Plan Review Notes
Plan Review Notes For Permit 16020194
Permit Number 16020194
Review Stop M
Sequence Number 3
Notes
Date Text
2016-08-26 09:57:253RD REVIEW FBC-2014 MECHANICAL
 PERMIT #16020194
 8/26/16
  
 1) THE REVISED AC COOLING AND HEATING CALCULATIONS ARE
 MISSING THE A1, A1 COR, A2, AND A3 SYSTEMS.
  
 2) THE ENERGY/GAUGE COMPLIANCE SUBMITTAL IS MISSING THE
 DATA FOR THE MITSUBISHI SYSTEMS.
  
 3) COMMENT #1 FROM THE PREVIOUS REVIEW HAS NOT
 COMPLETELY ADDRESSED. A) PROVIDE A REVISED FAN SCHEDULE
 ON SHEET M-5.2 THAT SHOWS THE NEW, LARGER CAPACITY
 GARAGE EXHAUST FANS. B) SHEETS M-2.1A & M-2.2A: THE
 6000 EXHAUST CFM'S SHOWN AT THE SOUTH SIDE OF THE
 GARAGE FOR LEVELS 1 & 2 DO NOT MATCH WITH THE EXHAUST
 CFMS SHOWN ON THE RISER DRAWING ON SHEET M-6.2.
  
 4) COMMENT #15 FROM THE PREVIOUS REVIEW HAS NOT BEEN
 COMPLETELY ADDRESSED. A) DEMAND CONTROLLED VENTILATION
 IS REQUIRED FOR THE THEATRE- PLEASE PLACE A NOTE ON THE
 PLAN AND SHOW THE LOCATIONS OF CO2 SENSORS. B) SUBMIT
 MANUFACTURER'S SPECIFICATIONS FOR THE SENSORS REVIEWED
 WITH SIGNATURE BY THE EOR. THE SPECS SHALL PROVIDE
 INSTRUCTIONS FOR INSTALLATION OF THE SENSORS
  
 INCLUDING PLACEMENT AND SPACING OF THE DEVICES.
  
 CHRISTOPHER L. COLE
 MECHANICAL PLANS EXAMINER
 561-805-6719
 [email protected]
  