| Date |
Text |
| 2016-07-08 08:40:54 | 1ST REVIEW: FBC 2014 MECHANICAL |
| | PERMIT REVISION #16061051 |
| | MASTER PERMIT #15091225 |
| | RESTORATION HARDWARE |
| | 7/6/2016 |
| | |
| | 1) PLEASE PROVIDE A SHEET-BY-SHEET NARRATIVE ITEMIZING |
| | ALL CHANGES MADE TO THE ORIGINAL MECHANICAL PLANS. |
| | PLACE CLOUDS AND DELTA TRIANGLE SYMBOLS ON THE REVISED |
| | PLANS TO HIGHLIGHT ALL CHANGES SUCH AS THE NEW AND |
| | RELOCATED VRV'S AND DUCT WORK, THE NEW EXHAUST FANS, |
| | THE NEW HEAT PUMPS AND OAI UNITS ETC. |
| | |
| | 2) SUBMIT REVISED AC COOLING AND HEATING CALCULATIONS |
| | FOR ALL SYSTEMS INCLUDING THE NEW HEAT PUMPS- 9 & 10, |
| | AND THE DUCTLESS TRASH ROOM AC SYSTEM SECTION C403.2.1 |
| | FBC-14 ENERGY CONSERVATION. |
| | |
| | 3) SUBMIT REVISED ENERGY CALCULATIONS PER SECTION |
| | C401.2 |
| | |
| | 4) ADVISORY: SEPARATE PERMITS ARE REQUIRED FOR THE |
| | KITCHEN EXHAUST HOODS AND FIRE SUPPRESSION SYSTEMS. |
| | PLEASE PLACE A NOTE ON THE PLAN ACCORDINGLY. |
| | |
| | 5) PROVIDE COMPLETE KITCHEN PLANS AND A KITCHEN |
| | EQUIPMENT SCHEDULE. CLARIFY IF WALK-IN COOLERS AND |
| | FREEZERS ARE TO BE INSTALLED AND SHOW THEIR LOCATIONS |
| | ON THE PLANS (SEPARATE PERMITS REQUIRED FOR WALK-INS |
| | AND REFRIGERATION). PLEASE NOTE IF GAS-FIRED COOKING |
| | APPLIANCES ARE TO BE INSTALLED, A GAS PIPING ISOMETRIC |
| | DRAWING AND COMBUSTION AIR CALCULATIONS WILL BE |
| | REQUIRED FOR REVIEW- SEE |
| | SECTIONS 304 & 401 FBC-14 FUEL GAS. |
| | |
| | 6) REFER TO TABLE 403.3 AND PROVIDE EXHAUST VENTILATION |
| | CALCULATIONS FOR THE KITCHEN, THE TRASH ROOM, THE |
| | COOKING OIL STORAGE ROOM, AND THE JANITOR'S CLOSET- SEE |
| | THE NEW EF SCHEDULE ON SHEET M.401. |
| | |
| | 7) PROVIDE AIR BALANCE CALCULATIONS FOR LEVEL-4. |
| | |
| | 8) PROVIDE AN EQUIPMENT SCHEDULE FOR MUA-1. |
| | |
| | 9) SHEET M-101: PROVIDE INDEPENDENT VENTILATION OR AC |
| | SYSTEMS FOR THE ELEVATOR CONTROL ROOMS 194 & 197. |
| | |
| | 10) M-101: INDICATE THE REQUIRED CLEARANCES FOR THE |
| | EF-12 TERMINATION SHOWN AT THE NORTH SIDE- SEE SECTION |
| | 501.3.1, AND PROVIDE A FLORIDA PRODUCT APPROVAL OR |
| | MIAMI-DADE NOA FOR THE EXHAUST LOUVER WITH SHOP DRAWING |
| | APPROVAL BY THE ENGINEER OF RECORD. |
| | |
| | 11) M-101: KEYED NOTE #7 IS MISSING AT THE NORTH SHAFT. |
| | |
| | 12) M-101, 102, 103, & 104: BECAUSE EACH FLOOR HAS A |
| | COMMON PLENUM, DUCT SMOKE DETECTORS ARE REQUIRED IN THE |
| | RETURN AIR SYSTEMS OF ALL VRV'S SHOWN ON THE PLAN- |
| | REFER TO SECTION 606.2.2. PLACE A SD SYMBOL AT EACH VRV |
| | LOCATION. |
| | |
| | 13) M-101, 102, 103, 104: PROVIDE EQUIPMENT SCHEDULES |
