| 2016-03-09 17:41:06 | 1ST REVIEW: FBC 2014 MECHANICAL |
| | PERMIT #16020418 |
| | BALLPARK OF THE PALM BEACHES |
| | 3/8/16 |
| | |
| | 1) THE DESIGN PROFESSIONALS OF RECORD MUST SIGN AND |
| | PROVIDE THEIR PROFESSIONAL REGISTRATION NUMBERS ON PAGE |
| | 3 OF THE ENERGY CONSERVATION FORM SUBMITTAL- SEE |
| | SECTION C103.1.1.1.2 FBC-14 ENERGY CONSERVATION. |
| | 2) DISCREPANCIES BETWEEN THE ENERGY FORM AND THE |
| | MECHANICAL PLANS: |
| | A) THE FORM LISTS ERU-A-2-5 CAPACITY AT 75300 BTUH , |
| | THE AC SCHEDULE ON SHEET M0.02 LISTS THE CAPACITY AT |
| | 92000 BTUH |
| | B) ENERGY FORM LISTS ERU-A-2-6 AT 75300, SCHEDULE- |
| | 92,000. |
| | C) ENERGY FORM LISTS COMPLIANCE DATA FOR AHU-S-2-4 , |
| | HOWEVER THIS SYSTEM IS NOT INCLUDED IN THE EQUIPMENT |
| | SCHEDULES ON THE PLANS. |
| | D) THE SPLIT SYSTEMS, THE 100% O/A SYSTEMS, THE DHU'S, |
| | THE COMPUTER ROOM AC, AND MANY OF THE VRF SYSTEMS ARE |
| | NOT LISTED IN THE ENERGY CONSERVATION FORM. |
| | 3) THE AC COOLING AND HEATING CALCULATIONS MUST BE |
| | SIGNED AND SEALED BY THE DESIGN PROFESSIONAL OF RECORD: |
| | SECTION C403.2.1 FBC-14 ENERGY CONSERVATION. |
| | 4) DISCREPANCIES BETWEEN THE AC CALCULATIONS AND THE |
| | MECHANICAL PLANS: |
| | A) CALCULATED COOLING LOAD FOR ACC-S-4 IS 391 MBH, |
| | HOWEVER THE SCHEDULE ON SHEET M0.04 INDICATES THE |
| | CAPACITY AT 528 MBH. |
| | B) AHU-A-2-1 COOLING LOAD- 925 MBH / SCHEDULE ON SHEET |
| | M0.02 INDICATES CAPACITY AT 836 MBH |
| | C) AHU-N-2-1 LOAD- 695 MBH/ SCHEDULE- 835 MBH. |
| | D) AHU-N-2-2 LOAD- 786 MBH/ SCHEDULE- 732 MBH. |
| | E) AHU- S-3-1 LOAD- 121.9 MBH/SCHEDULE- 197 MBH. |
| | F) AHU-S-3-2 LOAD- 52.8 MBH/ SCHEDULE- 87 MBH. |
| | G) AHU-S-3-4 LOAD- 58 MBH/ SCHEDULE-83. |
| | H) AHU-S-2-4 IS SHOWN IN THE CALCS BUT NOT IN THE |
| | SCHEDULES. |
| | I) AHU-S-3-5 IS SHOWN IN THE SCHEDULE BUT NOT IN THE |
| | CALCS. |
| | J) DHU-N-2-1 LOAD- 81.3 MBH/SCHEDULE- 133 MBH. |
| | K) ERU-A-2-5 LOAD- 245.7 MBH/ SCHEDULE- 92 MBH |
| | L) ERU-A-3-1 LOAD- 131.8 MBH/ SCHEDULE- 92 MBH. |
| | M) ERU-N-2-5 LOAD- 180 MBH/ SCHEDULE- 112.5 MBH. |
| | N) ERU-N-2-6 LOAD- 286.6 MBH/ SCHEDULE- 92 MBH. |
| | O) CLARIFY WHICH SYSTEMS WERE SIZED UNDER THE LOAD |
| | CALCULATIONS PAGES TITLED "MISC" AND "SYSTEM 023": I |
| | CANNOT CONNECT THESE UP WITH THE AC SCHEDULES. |
