| Date |
Text |
| 2016-06-15 15:19:18 | NEW SINGLE FAMILY RESIDENCE (R3) THIRD MECHANICAL |
| | REVIEW CHECKLIST. |
| | CODE: FBC 5TH EDITION (2014). |
| | |
| | ORIGINAL COMMENT: |
| | 1- EQUIPMENT SIZING CALCULATIONS NEED TO COMPLY WITH |
| | THE EQUIPMENT SIZING SECTION R403.6.1 FBC-ENERGY |
| | CONSERVATION, 5TH EDITION (2014). CALCULATIONS NEED TO |
| | BE DONE USING AN APPROVED SOFTWARE (FOR EXAMPLE ELITE, |
| | WRIGHTSOFT, ETC). NEED CALCULATIONS BASED ON THE |
| | BUILDING LOADS FOR THE DIRECTIONAL ORIENTATION OF THE |
| | BUILDING. AND, NEED TO BE DONE BASED ON THE INTERIOR |
| | DESIGN DESIGN TEMPERATURE REQUIRED BY SEC. R302.1 OF |
| | FBC-ENERGY CONSERVATION. REVISE AS REQUIRED. |
| | CALCULATIONS SUBMITTED ARE NOT DONE WITH AN APPROVED |
| | SOFTWARE AND THE INTERIOR DESIGN TEMPERATURE DOESN'T |
| | COMPLY WITH SEC. R302.1. |
| | |
| | RESPONSE: |
| | EQUIPMENT SIZING CALCULATIONS SUBMITTED: |
| | A) CALCULATIONS NEED TO BE DONE BASE ON THE ACTUAL |
| | ORIENTATION OF THE BUILDING AS REQUIRED BY SEC. |
| | R403.6.1 FBC-ENERGY CONSERVATION, 5TH EDITION (2014). |
| | CALCULATIONS SUBMITTED DON'T MATCH ACTUAL BUILDING |
| | ORIENTATION. REVISE AS REQUIRED. NOTE: COORDINATE WITH |
| | THE ENERGY CALCULATIONS ONCE THE ENERGY CALCULATIONS |
| | ARE REVISED. SEE BUILDING COMMENTS FOR ENERGY |
| | CALCULATIONS SUBMITTED. |
| | |
| | B) THE EQUIPMENT SIZE FOR UNITS 1 AND 2 IS OVERSIZED. |
| | ACCORDING TO SEC. R403.6.1.1 FBC-ENERGY CONSERVATION, |
| | THE EQUIPMENT CAN NOT BE MORE THAN 1.15 TIMES GREATER |
| | THAN THE TOTAL CALCULATED LOAD OR CLOSEST AVAILABLE |
| | SIZE. TOTAL COOLING LOADS ARE 27531 BTU'S AND 27192 |
| | BTU'S. THE CLOSES SIZE IS 2-1/2 TON NOT 3 TON. REVISE |
| | AS REQUIRED INCLUDING SHEET M.1. |
| | |
| | |
| | ORIGINAL COMMENT: |
| | 2- MECHANICAL PLAN M.1 SUBMITTED; |
| | A) SIZE OF "TRANSFER DUCTS" SHOWN ON THE SECOND FLOOR |
| | BEDROOMS DON'T COMPLY WITH THE BALANCED RETURN AIR SEC. |
| | M1602.4 OF FBC-RESIDENTIAL, 5TH EDITION (2014). SHOW |
| | COMPLIANCE. (REPEAT COMMENT). THE TRANSFER DUCT SIZE |
| | WAS NOT REVISED. IN ADDITION THE CFM'S SHOWN ON PLANS |
| | DON'T MATCH CFM SHOWN ON THE EQUIPMENT SIZING |
| | CALCULATIONS. REVISE AS REQUIRED TO MATCH. |
| | NOTE: INFORMATION WAS CHANGED ON THE FIRST FLOOR. THE |
| | TRANSFER DUCTS NEED TO COMPLY WITH THE BALANCED RETURN |
| | AIR SEC. M1602.4. ALSO, COORDINATE CFM'S WITH EQUIPMENT |
| | SIZING CALCULATIONS. REVISE AS REQUIRED. |
| | |
| | RESPONSE: |
| | SIZE OF MASTER BEDROOM #2 TRANSFER DUCT NEEDS TO BE |
| | REVISED TO COMPLY. |
| | |
| | ***PLEASE PROVIDE RESPONSE LETTER ADDRESSING EACH |
| | COMMENT TO EXPEDITE THE REVIEW PROCESS. |
| | ***PLEASE REMOVE AND REPLACE ANY REVISED DRAWING. DON'T |
| | STAPLE OLD COPY TO THE PLANS. SUBMIT OLD COPIES FOR |
| | REFERENCE. |
| | |
| | IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT |
| | JULIO GOMEZ |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | DEVELOPMENT SERVICES DEPARTMENT |
| | (561)805-6712 |
| | [email protected] |