| | AND SUBMITTALS FOR THE F/S DAMPERS AND ACCESS DOORS. |
| | SHOW THE DUCT CONNECTIONS TO THE FLOOR GRILLS ON THE |
| | 4TH LEVEL AT THE WINE VAULT AREAS, AND PROVIDE DETAILS |
| | FOR INSTALLATION OF FIRE DAMPERS AT THESE LOCATIONS. |
| | |
| | 14) M-103: THE 24X16 TRANSFER GRILL CONVEYING 1500 CFMS |
| | FROM THE RETAIL AREA IS UNDERSIZED PER SECTION 601.5: |
| | 50 SQUARE INCHES PER 100 CFM IS REQUIRED. |
| | |
| | 15) M-104: PLEASE CLEARLY LABEL THE KITCHEN HOOD |
| | EXHAUST AND MAKE UP AIR DUCTS AT THE HOOD LOCATION. |
| | |
| | 16) M-104: REMOVE THE NOTE INDICATING O/A DUCT |
| | CONNECTION FROM OAI-1 TO VRV-48. VRV-48 HAS O/A SUPPLY |
| | FROM OAI-4. |
| | |
| | 17) M-104: MOTORIZED DAMPERS ARE REQUIRED FOR THE O/A |
| | INTAKE DUCTS FOR THE 4TH FLOOR VRV'S- REFER TO SECTION |
| | C404.2.4.4 FBC-14 ENERGY CONSERVATION. |
| | |
| | 18) M-104: DEMAND CONTROLLED VENTILATION IS REQUIRED |
| | FOR THE DINING AND WINE VAULT AREAS PER SECTION |
| | C403.2.5.1. PROVIDE A SYSTEM THAT MEETS COMPLIANCE. |
| | |
| | 19) M-402: THE OUTSIDE AIR SCHEDULE APPEARS TO SHOW |
| | DEFICIENCIES IN SOME OF THE PROVIDED O/A CFMS WHEN |
| | COMPARED WITH THE CFMS SHOWN AS REQUIRED. |
| | |
| | 20) ADVISORY: COPIED BELOW ARE THE PROVISOS FROM THE |
| | MASTER PERMIT #15091225. THESE WIIL NOW APPLY TO THIS |
| | REVISION PERMIT #16061051. |
| | |
| | IN ADDITION PLEASE NOTE THAT THE ENGINEER'S LETTERS TO |
| | THE BUILDING OFFICIAL REGARDING THE AC STANDS AND |
| | REMOVABLE PLATFORMS THAT WERE SUBMITTED UNDER THE |
| | MASTER PERMIT MUST BE MODIFIED AND ATTACHED TO THIS |
| | REVISION PERMIT APPLICATION. |
| | |
| | MECHANICAL PROVISOS: |
| | PERMIT #15091225 |
| | 2/18/16 |
| | |
| | 1 ) C408.2 FBC-14 ENERGY CONSERVATION: MECHANICAL |
| | SYSTEMS COMMISSIONING AND COMPLETION REQUIREMENTS. |
| | PRIOR TO PASSING THE FINAL MECHANICAL INSPECTION, THE |
| | REGISTERED DESIGN PROFESSIONAL SHALL PROVIDE EVIDENCE |
| | OF MECHANICAL SYSTEMS COMMISSIONING AND COMPLETION IN |
| | ACCORDANCE THE PROVISIONS OF THIS SECTION. |
| | CONSTRUCTION DOCUMENT NOTES SHALL CLEARLY INDICATE |
| | PROVISIONS FOR COMMISSIONING AND COMPLETION |
| | REQUIREMENTS IN ACCORDANCE WITH THIS SECTION AND ARE |
| | PERMITTED TO REFER TO SPECIFICATIONS FOR FURTHER |
| | REQUIREMENTS. COPIES OF ALL DOCUMENTATION SHALL BE |
| | GIVEN TO THE OWNER AND MADE AVAILABLE TO THE CODE |
| | OFFICIAL UPON REQUEST IN ACCORDANCE WITH SECTIONS |
| | C408.2.4 AND C408.2.5. |
| | A) C408.2.1 COMMISSIONING PLAN. |
| | A COMMISSIONING PLAN SHALL BE DEVELOPED BY A REGISTERED |
| | DESIGN PROFESSIONAL OR APPROVED AGENCY AND SHALL |
| | INCLUDE THE FOLLOWING ITEMS: |