| | IN REFERENCE TO THE DISCREPANCIES ABOVE PLEASE REFER TO |
| | SECTION C403.2.2 FBC-14 ENERGY CONSERVATION. |
| | |
| | 2) SHEETS M0.03: INDICATE HOW EACH EXHAUST FAN IN THE |
| | SCHEDULE WAS SIZED: PROVIDE EXHAUST VENTILATION |
| | CALCULATIONS IN ACCORDANCE WITH TABLE 403.3 FBC-14 |
| | MECHANICAL, AND TABLE 6-4 ASHRAE 62.1-2010. |
| | 3) M0.04: REFER TO TABLE C403.2.3(10) FBC ENERGY |
| | CONSERVATION AND PROVIDE THE SCOP RATING FOR THE |
| | COMPUTER ROOM AC UNITS. |
| | 4) M2.03 & M2.04: THE PLANS APPEAR TO INDICATE |
| | MECHANICAL SYSTEMS ON THE SUITE AND ROOF LEVELS OF |
| | SECTOR A, HOWEVER THERE ARE NO ENLARGED PLANS FOR THOSE |
| | AREAS IN THE SETS AND THERE ARE ROOF TOP UNITS ON THE |
| | CONCOURSE LEVEL OF SECTOR A- PLEASE CLARIFY. |
| | 5) DUCT SMOKE DETECTORS ARE REQUIRED IN RETURN AIR |
| | SYSTEMS WITH DESIGN CAPACITIES GREATER THAN 2000 CFM |
| | PER SECTION 606.2.1 FBC-14 MECHANICAL. MANY OF THE |
| | PROPOSED AC SYSTEMS FOR THE PROJECT HAVE RETURN AIR |
| | SYSTEMS EXCEEDING THAT THRESHOLD. PLEASE PROVIDE DS |
| | DETECTOR SYMBOLS ON THE PLANS WHERE APPLICABLE, AND |
| | PROVIDE NOTES AND DETAILS CLARIFYING THE SEQUENCE OF |
| | OPERATION FOR THE DETECTORS AND HOW THEY WILL BE |
| | SUPERVISED- SECTION 606.4.1. PLEASE INCLUDE AN |
| | INSTALLATION DETAIL FOR THE DEVICES AND A PRODUCT |
| | SUBMITTAL APPROVED BY THE ENGINEER OF RECORD. |
| | 6) M2.110 AND ALL MECH. PLAN SHEETS: NUMEROUS SYMBOLS |
| | FOR ACCESS PANELS ARE SHOWN FOR THE ABOVE CEILING CAV'S |
| | AND VAV'S. REFER TO SECTION 306.1 AND PROVIDE THE |
| | DIMENSION AND CONSTRUCTION DETAILS FOR THE PANELS. |
| | PLEASE NOTE THE PANELS SHALL BE LARGE ENOUGH TO REMOVE |
| | AND REPLACE THE EQUIPMENT WITHOUT REMOVING PERMANENT |
| | CONSTRUCTION. |
| | 7) M2.111: PROVIDE A KEY NOTE IDENTIFYING WHICH AC |
| | SYSTEM IS PROVIDING THE 20X16 SUPPLY AND RETURN DUCT |
| | DROPS. |
| | 8) M2.111: PROVIDE KEY NOTES IDENTIFYING WHICH EXHAUST |
| | FANS ARE SERVICING THE EXHAUST DUCT RISERS SHOWN IN THE |
| | AREA OF THE CHEMICAL AND PAINT STORAGE ROOMS. |
| | 9) M2.111: CHEMICAL AND PAINT STORAGE ROOMS: A) REFER |
| | TO SECTION 414.1.3 FBC-14 BUILDING: [F] 414.1.3 |
| | INFORMATION REQUIRED. |
| | A REPORT SHALL BE SUBMITTED TO THE BUILDING OFFICIAL |
