| Date |
Text |
| 2016-06-16 15:18:15 | PLUMBING COMMENTS: |
| | |
| | 1. VALUE OF JOB APPEARS LOW. PER WPB AMEND. TO FBC SEC. |
| | 109.3 BUILDING PERMIT VALUATIONS. IF, IN THE OPINION OF |
| | THE BUILDING OFFICIAL, THE CLAIMED VALUATION OF |
| | BUILDING, ALTERATION, STRUCTURE, ELECTRICAL, GAS, |
| | MECHANICAL OR PLUMBING SYSTEMS APPEARS TO BE |
| | UNDERESTIMATED ON THE APPLICATION, THE PERMIT SHALL BE |
| | DENIED, UNLESS THE APPLICANT CAN SHOW |
| | DETAILED, QUANTITY ESTIMATES, AND/OR BONA FIDE SIGNED |
| | CONTRACTS (EXCLUDING LAND VALUE) TO MEET THE |
| | APPROVAL OF THE BUILDING OFFICIAL. FOR PERMITTING |
| | PURPOSES, VALUATION OF BUILDINGS AND SYSTEMS SHALL |
| | BE TOTAL REPLACEMENT VALUE TO INCLUDE STRUCTURAL, |
| | ELECTRIC, PLUMBING, MECHANICAL, INTERIOR FINISH, |
| | RELATIVE SITE WORK, ARCHITECTURAL AND DESIGN FEES, |
| | MARKETING COSTS, OVERHEAD AND PROFIT; EXCLUDING |
| | ONLY LAND VALUE. VALUATION REFERENCES MAY INCLUDE THE |
| | LATEST PUBLISHED DATA OF NATIONAL CONSTRUCTION |
| | COST ANALYSIS SERVICES (MARSHALL-SWIFT, MEANS, ETC.), |
| | AS PUBLISHED BY INTERNATIONAL CODE CONGRESS. |
| | FINAL BUILDING PERMIT VALUATION SHALL BE SET BY THE |
| | BUILDING OFFICIAL. |
| | |
| | 2.SANITARY PIPING ON FLAT PLAN DOES NOT MATCH RISER |
| | DIAGRAM PLEAS CLARIFY. PER WPB AMEND. TO FBC SEC. |
| | 107.2.1 |
| | |
| | 3. HORIZONTAL DRY VENT ON SHOWER NOT ALLOWED. PER FBC |
| | PL SEC. P3104.3- P3104.4 |
| | |
| | 4. SHT. E-1 SHOWS HORIZONTAL DRY VENT NOT ALLOWED. PER |
| | FBC PL SEC. P3104.3- P3104. |
| | |