| 2016-04-21 11:45:57 | 2ND REVIEW: FBC 2014 MECHANICAL |
| | PERMIT 16020418 |
| | 4/19/16 |
| | |
| | THE SECOND REVIEW OF THE PROJECT IS BASED ON THE |
| | REVISED PLANS AND NARRATIVE RESPONSES FROM WSP, AND |
| | SOME OF THE1ST REVIEW ISSUES THAT STILL EXIST. |
| | |
| | 1) 1ST REVIEW COMMENT #2: REFER TO SHEET M0.07 & THE |
| | FOLLOWING SHEETS WHERE LOCKER ROOM EXHAUST AT A RATE OF |
| | .5 CFM PER SF. IS MISSING. A) M2.111- MEN'S AND WOMEN'S |
| | LOCKER ROOMS 11102 &11103. B) M2.113- MLB COACHES |
| | LOCKER 11302. C) M2.114- STAFF/COACHES LOCKER 11415 |
| | (SEE SHEET M2.113 AND LABEL THE 16X14 EXHAUST RISER AND |
| | ROOF FAN). M2.117- MLB COACHES LOCKER 11702. |
| | 2) 1ST REVIEW COMMENT #4: M0.07, ERU CALCULATIONS- |
| | REFER TO SECTION 403.2.1 ITEM #4. IT APPEARS BY THE |
| | CALCULATION THAT MORE THAN 10% OF THE EXHAUST AIR FROM |
| | THE LOCKER ROOM AND BATH AREAS IS BEING RECIRCULATED. |
| | PLEASE SUBMIT MANUFACTURER'S PRODUCT DATA SHEETS FOR |
| | THE ERU'S. |
| | 3) 1ST REVIEW COMMENT #2: M0.07: VENTILATION |
| | CALCULATIONS FOR THE DHU'S NOT PROVIDED. PLEASE PROVIDE |
| | THE CALCULATIONS AND MANUFACTURER'S PRODUCT DATA |
| | SHEETS. |
| | 4) 1ST REVIEW COMMENT #5: A) SHEET M0.02: PLACE A NOTE |
| | FOR REQUIRED DUCT SMOKE DETECTORS IN THE ERU SCHEDULE. |
| | B) M0.05: PLACE A NOTE REQUIRING A DUCT SMOKE DETECTOR |
| | FOR AHU-S-4-1. C) M701, NOTE M: PLEASE PROVIDE |
| | ADDITIONAL INFORMATION PERTAINING TO FAN SHUT DOWN. |
| | CLARIFY WHICH FANS WILL SHUT DOWN WHEN A DETECTOR |
| | ACTIVATES- THE UNIT FAN, FANS IN THE FIRE AREA, BOTH |
| | SUPPLY AND EXHAUST FANS IN THE FIRE AREA? D) IT MAY BE |
| | HELPFUL TO PLACE DS SYMBOLS AT THE REQUIRED LOCATIONS |
| | ON THE LAYOUT PLANS. |
| | 5) M2.111, CHEMICAL AND PAINT STORAGE, 1ST REVIEW |
| | COMMENT #6: A) THE LETTER TITLED "LTAS BALLPARK OF THE |
| | PALM BEACHES-HAZMAT STORAGE.." AS NOTED IN THE |
| | NARRATIVE RESPONSE, WAS NOT UPLOADED FOR REVIEW, |
| | THEREFORE A COMPLETE REVIEW CANNOT BE COMPLETED AT THIS |
| | TIME. B) COMMENTS #6C- EXHAUST VENTILATION |
| | CALCULATIONS, AND #6D- MAKE UP AIR SOURCE LOCATION FOR |
| | THE EXHAUST STILL EXIST. |
| | 6) M0.06, COMMENT #16: PLEASE INDICATE WHICH MUA'S |
| | LISTED IN THE SCHEDULE ON M0.05 CORRESPOND WITH THE AIR |
| | BALANCE CALCULATIONS. AS PREVIOUSLY NOTED, THE KITCHEN |
| | HOODS AND ALL ASSOCIATED MAKE-UP AIR AND EXHAUST |
| | SYSTEMS AND FIRE SUPPRESSION WILL BE DONE UNDER |
| | SEPARATE PERMIT. A) PLEASE REVIEW THE MUA SCHEDULE ON |
| | M0.05: THE SECTOR LOCATIONS OF THE MUA'S ON THE |
| | CONCOURSE LEVELS DO NOT APPEAR TO MATCH THE LOCATIONS |
| | SHOWN ON THE PLANS. |
| | 7) M2.112, M2.117, M2.118, M2.119 COMMENT #17: PLEASE |
| | CLARIFY IF THE C, E & G TRANSFERS ARE TRANSFERRING THE |
| | AIR ABOVE OR BELOW THE CORRIDOR CEILINGS ON THESE PLANS |