| | IDENTIFYING THE MAXIMUM EXPECTED QUANTITIES OF |
| | HAZARDOUS MATERIALS TO BE STORED, USED IN A CLOSED |
| | SYSTEM AND USED IN AN OPEN SYSTEM, AND SUBDIVIDED TO |
| | SEPARATELY ADDRESS HAZARDOUS MATERIAL CLASSIFICATION |
| | CATEGORIES BASED ON TABLES 307.1(1) AND 307.1(2). THE |
| | METHODS OF PROTECTION FROM SUCH HAZARDS, INCLUDING BUT |
| | NOT LIMITED TO CONTROL AREAS, FIRE PROTECTION SYSTEMS |
| | AND GROUP H OCCUPANCIES SHALL BE INDICATED IN THE |
| | REPORT AND ON THE CONSTRUCTION DOCUMENTS. THE OPINION |
| | AND REPORT SHALL BE PREPARED BY A QUALIFIED PERSON, |
| | FIRM OR CORPORATION APPROVED BY THE BUILDING OFFICIAL |
| | AND PROVIDED WITHOUT CHARGE TO THE ENFORCING AGENCY. |
| | FOR BUILDINGS AND STRUCTURES WITH AN OCCUPANCY IN GROUP |
| | H, SEPARATE FLOOR PLANS SHALL BE SUBMITTED IDENTIFYING |
| | THE LOCATIONS OF ANTICIPATED CONTENTS AND PROCESSES SO |
| | AS TO REFLECT THE NATURE OF EACH OCCUPIED PORTION OF |
| | EVERY BUILDING AND STRUCTURE. |
| | B) PROVIDE ON THE PLAN AN ITEMIZED LIST OF THE |
| | HAZARDOUS MATERIALS TO BE STORED AND THEIR EXPECTED |
| | QUANTITIES, AND SUBMIT MSDS SHEETS FOR EACH ITEM. C) |
| | PROVIDE EXHAUST VENTILATION CALCULATIONS FOR EACH |
| | EXHAUST SYSTEM, INDICATE THE TYPE OF EXHAUST DUCTWORK |
| | TO BE INSTALLED, AND SEQUENCE OF OPERATION FOR THE |
| | FANS- SEE SECTIONS 502.8.1.1 & 510.1- 510.9. PLEASE |
| | NOTE THAT FIRE SUPPRESSION MAY BE REQUIRED FOR THE |
| | EXHAUST DUCTS. D) REFER TO SECTION 510.5.5 AND INDICATE |
| | HOW MAKE-UP AIR IS BEING PROVIDED FOR THE SYSTEMS AND |
| | THE RATE. PLEASE NOTE THAT THE SOURCE OF THE MAKE-UP |
| | AIR MUST BE DIRECTLY FROM THE OUTDOORS AND TRANSFER |
| | DUCTS FROM ADJOINING ROOMS CANNOT BE USED. |
| | 10) M2.111: FIRE DAMPERS ARE REQUIRED FOR THE 12X12 |
| | LOCKER AND RESTROOM EXHAUST DUCT PENETRATING THE |
| | FIRE-RATED PAINT STORAGE WALLS IN ACCORDANCE WITH |
| | SECTION 607.5.2 FBC-14 MECHANICAL. |
| | 11) M2.111: PROVIDE THROUGH-PENETRATION FIRESTOPPING |
| | SYSTEM DETAILS FOR DUCTS PENETRATING FIRE-RATED WALLS- |
| | SEE SECTION 714.1.1 FBC-14 BUILDING. |
| | 12) M2.111: INDICATE THE REQUIRED CLEARANCES FOR THE |
| | EXHAUST OUTLETS FROM EF S-1-1 AND EF S-1-2: REFER TO |
| | SECTION 501.3.1 FBC-14 MECHANICAL. IDENTIFY THE ROOMS |
| | IN THE MAINTENANCE MEZZANINE AND INDICATE A SOURCE OF |