| | 1. A NARRATIVE DESCRIPTION OF THE ACTIVITIES THAT WILL |
| | BE ACCOMPLISHED DURING EACH PHASE OF COMMISSIONING, |
| | INCLUDING THE PERSONNEL INTENDED TO ACCOMPLISH EACH OF |
| | THE ACTIVITIES. |
| | 2. A LISTING OF THE SPECIFIC EQUIPMENT, APPLIANCES OR |
| | SYSTEMS TO BE TESTED AND A DESCRIPTION OF THE TESTS TO |
| | BE PERFORMED. |
| | 3. FUNCTIONS TO BE TESTED, INCLUDING, BUT NOT LIMITED |
| | TO CALIBRATIONS AND ECONOMIZER CONTROLS. |
| | 4. CONDITIONS UNDER WHICH THE TEST WILL BE PERFORMED. |
| | AT A MINIMUM, TESTING SHALL AFFIRM WINTER AND SUMMER |
| | DESIGN CONDITIONS AND FULL OUTSIDE AIR CONDITIONS. |
| | 5. MEASURABLE CRITERIA FOR PERFORMANCE. |
| | |
| | B) C408.2.2 AIR DISTRIBUTION SYSTEM TESTING, ADJUSTING |
| | AND BALANCING. |
| | CONSTRUCTION DOCUMENTS SHALL REQUIRE THAT A WRITTEN |
| | BALANCE REPORT BE PROVIDED TO THE OWNER OR THE |
| | DESIGNATED REPRESENTATIVE OF THE BUILDING OWNER FOR |
| | HVAC SYSTEMS SERVING ZONES WITH A TOTAL CONDITIONED |
| | AREA EXCEEDING 5000 SQUARE FEET (465 M2). AIR |
| | DISTRIBUTION SYSTEMS SHALL BE TESTED, ADJUSTED, AND |
| | BALANCED BY A LICENSED ENGINEER OR A COMPANY OR |
| | INDIVIDUAL HOLDING A CURRENT CERTIFICATION FROM A |
| | RECOGNIZED TESTING AND BALANCING AGENCY ORGANIZATION IN |
| | ACCORDANCE WITH GENERALLY ACCEPTED ENGINEERING |
| | STANDARDS. |
| | |
| | C) C408.2.4 PRELIMINARY COMMISSIONING REPORT. |
| | A PRELIMINARY REPORT OF COMMISSIONING TEST PROCEDURES |
| | AND RESULTS SHALL BE COMPLETED AND CERTIFIED BY THE |
| | REGISTERED DESIGN PROFESSIONAL OR APPROVED AGENCY AND |
| | PROVIDED TO THE BUILDING OWNER. THE REPORT SHALL BE |
| | IDENTIFIED AS ?PRELIMINARY COMMISSIONING REPORT? AND |
| | SHALL IDENTIFY: |
| | 1. ITEMIZATION OF DEFICIENCIES FOUND DURING TESTING |
| | REQUIRED BY THIS SECTION THAT HAVE NOT BEEN CORRECTED |
| | AT THE TIME OF REPORT PREPARATION. |
| | 2. DEFERRED TESTS THAT CANNOT BE PERFORMED AT THE TIME |
| | OF REPORT PREPARATION BECAUSE OF CLIMATIC CONDITIONS. |
| | 3. CLIMATIC CONDITIONS REQUIRED FOR PERFORMANCE OF THE |
| | DEFERRED TESTS. |
| | |
| | D) C408.2.4.1 ACCEPTANCE OF REPORT. |
| | BUILDINGS, OR PORTIONS THEREOF, SHALL NOT PASS THE |
| | FINAL MECHANICAL INSPECTION UNTIL SUCH TIME AS THE CODE |
| | OFFICIAL HAS RECEIVED A LETTER OF TRANSMITTAL FROM THE |
| | BUILDING OWNER ACKNOWLEDGING THAT THE BUILDING OWNER |
| | HAS RECEIVED THE PRELIMINARY COMMISSIONING REPORT. |
| | |
| | E) C408.2.4.2 COPY OF REPORT. |
| | THE CODE OFFICIAL SHALL BE PERMITTED TO REQUIRE THAT A |
| | COPY OF THE PRELIMINARY COMMISSIONING REPORT BE MADE |
| | AVAILABLE FOR REVIEW BY THE CODE OFFICIAL. |
| | |
