| 2016-10-27 17:22:28 | SOME PLUMBING SHEETS WERE PREPARED BY ONE ENGINEER AND |
| | DIGITALLY SIGNED AND SEALED BY A DIFFERENT ENGINEER. |
| | |
| | |
| 2016-10-27 15:15:52 | DIGITAL SIGNATURES FOR MECHANICAL PLANS AND |
| | CALCULATIONS VERIFIED/CC |
| | 10/27/2016 |
| 2016-10-21 14:38:48 | 10/21/16 3RD BUILDING REVIEW, SIGNATURE / SEAL |
| | VERIFICATION |
| | |
| | THE FOLLOWING HAVE BEEN REVIEWED AND APPROVED: |
| | |
| | 9/9/16, 6/7/16 VERIFIED A & S SHEET DIGITAL SIGNATURES, |
| | 2ND & 3RD REVIEW & BUILDING SUBMITTALS (SH) |
| | |
| | 9/9/16 DIGITAL SIGNATURE ON STRUCTURAL CALCS VERIFIED |
| | ORIGINAL SIGNED & SEALED SOILS REPORT WAS PROVIDED FOR |
| | PERMIT 16020199 (VIBROFLOTATION PERMIT) |
| | DIGITAL SIGNATURES ON EACH SHEET (S, LS, A, GA) OK |
| | ORIGINAL SURVEY NOT REQUIRED AS IT IS NOW SUPERSEDED BY |
| | REPLAT RECORDED BOOK 122, PAGES 16-17. |
| | |
| | |
| 2016-06-09 12:52:03 | 6/9/16 |
| | CCOLE |
| | |
| | EACH UPLOADED WIND LOAD ENGINEERING DOCUMENT FOR THE |
| | CARRIER, MITSUBISHI, FIRST COMPANY UNITS, AND FOR THE |
| | ROOF STANDS AND WALL BRACKETS HAVE SCANNED ENGINEER'S |
| | SEALS- EACH MUST BE DIGITALLY SIGNED AND SEALED BY THE |
| | ENGINEER WHO PREPARED THEM. THE DOCUMENTS MUST ALSO BE |
| | APPROVED WITH SIGNATURE BY THE ENGINEER OF RECORD. |
| 2016-06-07 07:23:53 | 9/9/2016 FAILED |
| | |
| | 1. ENERGY CALCS AND SOME MECHANICAL PAGES (FOR |
| | EXAMPLES, SEE SHEETS M2.6B, M2.3B, CHECK ALL) ARE |
| | PREPARED BY ALEJANDRO FRANYIE, BUT IS DIGITALLY SIGNED |
| | AND SEALED BY VIVIANA FRANYIE. |
| | 2. SEE ALSO OTHER REVIEWER('S) LIST(S). |
| | |
| | THE FOLLOWING HAVE BEEN REVIEWED AND APPROVED: |
| | |
| | 9/9/16, 6/7/16 VERIFIED A & S SHEET DIGITAL SIGNATURES, |
| | 2ND SUBMITTAL & 3RD SUBMITTALS (SH) |
| | |
| | 9/9/16 DIGITAL SIGNATURE ON STRUCTURAL CALCS VERIFIED |
| | ORIGINAL SIGNED & SEALED SOILS REPORT WAS PROVIDED FOR |
| | PERMIT 16020199 (VIBROFLOTATION PERMIT) |
| | DIGITAL SIGNATURES ON EACH SHEET (S, LS, A, GA) OK |
| | ORIGINAL SURVEY NOT REQUIRED AS IT IS NOW SUPERSEDED BY |
| | REPLAT RECORDED BOOK 122, PAGES 16-17. |
| | |
| | 3/16 ALL TITLE BLOCKS CHECKED, LICENSES VERIFIED |
| | |
| | |