Plan Review Notes
Plan Review Notes For Permit 16040307
Permit Number 16040307
Review Stop M
Sequence Number 2
Notes
Date Text
2016-05-12 10:32:482ND REVIEW: FBC 2014 MECHANICAL
 PERMIT #16040307
 5/12/16
  
 1) THE RE-SUBMITTED PLANS DO NOT INDICATE THAT COMMENTS
 #1, 2, & 3 HAVE BEEN ADDRESSED COMPLETELY. I AM
 RE-PRINTING THOSE COMMENTS BELOW FOR REVIEW BY THE
 DESIGN PROFESSIONALS.
  
 1) REFER TO SECTIONS 809.1 AND 809.2 FBC-14 EXISTING
 BUILDING AND PROVIDE MINIMUM VENTILATION CALCULATIONS
 FOR ALL ROOMS AND SPACES OF THE NEW OCCUPANCY IN
 ACCORDANCE WITH TABLE 403.3 FBC-14 MECHANICAL. PLEASE
 NOTE THAT PER SECTION 403.3 THE NEW LAB MUST BE
 VENTILATED PER THE RATES INDICATED FOR SCIENCE
 LABORATORIES INCLUDING A .7 CFM PER SQ. FT. EXHAUST
 RATE.
 **PLEASE NOTE THAT IN RESPONSE TO THIS COMMENT ABOVE
 THE DESIGN PROFESSIONAL HAS PROVIDED THE REQUIRED O/A
 CALCULATIONS, HOWEVER THE REQUESTED EXHAUST VENTILATION
 SYSTEM AND CALCULATIONS FOR THE LAB AREA ARE NOT SHOWN
 ON THE PLAN.**
  
 2) REFER TO SECTION 414.1.3 FBC-14 BUILDING AND SHOW
 COMPLIANCE FOR CHEMICAL STORAGE IN THE NEW OCCUPANCY.
 [F] 414.1.3 INFORMATION REQUIRED.
 A REPORT SHALL BE SUBMITTED TO THE BUILDING OFFICIAL
 IDENTIFYING THE MAXIMUM EXPECTED QUANTITIES OF
 HAZARDOUS MATERIALS TO BE STORED, USED IN A CLOSED
 SYSTEM AND USED IN AN OPEN SYSTEM, AND SUBDIVIDED TO
 SEPARATELY ADDRESS HAZARDOUS MATERIAL CLASSIFICATION
 CATEGORIES BASED ON TABLES 307.1(1) AND 307.1(2). THE
 METHODS OF PROTECTION FROM SUCH HAZARDS, INCLUDING BUT
 NOT LIMITED TO CONTROL AREAS, FIRE PROTECTION SYSTEMS
 AND GROUP H OCCUPANCIES SHALL BE INDICATED IN THE
 REPORT AND ON THE CONSTRUCTION DOCUMENTS. THE OPINION
 AND REPORT SHALL BE PREPARED BY A QUALIFIED PERSON,
 FIRM OR CORPORATION APPROVED BY THE BUILDING OFFICIAL
 AND PROVIDED WITHOUT CHARGE TO THE ENFORCING AGENCY.
 FOR BUILDINGS AND STRUCTURES WITH AN OCCUPANCY IN GROUP
 H, SEPARATE FLOOR PLANS SHALL BE SUBMITTED IDENTIFYING
 THE LOCATIONS OF ANTICIPATED CONTENTS AND PROCESSES SO
 AS TO REFLECT THE NATURE OF EACH OCCUPIED PORTION OF
 EVERY BUILDING AND STRUCTURE.
  
 3) PROVIDE MANUFACTURER'S SPECIFCATIONS AND DATA SHEETS
 FOR THE FORE PUMP AND EXHAUST SYSTEM, AND ALL OTHER
 EQUIPMENT THAT REQUIRE EXHAUST SYSTEMS SUCH AS THE
 NIOTROGEN GENERATOR. PROVIDE ON THE PLANS EXHAUST
 SYSTEM DIAGRAMS INDICATING THE TYPES AND SIZES OF
 EXHAUST PIPES AND DUCTS, EXHAUST RUN LENGTHS, AND
 TERMINATION LOCATIONS.
  
 CHRISTOPHER L. COLE
 MECHANICAL PLANS EXAMINER
 561-805-6719
 [email protected]
  