| | MAKE-UP AIR FOR THE EXHAUST SYSTEMS. |
| | 13) M2.111: PLEASE NOTE THAT ALL EXTERIOR EXHAUST |
| | OUTLET AND AIR INTAKE OPENINGS SHOWN ON THIS PLAN SHEET |
| | AND ALL OTHERS MUST BE PROTECTED IN ACCORDANCE WITH |
| | SECTIONS 1609.1.2 AND 1609.6.4.4.1 FBC-14 BUILDING. |
| | MIAMI-DADE NOA'S AND/OR FLORIDA PRODUCT APPROVALS SHALL |
| | BE SUBMITTED FOR ALL COMPONENTS AND CLADDINGS WITH |
| | REVIEW AND APPROVAL SIGNATURES FROM THE DESIGN |
| | PROFESSIONALS OF RECORD. |
| | |
| | 14) M2.112, LAUNDRY: A) PROVIDE AN EQUIPMENT SCHEDULE |
| | ON THE PLAN FOR THE DRYERS AND SUBMIT MANUFACTURER'S |
| | SPECIFICATIONS REVIEWED AND APPROVED BY THE DESIGN |
| | PROFESSIONAL OF RECORD. B) A COMBUSTION AIR INTAKE DUCT |
| | IS INDICATED- PROVIDE COMBUSTION AIR CALCULATIONS FOR |
| | SIZING THE DUCT. C) EXPAND NUMBERED NOTE #5 TO INDICATE |
| | THE TYPE AND GAGE OF DUCT MATERIAL, THE INTAKE HOOD THE |
| | DUCT IS CONNECTED TO, AND HOW THE DUCT WILL BE |
| | SUPPORTED. D) EXPAND NUMBERED NOTE #1 TO INDICATE |
| | COMPLIANCE WITH SECTION 504.7: COMMERCIAL CLOTHES |
| | DRYERS. |
| | THE INSTALLATION OF DRYER EXHAUST DUCTS SERVING |
| | COMMERCIAL CLOTHES DRYERS SHALL COMPLY WITH THE |
| | APPLIANCE MANUFACTURER'S INSTALLATION INSTRUCTIONS. |
| | EXHAUST FAN MOTORS INSTALLED IN EXHAUST SYSTEMS SHALL |
| | BE LOCATED OUTSIDE OF THE AIRSTREAM. IN MULTIPLE |
| | INSTALLATIONS, THE FAN SHALL OPERATE CONTINUOUSLY OR BE |
| | INTERLOCKED TO OPERATE WHEN ANY INDIVIDUAL UNIT IS |
| | OPERATING. DUCTS SHALL HAVE A MINIMUM CLEARANCE OF 6 |
| | INCHES (152 MM) TO COMBUSTIBLE MATERIALS. CLOTHES DRYER |
| | TRANSITION DUCTS USED TO CONNECT THE APPLIANCE TO THE |
| | EXHAUST DUCT SYSTEM SHALL BE LIMITED TO SINGLE LENGTHS |
| | NOT TO EXCEED 8 FEET (2438 MM) IN LENGTH AND SHALL BE |
| | LISTED AND LABELED FOR THE APPLICATION. TRANSITION |
| | DUCTS SHALL NOT BE CONCEALED WITHIN CONSTRUCTION. E) |
| | SEE TABLE 403.3 AND PROVIDE OUTSIDE AIR CALCULATIONS |
| | FOR THE LAUNDRY AREA. F) SUBMIT SPECS FOR THE ENERVEX |
| | MEC 18 EXHAUST CONTROL SYSTEM REVIEWED AND APPROVED BY |
| | THE DESIGN PROFESSIONAL OF RECORD. |
| | 15) M2.112: PROVIDE NUMBERED KEY NOTES AT THE MAIN |
| | SUPPLY AND RETURN DUCT DROPS TO IDENTIFY WHICH AC AND |
| | ERU SYSTEMS ARE SERVICING THE AREAS. |
