| 2016-02-25 14:40:29 | 2ND ELECTRICAL REVIEW NOTES FOR REVISION #:15110823 |
| | REVIEWED FOR COMPLIANCE WITH: |
| | FBC 2010 EDITION |
| | NFPA 70 2008 (NEC) |
| | |
| | CORRECTIONS REQUIRED: |
| | SHEET E001 & E002 |
| | 1. DEFINE ON THIS RISER DIAGRAM THE AREA OR AREAS |
| | AFFECTED BY THIS PROJECT. |
| | SHEET E008 |
| | 1. YOU SUBMITTED A FIXTURE SCHEDULE THAT IS PROBABLY |
| | FOR THE MASTER PERMIT BUT HAVE NOT SUBMITTED ANY |
| | LIGHTING PLANS OR DESIGN FOR THIS SCOPE OF WORK. |
| | SHEET E201 & E213 |
| | 1. MISSING GROUNDING DETAIL 11 ON SHEET E701. |
| | 2. MISSING TRANSFORMER SUPPORT DETAIL 3 ON SHEET E701. |
| | 3. DEFINE THE AREA OF WORK ON THE FLOOR PLANS. |
| | 4. YOU NEED TO SUBMIT A CODE COMPLIANT LIGHTING DESIGN |
| | FOR THE AREA IN QUESTION. THIS SHALL TAKE INTO |
| | CONSIDERATION ALL THE REQUIREMENTS OF THE FBC-ENERGY |
| | CONSERVATION. |
| | 5. YOU SHALL INCLUDE THE REQUIRED EMERGENCY AND EXIT |
| | LIGHTS FOR THE WORK AREA. |
| | SHEET E602 & E603 |
| | 1. ONCE THE SCOPE OF WORK OR AREA OF WORK IS DEFINED |
| | AND THE LIGHTING PLAN PROVIDED THE PANEL AND CIRCUIT |
| | DESIGNATIONS CAN BE REVIEWED. |
| | SHEET G000 |
| | 1. CORRECT THE DRAWING SCHEDULE TO INCLUDE ALL OF AND |
| | ONLY THOSE SHEETS PERTINENT TO THIS PROJECT. |
| | |
| | WHEN RESUBMITTING, FOR A QUICKER RETURN ON YOUR |
| | RE-SUBMITTAL, PLEASE PROVIDE A RESPONSE LETTER |
| | (NARRATIVE) ADDRESSING EACH ITEM AND THE PAGE NUMBER |
| | WHERE THE CORRECTIONS APPEAR ALONG WITH THE STANDARD |
| | CITY RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT |
| | CORRECTED PAGES INTO THE SUBMITTAL PACKAGE. MARK VOID |
| | AND LEAVE THE PREVIOUSLY REVIEWED SHEETS FOR |
| | COMPARATIVE REVIEW. CLOUDING THE CHANGES WILL BE |
| | GREATLY APPRECIATED. |
| | |
| | IF YOU HAVE FURTHER QUESTIONS, PLEASE DON?T HESITATE TO |
| | CONTACT ME DIRECTLY. |
| | |
| | THANK YOU, |
| | MIKE ALBARRAN |
| | ELECTRICAL PLANS EXAMINER |
| | PH: 561-805-6746 |