DRAWINGS SUBMITTED UNDER |
| | REVISION #16061282. ENGINEER SELECTED ASSEMBLY WITH THE |
| | MAXIMUM DESIGN PRESSURES OF -52.5 . ENGINEER DOING THE |
| | RAS 117 CALCULATIONS IS USING ASSEMBLY WITH A MAXIMUM |
| | DESIGN PRESSURE OF -45PSF. IN ADDITION, THE FASTENER |
| | USED FOR THE ASSEMBLY WITH A MAXIMUM DESIGN PRESSURE OF |
| | -45PSF IS DIFFERENT THAN THE ONE SPECIFIED BY THE |
| | ENGINEER DOING THE RAS 117 CALCULATIONS. FASTENERS ON |
| | THE APPROVED ASSEMBLIES CAN NOT BE INTERCHANGED. REVISE |
| | AS REQUIRED TO MATCH. COORDINATE ALL THE INFORMATION TO |
| | AVOID MORE CONFLICTS AND UN-NECESSARY DELAYS. SEC. |
| | R301.1 FBC-RESIDENTIAL 2010. |
| | |
| | B) THIS PROJECT WAS REVIEWED UNDER THE 2010 FBC |
| | RESIDENTIAL NOT 2017. REVISE AS REQUIRED. CHAPTER 553 |
| | F.S. |
| | |
| | IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT |
| | JULIO GOMEZ |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | DEVELOPMENT SERVICES DEPARTMENT |
| | BUILDING DIVISION |
| | (561)805-6712 |
| | [email protected] |
| | |
| | |