| | 16) M2.112: THE KITCHEN HOOD EXHAUST AND FIRE |
| | SUPPRESSION SYSTEMS SHALL BE DONE UNDER A SEPARATE |
| | PERMIT- PLEASE PLACE A NOTE ON THE PLAN ACCORDINGLY AND |
| | PROVIDE AN AIR BALANCE CALCULATION FOR THE AREA. PLEASE |
| | NOTE ALL OTHER KITCHEN HOOD EXHAUST AND FIRE |
| | SUPPRESSION SYSTEMS THROUGHOUT THE FACILITY WILL ALSO |
| | BE DONE UNDER SEPARATE PERMIT WITH AIR BALANCE CALCS |
| | REQUIRED FOR EACH. |
| | 17) M2.112: I AM NOT SEEING ANY OUTSIDE AIR |
| | CALCULATIONS IN THE SCHEDULES FOR THE CORRIDOR |
| | SERVICING THIS SECTOR OR CALCULATIONS FOR ANY OF THE |
| | OTHER SECTOR CORRIDORS- REFER TO TABLE 403.3 AND |
| | PROVIDE THE CALCULATIONS. IT ALSO NEEDS TO BE VERIFIED |
| | THAT THE CORRIDORS IN ALL SECTORS ARE NOT SERVING AS |
| | SUPPLY, RETURN, EXHAUST, RELIEF, OR VENTILATION AIR |
| | DUCTS PER SECTION 601.2. AS NOTED IN SECTION 601.2.1, |
| | THE CEILINGS ABOVE THE CORRIDORS MAY SERVE AS RETURN |
| | AIR PLENUMS. |
| | 18) M2.113: EXPAND NUMBERED NOTE #11 TO INDICATE WHICH |
| | AC SYSTEM |
| | 19) M2.113: PLACE A NUMBERED NOTE ON THE PLAN TO |
| | INDICATE WHERE THE HVAC SYSTEMS FOR THE HYDRO ROOM CAN |
| | BE FOUND. |
| | 20) INDICATE THE REQUIRED CLEARANCE DISTANCE |
| | MEASUREMENTS FOR THE EXHAUST OUTLET FOR EF N-1-3. REFER |
| | TO COMMENT #12 ABOVE FOR MORE INFO. |
| | 21) M2.113: REFER TO COMMENTS # 13 AND 15 FOR THE |
| | LAUNDRY AND KITCHEN AREAS ON THIS PLAN SHEET. |
| | 22) M2.114: PROVIDE AN EXHAUST SYSTEM AND CALCULATIONS |
| | FOR THE STAFF/COACHES LOCKER ROOM- SEE TABLE 403.3. |
| | 23) M2.115 & M2.412: THE 8" ROUND UNDERGROUND EXHAUST |
| | DUCT FROM THE DUGOUT SHALL BE CONSTRUCTED OF PVC HAVING |
| | A MINIMUM PIPE STIFFNESS OF 8 PSI AT 5-PERCENT |
| | DEFLECTION WHEN TESTED IN ACCORDANCE WITH ASTM D2412. |
| | PROVIDE A SUBMITTAL FOR THE DUCT REVIEWED AND APPROVED |
| | BY THE DESIGN PROFESSIONAL OF RECORD. |
| | 24) M2.115: PROVIDE A NUMBERED KEY NOTE IDENTIFYING |
| | WHICH AC SYSTEM THE 24X14 SUPPLY AND 26X20 RETURN DUCT |
| | DROPS ARE CONNECTED TO. |
| | |
| | 25) SHEETS M2.117, 118, & 119- CLUBHOUSE SECTORS H, J, |
| | & K: MANY OF THE COMMENTS PRINTED ABOVE FOR SHEETS |
| | M2.111, 112, 113, 114, & 115 (NATIONAL'S CLUBHOUSE) CAN |
| | APPLIED TO THESE PLAN SHEETS AND SECTORS FOR THE ASTROS |