| | F) C408.2.5.4 FINAL COMMISSIONING REPORT. |
| | A REPORT OF TEST PROCEDURES AND RESULTS IDENTIFIED AS |
| | "FINAL COMMISSIONING REPORT" SHALL BE DELIVERED TO THE |
| | BUILDING OWNER AND SHALL INCLUDE: |
| | 1. RESULTS OF FUNCTIONAL PERFORMANCE TESTS. |
| | 2. DISPOSITION OF DEFICIENCIES FOUND DURING TESTING, |
| | INCLUDING DETAILS OF CORRECTIVE MEASURES USED OR |
| | PROPOSED. |
| | 3. FUNCTIONAL PERFORMANCE TEST PROCEDURES USED DURING |
| | THE COMMISSIONING PROCESS INCLUDING MEASURABLE CRITERIA |
| | FOR TEST ACCEPTANCE, PROVIDED HEREIN FOR REPEATABILITY. |
| | EXCEPTION: DEFERRED TESTS WHICH CANNOT BE PERFORMED AT |
| | THE TIME OF REPORT PREPARATION DUE TO CLIMATIC |
| | CONDITIONS. |
| | |
| | 2) DEFERRED SUBMITTAL: 107.3.4.2 DEFERRED SUBMITTALS. |
| | FOR THE PURPOSES OF THIS SECTION, DEFERRED SUBMITTALS |
| | ARE DEFINED AS THOSE PORTIONS OF THE DESIGN THAT ARE |
| | NOT SUBMITTED AT THE TIME OF THE |
| | APPLICATION AND THAT ARE TO BE SUBMITTED TO THE |
| | BUILDING OFFICIAL WITHIN A SPECIFIED PERIOD. DEFERRAL |
| | OF ANY SUBMITTAL ITEMS SHALL HAVE THE PRIOR APPROVAL OF |
| | THE BUILDING OFFICIAL. THE REGISTERED DESIGN |
| | PROFESSIONAL IN RESPONSIBLE CHARGE SHALL LIST THE |
| | DEFERRED SUBMITTALS ON THE CONSTRUCTION DOCUMENTS FOR |
| | REVIEW BY THE BUILDING OFFICIAL. |
| | DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE |
| | SUBMITTED TO THE REGISTERED DESIGN PROFESSIONAL IN |
| | RESPONSIBLE CHARGE WHO SHALL REVIEW THEM AND FORWARD |
| | THEM TO THE BUILDING OFFICIAL WITH A NOTATION |
| | INDICATING THAT THE DEFERRED SUBMITTAL DOCUMENTS HAVE |
| | BEEN REVIEWED AND FOUND TO BE IN GENERAL CONFORMANCE TO |
| | THE DESIGN OF THE BUILDING. THE DEFERRED SUBMITTAL |
| | ITEMS SHALL NOT BE INSTALLED UNTIL THE DEFERRED |
| | SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE BUILDING |
| | OFFICIAL. |
| | A) DEFERRED SUBMITTAL. 2010 FBC 107.3.4.1 PRODUCT |
| | APPROVALS. THOSE PRODUCTS WHICH ARE REGULATED BY THE |
| | DCA RULE 9N-03 SHALL BE REVIEWED AND APPROVED IN |
| | WRITING BY THE DESIGNER OF RECORD PRIOR TO SUBMITTAL |
| | FOR JURISDICTIONAL APPROVAL. |
| | |
| | 3) FINAL APPROVAL OF THE ALTERNATE METHOD OF |
| | CONSTRUCTION OF THE ACCESS PANELS FOR ABOVE CEILING AC |
| | EQUIPMENT MECHANICAL IS CONTINGENT ON A LETTER OF |
| | ACKNOWLEDGEMENT FROM THE RESTORATION HARDWARE FACILITY |
| | MANAGER, AND YOU ALSO INCLUDE THE DISASSEMBLY PROCEDURE |
| | INSTRUCTIONS IN THE O & M MANUAL THAT THE |
| | CONTRACTOR/DESIGN TEAM WILL PROVIDED TO RESTORATION |
| | HARDWARE. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 561-805-6719 |
| | [email protected] |
| | |