| 2016-08-05 10:26:30 | 8/5/16 |
| | RE-SUBMITTED PLANS ARE MISSING. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 561-805-6719 |
| | [email protected] |
| | |
| | 2ND REVIEW FBC-2014 MECHANICAL |
| | PERMIT #16051290 |
| | 8/11/16 |
| | |
| | 1) THE ENERGYGAUGESUMMIT SUBMITTAL DOES NOT INCLUDE |
| | COMPLIANCE DATA FOR THE WATER HEATER OR THE CHILLED |
| | WATER PIPING AND INSULATION. |
| | |
| | 2) REFER TO COMMENT #4 FROM THE 1ST REVIEW AND SUBMIT |
| | MANUFACTURER'S SPECIFICATIONS FOR THE CONVECTION OVEN. |
| | PROVIDE EXHAUST AS REQUIRED BY SECTION 507.2.2 AND |
| | TABLE 6-4 ASHRAE 62.1-2010. |
| | |
| | 3) COMMENT #8 FROM THE 1ST REVIEW STILL EXISTS- |
| | ENGINEERED DETAILS FOR INSTALLATION OF OACU-1 & 2 NOT |
| | SHOWN ON THE PLAN, ALTHOUGH STRUCTURAL CALCULATIONS |
| | HAVE BEEN SUBMITTED FOR REVIEW. THE REQUESTED |
| | MIAMI-DADE ROOF STAND NOA NOT SUBMITTED. |
| | |
| | 4) COMMENT #11 FROM THE 1ST REVIEW STILL EXISTS. AS |
| | PREVIOUSLY REQUESTED PROVIDE THE FLEX DUCT SIZES ON THE |
| | PLAN, OR RELOCATE THE AIR DISTRIBUTION AND FLEX DUCT |
| | SCHEDULE TO THE M2.1 PLAN SHEET (MECHANICAL DUCTWORK |
| | PLAN). |
| | |
| | 5) PROVIDE SUBMITTALS FOR ALL PIPING INSULATIONS TO BE |
| | INSTALLED IN THE RETURN PLENUM, AND PLACE A NOTE ON |
| | M2.1 INDICATING THE AREA ABOVE THE CEILING IS A RETURN |
| | PLENUM- SEE SECTION 602. |
| | |
| | 6) M2.1: PROVIDE NOTES OR DETAILS TO INDICATE HOW |
| | SERVICE ACCESS TO ALL ABOVE CEILING MECHANICAL |
| | EQUIPMENT WILL BE PROVIDED- SECTION 306.1. |
| | |
| | 7) M2.1 & A1.0: REFER TO SECTION C403.2.7.3 AND TABLE |
| | C403.2.7.2 FBC-14 ENERGY CONSERVATION, AND SHOW |
| | COMPLIANCE FOR THE REQUIRED CONTINOUS AIR BARRIER |
| | FORMING THE ABOVE CEILING RETURN PLENUM. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 561-805-6719 |