| | AND OTHER PLANS WITH CORRIDORS. |
| | 8) M2.113, COMMENT #21: COMBUSTION AIR AND LOCATION OF |
| | GIH-N-2-1 NOT SHOWN. |
| | 9) M2.114, COMMENT #22 STILL EXISTS. REFER TO COMMENT |
| | #2 OF THIS REVIEW. |
| | 10) M2.117, COMMENT #25 COMBUSTION AIR CALCULATION AND |
| | SOURCE OF THE AIR. |
| | 11) M2.120, COMMENT #26: FOR CLARIFICATION PLEASE |
| | INDICATE THE TYPE OF EXHAUST DUCTWORK FOR THE TYPE 1 |
| | HOODS. |
| | 12) 1ST REVIEW COMMENT #27: THE REQUESTED WIND LOAD |
| | ENGINEERED INSTALLATION DETAILS FOR THE ROOFTOP |
| | MECHANICAL EQUIPMENT HAS NOT BEEN PROVIDED. REFERENCE |
| | IS MADE TO THE STRUCTURAL DRAWINGS IN THE NARRATIVE, |
| | HOWEVER NO EXACT SHEET IS REFERENCED AND THE REFERENCE |
| | TO ARCHITECTURAL SHEET A7.21 DOES NOT PROVIDE ANY INFO. |
| | PLEASE NOTE THAT THE REQUIRED ENGINEERING CAN BE DONE |
| | AS A DEFERRED SUBMITTAL, HOWEVER REQUIRED MECHANICAL |
| | INSPECTIONS WILL BE ON HOLD UNTIL ENGINEERING HAS BEEN |
| | REVIEWED AND APPROVED. GIVEN THE AMOUNT OF EQUIPMENT TO |
| | BE INSTALLED, IT IS HIGHLY RECOMMENDED THAT ENGINEERING |
| | IS EXPEDITED BY THE DESIGN PROFESSIONALS IN ORDER TO |
| | AVOID ANY DELAYS. |
| | 13) M2.125, COMMENT #28: ENVIRONMENTAL AIR AS DEFINED |
| | IN SECTION 202 DOES NOT INCLUDE AIR EXHAUSTED FROM |
| | STORAGE ROOMS. PLEASE RELOCATE ALL EXHAUST OUTLETS TO |
| | MINIMUM 10' ABOVE ADJOINING GRADE AND REFER TO SECTIONS |
| | 501.3, 501.3.1 (2), AND 501.3.1.1 FOR ADDITIONAL |
| | COMPLIANCES. |
| | 14) 1ST REVIEW COMMENT #31A: IN RESPONSE TO THIS |
| | COMMENT ABOUT REQUIRED EQUIPMENT ACCESS PANELS, THE |
| | NARRATIVE STATES THE CONTRACTOR MAY PROVIDE A CEILING |
| | COORDINATION DRAWING DURING CONSTRUCTION. RESPECTFULLY, |
| | THE BUILDING DIVISION WILL REQUIRE THE DESIGN |
| | PROFESSIONALS TO PROVIDE THOSE DRAWINGS INDICATING |
| | PANEL LOCATIONS, PANEL SIZES, AND CONSTRUCTION DETAILS. |
| | PLEASE NOTE THAT PANELS SHALL BE SIZED LARGE ENOUGH TO |
| | REMOVE AND REPLACE THE EQUIPMENT LOCATED ABOVE THE |
| | CEILINGS- SECTION 306.1. |
| | 15) 1ST REVIEW COMMENT #33A: UL APPROVED FIRE STOPPING |
| | ASSEMBLIES ARE REQUIRED FOR REFRIGERANT PIPING |
| | PENETRATING FIRE-RATED WALLS AND FLOORS. PLEASE REVISE |
| | DETAIL 2/M6.-01. |
| | 16) 1ST REVIEW COMMENT #34: THE REQUESTED DETAILS WERE |
| | NOT PROVIDED, AND REFERENCE TO THE PROJECT |
| | SPECIFICATION BOOK WAS MADE IN THE NARRATIVE, HOWEVER |
| | WE DO NOT REVIEW SPEC BOOKS. PLEASE PROVIDE DETAILS ON |
| | THE PLANS. |
| | 17) 1ST REVIEW COMMENT #35, SHEET M7.02: PLEASE PROVIDE |
| | THE CONTROLS OPERATION FOR THE DHU'S AND A SYMBOL |
| | LEGEND. |
| | 18) SHEET M0.04: THE GAGE OF ALUMINUM DUCTWORK IS |
| | INDICATED TO BE 14 INCHES- PLEASE CLARIFY. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 561-805-6719 |
| | [email protected] |
| | |
| | |