| Date |
Text |
| 2017-02-07 12:13:35 | MECHANICAL PROVISOS: |
| | 2/7/17 |
| | |
| | 1) A REVISION TO THE APPROVED PLANS IS REQUIRED TO SHOW |
| | THE MISSING FIRE OR FIRE/SMOKE DAMPERS AT THE LOCATIONS |
| | LISTED BELOW. |
| | |
| | * M2.0P2 NORTH CORE: 4X4 O/A DUCT PENETRATION RESIDENT |
| | STORAGE WALL |
| | * M2.0P2 EAST: 6X4 O/A DUCT PENETRATING STORAGE ROOM |
| | WALL AT EAST SIDE OF BUILDING. |
| | * M2.0P1: 4X4 O/A DUCT AT WATER FEATURE WALL |
| | * M2.0P1: 4X4 O/A DUCT AT MAINTENANCE WALL |
| | * M2.0P1: 6X6 O/A DUCT AT RESIDENT STORAGE |
| | * M2.0P1: 4X4 O/A DUCT AT CORRIDOR |
| | * M2.0P1: 6' FLEX DUCT AT STORAGE P116. |
| | * M2.0P1: 12X6 DUCT PENETRATING WALLS AT MEP/CAR |
| | WASH/DOG SPA. |
| | * M2.0P1: 12X12 EXHAUST DUCT AT DOG SPA. |
| | * M2.01: INTAKE OPENING AND EXHAUST OUTLET AT GENERATOR |
| | ROOM. |
| | * M2.01: EXHAUST DUCT AT MANICURE ROOM WALL. |
| | * M2.01: 12X6 O/A DUCT AT CORRIDOR |
| | * M2.02: SOUTH CORE- 10X10 DUCT AT JANITOR/FIRE VEST. & |
| | FIRE VEST./ELEV. LOBBY. |
| | * M2.02: 26X12 DUCT AT MEP CLOSET. |
| | * M2.02 18X10 DUCT AT YOGA ROOM.. |
| | * M2.05: SOUTH CORE- 18X10 DUCT PENETRATING THE SHAFT |
| | NEAR STAIR #3. |
| | * M2.05: NORTH CORE- TWO DUCTS SHOWN IN STAIR #1 |
| | ENCLOSURE PENETRATING STAIR ENCLOSURE/UTILITY ROOM |
| | WALL. |
| | * M2.17, 18, 20, 21, 22: 18X10 DUCT ATR SHAFT |
| | PENETRATION. |
| | * M2.22: SOUTH CORE- 50X16 O/A DUCT AND 14X6 SUPPLY |
| | DUCT AT SHAFT. |
| | * M2.22 NORTH CORE- 22X6 O/A DUCT AT SHAFT PENETRATION. |
| | * M2.23: NORTH CORE- 22X6 O/A DUCT AT SHAFT |
| | PENETRATION. |
| | * M2.24: SOUTH CORE- EXHAUST DUCTS PENETRATING SHAFTS. |
| | * M2.25: SOUTH CORE- 18X10 AT SHAFT. |
| | * M2.26: SOUTH CORE: EXHAUST DUCT KEF #3 AT SHAFT. |
| | * M2.26: NORTH CORE: OA-1 DUCT AT SHAFTI |
| | |
| | 2) ACCESS FOR MAINTENANCE AND REPLACEMENT OF ALL |
| | MECHANICAL EQUIPMENT SHALL BE PROVIDED. SUBMIT |
| | STRUCTURAL DETAILS FOR PANELS WHERE NECESSARY. |
| | |
| | 3) THE FOLLOWING LIST OF DEFERRED SUBMITTALS SHALL BE |
| | SUBMITTED PRIOR TO FIELD INSPECTION REQUESTS: |
| | |
| | A) STRUCTURAL DETAILS AND WIND LOAD ENGINEERING FOR ALL |
| | ROOFTOP AND EXTERIOR MECHANICAL EQUIPMENT AND |
| | COMPONENTS INCLUDING THE COOLING TOWER, THE DOA UNITS, |
| | THE FANS AND FAN CURBS, LOUVERS, ETC. |
| | |
| | B) STRUCTURAL DRAWINGS AND DETAILS FOR THE COOLING |
| | TOWER ACCESS PLATFORM AND LADDER. |
| | |
| | C) MANUFACTURER'S SPECIFICATIONS FOR: |
| | COOLING TOWER |
| | GENERATOR |
| | SMOKE CONTROL AND PRESSURIZATION FANS |
| | BOILER AND BOILER VENTING |
| | HEAT EXHANGERS |
| | FLAMEBAR DUCT |
| | FSD & FD DAMPERS |
| | O/A MOTORIZED DAMPERS |
| | CO AND NO2 DETECTORS |
| | FIRESTOPPING |
| | ACCESS PANELS FOR ABOVE CEILNG HP'S |
| | CHILLED WATER PIPING INSULATION |
| | |
| | D) FLORIDA PRODUCT APPROVALS AND/OR MIAMI-DADE NOA'S |
| | FOR LOUVERS AND ROOF STANDS |
| | |
| | 1) DEFERRED SUBMITTAL: 107.3.4.2 DEFERRED SUBMITTALS. |
| | FOR THE PURPOSES OF THIS SECTION, DEFERRED SUBMITTALS |
| | ARE DEFINED AS THOSE PORTIONS OF THE DESIGN THAT ARE |
| | NOT SUBMITTED AT THE TIME OF THE |
| | APPLICATION AND THAT ARE TO BE SUBMITTED TO THE |
| | BUILDING OFFICIAL WITHIN A SPECIFIED PERIOD. DEFERRAL |
| | OF ANY SUBMITTAL ITEMS SHALL HAVE THE PRIOR APPROVAL OF |
| | THE BUILDING OFFICIAL. THE REGISTERED DESIGN |
| | PROFESSIONAL IN RESPONSIBLE CHARGE SHALL LIST THE |
| | DEFERRED SUBMITTALS ON THE CONSTRUCTION DOCUMENTS FOR |
| | REVIEW BY THE BUILDING OFFICIAL. |
| | |
| | DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE |
| | SUBMITTED TO THE REGISTERED DESIGN PROFESSIONAL IN |
| | RESPONSIBLE CHARGE WHO SHALL REVIEW THEM AND FORWARD |
| | THEM TO THE BUILDING OFFICIAL WITH A NOTATION |
| | INDICATING THAT THE DEFERRED SUBMITTAL DOCUMENTS HAVE |
| | BEEN REVIEWED AND FOUND TO BE IN GENERAL CONFORMANCE TO |
| | THE DESIGN OF THE BUILDING. THE DEFERRED SUBMITTAL |
| | ITEMS SHALL NOT BE INSTALLED UNTIL THE DEFERRED |
| | SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE BUILDING |
| | OFFICIAL. |
| | 2) DEFERRED SUBMITTAL. 2010 FBC 107.3.4.1 PRODUCT |
| | APPROVALS. THOSE PRODUCTS WHICH ARE REGULATED BY THE |
| | DCA RULE 9N-03 SHALL BE REVIEWED AND APPROVED IN |
| | WRITING BY THE DESIGNER OF RECORD PRIOR TO SUBMITTAL |
| | FOR JURISDICTIONAL APPROVAL. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 561-805-6719 |
| | [email protected] |
| | |
| | |
| | |
| | |