| | CLUBHOUSE INCLUDING: A) REQUIRED EXHAUST SYSTEM AND |
| | CALCULATIONS FOR THE MLB COACHES LOCKER ROOM (M2.117). |
| | B) LAUNDRY AND KITCHEN AREAS. C) AC SYSTEM |
| | IDENTIFICATIONS AT DUCT DROPS. D) EXHAUST OUTLET AND |
| | AIR INLET CLEARANCE DISTANCES. E) NOA?S AND PRODUCT |
| | APPROVALS. F) OUTSIDE AIR FOR CORRIDORS. |
| | 26) M2.120: EXPAND GENERAL NOTE A TO INDICATE THE GAGE |
| | OF ALUMINUM DUCTWORK. |
| | 27) M2.120, 121, 122, 123, 127, 128, 129, 132, 134, |
| | 135, 136, 137, 138, 139, 145: WIND LOAD ENGINEERING IS |
| | REQUIRED FOR THE ROOF-MOUNTED ERU'S, AHU'S, ACC'S CU'S, |
| | EF'S, MUA'S, DUH'S, GIH'S, AND ALL OTHER ROOF MOUNTED |
| | EQUIPMENT, COMPONENTS, AND DUCTWORK- SECTION 301.15 |
| | PROVIDE STRUCTURAL DETAILS ACCORDINGLY INCLUDING |
| | SECTION CUTS INDICATING CURB HEIGHTS ABOVE THE ROOF |
| | SURFACES, CURB TO STRUCTURE AND UNIT TO CURB |
| | ATTACHMENTS, STAND TO STRUCTURE AND UNIT TO STAND |
| | ATTACHMENTS ETC. IF THE DETAILS ARE FOUND ON |
| | ARCHITECTURAL OR STRUCTURAL SHEETS PLEASE PLACE NOTES |
| | ON THE PLAN INDICATING THE SHEET AND DETAIL NUMBERS. |
| | 28) M2.125: A) PROVIDE EXHAUST OUTLET CLEARANCE |
| | DISTANCES FOR EF-S-2-5 AND PROTECTION FOR THE OPENING. |
| | B) IDENTIFY WITH A NUMBERED NOTE WHICH AC SYSTEM IS |
| | PROVIDING THE O/A DROP. C) SEPARATE PERMITS REQUIRED |
| | FOR THE KITCHEN HOOD GREASE EXHAUST AND FIRE |
| | SUPPRESSION SYSTEMS D) IDENTIFY WITH A NOTE WHICH AC |
| | SYSTEM IS PROVIDING THE 28X20 SA AND RA DROPS. E) |
| | NUMBERED NOTE #5 INDICATES CONDENSATE FROM AC S-2-1 & |
| | S-2-4 DISCHARGING INTO A PLUMBING DRAIN- PLEASE NOTE |
| | THAT THIS CONDENSATE AND ALL OTHER CONDENSATE FROM AC |
| | COOLING COILS IS PROHIBITED TO DRAIN INTO THE WPB |
| | SANITY SEWER SYSTEM PER SEC. 90-126 WPB CODE OF |
| | ORDINANCES. |
| | 29) M2.126: IDENTIFY WITH A NOTE WHICH AC SYSTEM IS |
| | PROVIDING THE 20X12 AND 18X12 SA AND RA DROPS. |
| | 30) M2.129: I AM NOT SEEING MAU S-3-6 IN THE EQUIPMENT |
| | SCHEDULES- PLEASE INDICATE WHERE IT IS LOCATED. PLEASE |
| | NOTE THAT THE VENTILATION CALCULATION AND EQUIPMENT |
| | SCHEDULES DO NOT LIST THIS UNIT. MAU-N-2-6 & MAU-N-2-7 |
| | ARE LISTED IN THE VENTILATION SCHEDULES HOWEVER I CAN?T |
| | FIND THEM ON THE PLANS ON IN THE EQUIPMENT SCHEDULES- |
