Plan Review Notes
Plan Review Notes For Permit 15110708
Permit Number 15110708
Review Stop M
Sequence Number 1
Notes
Date Text
2015-12-23 15:09:321ST REVIEW: FBC 2014 5TH ED. RESIDENTIAL
  
 1) NOTE 3 ON SHEET M-2 CITES THE 2010FBC AS THE CODE IN
 EFFECT. PLEASE REVISE TO THE CODE REFERENCED ABOVE.
  
 2) PROVIDE AN ENERGY SUBMITTAL PER THE BELOW:
  
 FBCE-R101.5.1.1 BUILDING THERMAL ENVELOPE ALTERNATIVE.
 AN ACCURATELY COMPLETED RESIDENTIAL BUILDING FORM R402
 SHALL BE SUBMITTED TO THE BUILDING OFFICIAL TO
 DEMONSTRATE CODE COMPLIANCE BY THIS METHOD.
  
 FBCE-101.5.1.1.2 SIMULATED PERFORMANCE ALTERNATIVE.
 AN ACCURATELY COMPLETED RESIDENTIAL BUILDING FORM R405
 (GENERATED BY COMMISSION APPROVED SOFTWARE) SHALL BE
 SUBMITTED TO THE BUILDING OFFICIAL TO DEMONSTRATE CODE
 COMPLIANCE BY SECTION 405.
  
 3) PROVIDE AN EQUIPMENT SIZING CALCULATION:
  
 FBCER403.6.1 EQUIPMENT SIZING.
 HEATING AND COOLING EQUIPMENT SHALL BE SIZED IN
 ACCORDANCE WITH ACCA MANUAL S BASED ON THE EQUIPMENT
 LOADS CALCULATED IN ACCORDANCE WITH ACCA MANUAL J OR
 OTHER APPROVED HEATING AND COOLING CALCULATION
 METHODOLOGIES, BASED ON BUILDING LOADS FOR THE
 DIRECTIONAL ORIENTATION OF THE BUILDING. THE
 MANUFACTURER AND MODEL NUMBER OF THE OUTDOOR AND INDOOR
 UNITS (IF SPLIT SYSTEM) SHALL BE SUBMITTED ALONG WITH
 THE SENSIBLE AND TOTAL COOLING CAPACITIES AT THE DESIGN
 CONDITIONS DESCRIBED IN SECTION R302.1. THIS CODE DOES
 NOT ALLOW DESIGNER SAFETY FACTORS, PROVISIONS FOR
 FUTURE EXPANSION OR OTHER FACTORS WHICH AFFECT
 EQUIPMENT SIZING. SYSTEM SIZING CALCULATIONS SHALL NOT
 INCLUDE LOADS CREATED BY LOCAL INTERMITTENT MECHANICAL
 VENTILATION SUCH AS STANDARD KITCHEN AND BATHROOM
 EXHAUST SYSTEMS.
  
 FBCER403.6.1.1 COOLING EQUIPMENT CAPACITY.
 COOLING ONLY EQUIPMENT SHALL BE SELECTED SO THAT ITS
 TOTAL CAPACITY IS NOT LESS THAN THE CALCULATED TOTAL
 LOAD, BUT NOT MORE THAN 1.15 TIMES GREATER THAN THE
 TOTAL LOAD CALCULATED ACCORDING TO THE PROCEDURE
 SELECTED IN SECTION 403.6, OR THE CLOSEST AVAILABLE
 SIZE PROVIDED BY THE MANUFACTURER?S PRODUCT LINES. THE
 CORRESPONDING LATENT CAPACITY OF THE EQUIPMENT SHALL
 NOT BE LESS THAN THE CALCULATED LATENT LOAD.
  
 4) PROVIDE A DETAIL AS TO THE PLACEMENT OF THE
 CONDENSER EQUIPMENT TO ASSURE IS WILL BE PLACED AT THE
 MINIMUM FLOOD ELEVATION LEVEL OF 7.5' INCORPORATE FLOOD
 RESISTANT CONSTRUCTION TECNIQUES SO AS TO PREVENT SCOUR
 UNDER THE SUPPORTING STRUCTURE.
  
 FBC-R322.1.6 PROTECTION OF MECHANICAL AND ELECTRICAL
 SYSTEMS.
 ELECTRICAL SYSTEMS, EQUIPMENT AND COMPONENTS; HEATING,
 VENTILATING, AIR CONDITIONING; PLUMBING APPLIANCES AND
 PLUMBING FIXTURES; DUCT SYSTEMS; AND OTHER SERVICE
 EQUIPMENT SHALL BE LOCATED AT OR ABOVE THE ELEVATION
 REQUIRED IN SECTION R322.2 (FLOOD HAZARD AREAS
 INCLUDING A ZONES)
  
 STEVEN KENNEDY, CBO
 CHIEF PLANS EXAMINER
 (561) 805-6710
 [email protected]
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved