| Plan Review Notes For Permit 16040430 |
| Permit Number |
16040430 |
|
| Review Stop |
G |
| Sequence Number |
1 |
|
| Notes |
| Date |
Text |
| 2016-10-15 06:57:57 | A GAS PLAN HAS NOT BEEN INCLUDED IN THIS SUBMITTAL | | | PACKAGE. A GAS PLAN REVIEW HAS NOT BEEN PERFORMED AT | | | THIS TIME. A GAS PERMIT IS REQUIRED FOR A CONTRACTOR TO | | | PERFORM THE RELATED WORK. PROVIDE COMPLETE PLANS THAT | | | REFLECT THE ENTIRE SCOPE OF GAS WORK TO BE DONE. WPB | | | AMEND. TO FBC SEC.107.2.1. | | | | | | GAS APPLIANCES SHALL BE LISTED AND LABELED PER THE | | | FBC-R, SEC. G2404.3. | | | GAS APPLIANCES SHALL BE LISTED AND LABELED PER FBC-FUEL | | | GAS SEC. 301.3. | | | | | | A SEPARATE PERMIT IS REQUIRED FOR THE GAS INSTALLATION. | | | | | | TIM LARGE | | | CHIEF PLUMBING INSPECTOR | | | PLUMBING PLAN REVIEW | | | 561-805-6692 | | | [email protected] | | | |
|