| Date |
Text |
| 2016-05-03 13:57:57 | 1ST REVIEW: FBC 2014 |
| | |
| | GEORGE JOHNSON |
| | PLUMBING PLANS EXAMINER |
| | CITY OF WEST PALM BEACH |
| | 561-805-6711 |
| | [email protected] |
| | |
| | PLUMBING COMMENTS: |
| | |
| | |
| | 1. A TOTAL OF 6 DRINKING FOUNTAINS ARE REQUIRED PER FBC |
| | PL TABLE 403.1. THEY SHALL COMPLY WITH FBC ACC. SEC. |
| | 211.3 MORE THAN MINIMUM NUMBER. |
| | WHERE MORE THAN THE MINIMUM NUMBER OF DRINKING |
| | FOUNTAINS SPECIFIED IN 211.2 ARE PROVIDED, 50 PERCENT |
| | OF THE TOTAL NUMBER OF DRINKING FOUNTAINS PROVIDED |
| | SHALL COMPLY WITH 602.1 THROUGH 602.6, AND 50 PERCENT |
| | OF THE TOTAL NUMBER OF DRINKING FOUNTAINS PROVIDED |
| | SHALL COMPLY WITH 602.7. |
| | |
| | 2. SHT. A050 THE BUILDING CODE DATA HAS A NOTE THAT |
| | STATES GRADES 9 THRU 12 MY UNDERSTANDING WAS THIS |
| | SCHOOL WAS TO BE PREK THRU 4TH GRADE PLEASE CLARIFY PER |
| | WPB AMEND. TO FBC SEC. 107.2.1 |
| | |
| | 3. WHAT GRADES ARE CLASSROOM S 202 AND 203. PER WPB |
| | AMEND. TO FBC 107.2.1 |
| | |
| | 4. SEPARATE FACILITIES ARE REQUIRED FOR MALE AND FEMALE |
| | 4TH GRADE AND ABOVE PER FBC PL 403.2 AND FBC 468.3.5 |
| | |
| | 5. SHT. A400 NOTE # 1 PROVIDE MIN AND MAXIMUM FOR ALL |
| | DIMENSIONS WHEN PROVIDED IN CODE. PER WPB AMEND. TO FBC |
| | 107.2.1 |
| | |
| | 6. GRAB BARS TO BE MEASURED TO THE TOP OF THE GRIPING |
| | SURFACE . PER FBC ACC SEC. 609.4 |
| | |
| | 7. SHT. P-201 THE RISER DIAGRAM IS SHOWING WALL MOUNTED |
| | WATER CLOSETS BUT THE PLUMBING SCHEDULE ON SHT A-400 |
| | HAS FLOOR MOUNTED PLEASE CLARIFY PER WPB AMEND. TO FBC |
| | 107.2.1 |
| | |
| | 8. ALL LAVATORY'S AND SINKS SHALL HAVE TEMPERED WATER. |
| | PER FBC PL SEC. 607.1 AND SHALL COMPLY WITH FBC PL SEC. |
| | 416.5 |
| | |
| | 9. HOT WATER SYSTEM SHALL COMPLY WITH FBC PL SEC. 607.2 |
| | HOT OR TEMPERED WATER SUPPLY TO FIXTURES. |
| | THE DEVELOPED LENGTH OF HOT OR TEMPERED WATER PIPING, |
| | FROM THE SOURCE OF HOT WATER TO THE FIXTURES THAT |
| | REQUIRE HOT OR TEMPERED WATER, SHALL NOT EXCEED 50 FEET |
| | (15 240 MM). RECIRCULATING SYSTEM PIPING AND |
| | HEAT-TRACED PIPING SHALL BE CONSIDERED TO BE SOURCES OF |
| | HOT OR TEMPERED WATER. |
| | |
| | 10. A BACK FLO IS REQUIRED FOR THE 1/2IN. LINE TO |
| | PLANTER AREA PER FBC PL SEC. 608 |
| | |
| | 11. THERMAL EXPANSION CONTROL IS REQUIRED FOR WATER |
| | HEATER PER FBC PL SEC. 607.3 |
| | |
| | 12. PROVIDE MANUFACTURE SPECS FOR SUMP PUMP WITH OIL |
| | MINDER, WATER HEATERS . PER WPB AMEND. TO FBC 107.2.1 |
| | |
| | 13. PROVIDE GREASE CALCULATIONS FROM SCHIER YOU CAN |
| | CONTACT LEE SCHNEEWEISS FOR THOSE AT PH# 800-538-4792 |
| | PER WPB AMEND. TO FBC 107.2.1 |
| | |
| | 14. SAMPLING PORT FROM GREASE SHALL BE MIN OF 6IN. AND |
| | SHALL NOT BE MADE WITH A SANITARY CROSS PER WPB |
| | UTILITIES. |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |