| 2015-12-01 11:31:38 | 1ST REVIEW 2014 MECHANICAL |
| | PERMIT #15110873 |
| | 12/1/15 |
| | |
| | 1) THE SUBMITTED SPRAY BOOTH PLAN SHEET 1-1 SHALL BEAR |
| | THE TITLE BLOCK, AND SIGNATURE AND SEAL OF A FLORIDA |
| | LICENSED ENGINEER PER SECTION 105.3.1.2 WPB AMENDMENTS |
| | TO THE FLORIDA BUILDING CODE- 2014. |
| | 2) REFER TO SECTION 107.2 WPB AMENDMENTS AND SUBMIT |
| | LEGIBLE DIMENSIONED DRAWINGS AT MINIMUM 1/8" SCALE THAT |
| | DEPICT THE ENTIRE PROPOSED COMPLETE PROJECT INCLUDING: |
| | A) THE REQUIRED MINIMUM 3' SEPARATION DISTANCE FROM THE |
| | BOOTH TO A 1HR. FIRE RATED WALL- SECTION 5.3 NFPA 33. |
| | B) A POSITIVE MECHANICAL VENTILATION PROVIDING A |
| | MINIMUM OF SIX COMPLETE AIR CHANGES PER HOUR- SECTION |
| | 502.7.2 FBC-14 MECHANICAL. CLARIFY HOW MAKE-UP AIR IS |
| | BEING PROVIDED AND SHOW CALCULATIONS. |
| | C) NOTES AND DETAILS INDICATING HOW THE VENTILATION |
| | SYSTEM WILL BE KEPT IN OPERATION WHILE SPRAYING |
| | OPERATIONS ARE BEING CONDUCTED AND FOR SUFFICIENT TIME |
| | THEREAFTER. PLEASE NOTE THAT SPRAYING EQUIPMENT SHALL |
| | BE INTERLOCKED WITH THE VENTILATION SYSTEM- INDICATE |
| | HOW THIS IS BEING ACCOMPLISHED- SECTION 502.7.3.1 |
| | D) AN AIR VELOCITY CALCULATION OVER THE OPEN FACE OF |
| | THE BOOTH, OR BOOTH CROSS SECTION - SECTION 502.7.3.3. |
| | E) AN EQUIPMENT SCHEDULE FOR THE EXHAUST FAN AND DETAIL |
| | SHOWING THE LOCATION OF THE FAN IN RELATION TO THE |
| | EXHAUST DUCT- SECTION 502.7.3.6 |
| | F) A CROSS SECTION DRAWING OF THE EXHAUST DUCT FROM THE |
| | BOOTH TO THE TERMINATION CAP ABOVE THE ROOF THAT |
| | INDICATES THE DUCT DIMENSIONS AND GAUGE OF STEEL, THE |
| | HEIGHT OF THE DUCT TERMINATION CAP ABOVE THE ROOF |
| | SURFACE, AND HOW THE DUCT WILL BE SUPPORTED BELOW AND |
| | ABOVE THE ROOF. PLEASE NOTE THAT SITE SPECIFIC WIND |
| | LOAD ENGINEERING IS REQUIRED FOR ALL ROOFTOP MECHANICAL |
| | EQUIPMENT- SECTION 301.15. |
| | G) A ROOF DRAWING SHOW THE CLEARANCE DISTANCES FROM THE |
| | EXHAUST TERMINATION CAP AS OUTLINED IN SECTION 501.3.1 |
| | ITEM #1) FOR DUCTS CONVEYING EXPLOSIVE OR FLAMMABLE |
| | VAPORS, FUMES OR DUSTS: 30 FEET (9144 MM) FROM PROPERTY |
| | LINES; 10 FEET (3048 MM) FROM OPERABLE OPENINGS INTO |
| | BUILDINGS; 6 FEET (1829 MM) FROM EXTERIOR WALLS AND |
| | ROOFS; 30 FEET (9144 MM) FROM COMBUSTIBLE WALLS AND |
| | OPERABLE OPENINGS INTO BUILDINGS WHICH ARE IN THE |
| | DIRECTION OF THE EXHAUST DISCHARGE; 10 FEET (3048 MM) |
| | ABOVE ADJOINING GRADE. |
| | 3) PROVIDE EQUIPMENT SCHEDULES FOR THE PAINT SPRAYERS |
| | AND COMPRESSOR, AND A PIPING PLAN THAT INDICATES THE |
| | TYPE OF PIPING, THE PIPING RUNS, AND HOW THE PIPE WILL |
| | BE SUPPORTED- SECTION 8.4 NFPA 33 |
| | 4) SHOW ON THE PLAN WHERE PAINT OR FINISH MATERIALS |
| | WILL BE STORED, THE QUANTITIES BEING STORED, AND HOW IT |
| | IS TO BE STORED- REFER TO SECTION 8.1 NFPA 33, |
| | 5) CLARIFY IF A MIXING ROOM OR AREA WILL BE PROVIDED |
| | AND HOW IT WILL BE VENTILATED- SECTION 8.3 NFPA 33. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 561-805-6719 |
| | [email protected] |
| | |
| | |