| | PLEASE CLARIFY AND INDICATE HOW THESE SYSTEMS WERE |
| | SIZED. |
| | 31) M2.132, 134, 135 & M0.07: THE VENTILATION |
| | CALCULATIONS ARE INCORRECT FOR THE SUITES AND OTHER |
| | SPECTATOR AREAS ON THE SUITE LEVEL. REFER TO TABLE |
| | 403.3 FBC-14 MECHANICAL: SPECTATOR AREAS ARE CALCULATED |
| | AT 150 PEOPLE PER 1000 SQ.FT. AND REQUIRE 7.5 CFM PER |
| | PERSON- PLEASE CORRECT. A) PROVIDE ACCESS PANEL SYMBOLS |
| | FOR THE FCU?S AND DIMENSIONED DETAILS FOR INSTALLATION |
| | OF THE PANELS. |
| | 32) M4.01, 402: EXPAND NOTE #3 TO INDICATE WHICH AC |
| | SYSTEM IS PROVIDING THE SA AND RA DROPS TO THE AREAS. |
| | 33) M4.02: PROVIDE AN EQUIPMENT SCHEDULE FOR THE SF |
| | N-1-4, AND DETAILS FOR WIND LOAD ENGINEERING FOR |
| | ANCHORING THE FAN AND DUCTWORK- SECTION 301.15. |
| | 34) M4.02 & 403.: THE REFRIGERANT PIPING DIAGRAMS ARE |
| | INCOMPLETE: PROVIDE DIAGRAMS FOR ALL SYSTEMS AND |
| | INCLUDE PIPE AND PIPE INSULATION SPECIFICATIONS, AND |
| | FIRESTOPPING DETAILS FOR ALL PIPES PENETRATING |
| | FIRE-RATED WALLS OR FLOOR/CEILING ASSEMBLIES |
| | 34) M.602 & 603: PROVIDE SUPPORT AND HANGING DETAILS |
| | FOR INSTALLATION OF THE FCU?S, THE VAV AND CAV BOXES, |
| | THE INLINE FANS, THE G90 AND ALUMINUM DUCTWORK, AND THE |
| | FLEX DUCTS. INCLUDE CONNECTION AND REINFORCEMENT |
| | DETAILS FOR ALL DUCTWORK, AND TYPES AND SIZES OF |
| | HANGERS AND FASTENERS- REFER TO TABLE C403.2.7.2 FBC-14 |
| | ENERGY CONSERVATION AND SMACNA HVAC DUCT CONSTRUCTION |
| | STANDARDS-2005. |
| | |
| | 35) REFER TO SECTION C403.2.4.4 FBC-14 ENERGY |
| | CONSERVATION: PROVIDE SHUTOFF DAMPER CONTROLS FOR |
| | OUTDOOR AIR SUPPLY AND EXHAUST DUCTS WHERE REQUIRED. |
| | 36) REFER TO SECTION C408: COMMISSIONING OF THE |
| | MECHANICAL AND ELECTRICAL POWER AND LIGHTING SYSTEMS IS |
| | REQUIRED. PLEASE REVIEW ALL SUB-SECTIONS UNDER C408 AND |
| | SUBMIT A COMMISSIONING PLAN FOR REVIEW. |
| | 37) PROVIDE A SUBMITTAL PACKAGE FOR ALL MECHANICAL |
| | EQUIPMENT AND COMPONENTS INCLUDING BUT NOT LIMITED TO |
| | THE AC SYSTEMS, EXHAUST AND SUPPLY FANS, ROOF TOP CURBS |
| | AND STANDS, EXHAUST OUTLET AND AIR INLET LOUVERS, DUCT |
| | SMOKE DETECTORS, FIRE DAMPERS, THE DRYERS, ETC. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 561-805-6719 |
| | [email protected] |
| | |
| | |