| Date |
Text |
| 2015-11-25 14:21:12 | 1) MEN'S AND WOMEN'S RESTROOMS - 2014 FBC- |
| | ACCESSIBILITY SEC. 213.3.4 - WHERE LAVATORIES ARE |
| | PROVIDED, AT LEAST ONE SHALL COMPLY WITH SEC. 606 OF |
| | THE 2014 FBC- ACCESSIBILITY AND SHALL NOT BE LOCATED IN |
| | A TOILET COMPARTMENT. PROVISIONS SHALL BE PROVIDED FOR |
| | A FORWARD APPROACH TO THE LAVATORY. (SEC. 606.2) |
| | 2) SHT. A7.1 - GRAB BARS SHALL BE MEASURED TO THE TOP |
| | OF THE GRIPPING SURFACE FROM THE FINISH FLOOR, NOT TO |
| | THE CENTER AS SHOWN ON THE ELEVATION DETAILS. 2014 |
| | FBC-ACCESSIBILITY SEC. 609.4. |
| | 3) SUBMIT MANUFACTURER'S SPECIFICATIONS FOR ALL GAS |
| | EQUIPMENT. GAS EQUIPMENT SHALL BE LISTED AND LABELED |
| | PER THE 2014 FBC-FUEL GAS SEC. 301.3. |
| | 4) SUBMIT GREASE INTERCEPTOR SIZING CALCULATIONS TO |
| | ENSURE THAT THE EXISTING INTERCEPTORS HAVE ADEQUATE |
| | CAPACITY FOR THE NEW RESTAURANT.SUBMIT THE CAPACITY AND |
| | NUMBER OF THE EXISTING INTERCEPTORS. WPB AMEND. TO FBC |
| | SEC. 107.2.1. |
| | 5) SHT. P0.0 - GENERAL NOTE #3 - DRAINAGE PIPE SHALL |
| | BEE SLOPED IN ACCORDANCE WITH 2014 FBC-PLUMBING TABLE |
| | 704.1. |
| | 6) SHT. P1.0 - SHOWS CONDENSATE DISCHARGING TO THE |
| | GREASE SYSTEM. WASTES THAT DO REQUIRE TREATMENT OR |
| | SEPARATION SHALL NOT BE DISCHARGED INTO ANY INTERCEPTOR |
| | OR SEPARATOR.2014 FBC-PLUMBING SEC.1003.2. |
| | 7) SHT. P4.0 - DETAIL #2 - NOTE #1 - INDIRECT WASTE |
| | EXCEEDING 30 INCHES IN LENGTH SHALL BE TRAPPED PER THE |
| | 2014 FBC-PLUMBING SEC. 802.2. |
| | 8) SHT. P4.0 - THE DETAIL IS LABELED AS A FLOOR DRAIN |
| | BUT THE DETAIL IS OF A CLEANOUT. PLEASE REVISE. |
| | 9) SHT. P4.0 - DETAIL #4 SHOWS THE CONDENSATE |
| | DISCHARGING TO THE ROOF BUT SHT. P 3.0 SHOWS THE |
| | CCONDENSATE DISCHARGING TO A ROOF DRAIN.THE CONDENSATE |
| | SHALL DRAIN TO A ROOF DRAIN.CLARIFY. |
| | 10) SHT. P 6.0 - THE 2 INCH WATER LINE COMES INTO THE |
| | BUILDING, REDUCES TO 1 1/2 INCH TO THE WATER |
| | HEATER,INCREASES TO 2 INCH, AND REDUCES TO 1 1/2 INCH |
| | AGAIN. CLARIFY. |
| | 11) SHT. P 6.0 - SHUTOFF VALVES ARE REQD. ON EQUIPMENT |
| | #50, #50.1, & 52. 2014 FBC- PLUMBING SEC.606.2. |
| | 12) SHT. P6.0 - INDICATE THE PSI OF THE GAS SYATEM. WPB |
| | AMEND. TO FBC SEC. 107.3.5.1.3. |
| | 13) SHT. P6.0 - INDICATE THE TYPE OF PIPE BEING USED |
| | FOR THE GAS SYSTEM. |
| | 14) INDICATE ON SHT. P6.0 THE GAS SIZING TABLE FROM THE |
| | 2014 FBC-FUEL GAS CODE USED FOR THE PIPE SIZING OF THE |
| | GAS SYSTEM. |
| | 15) SUBMIT COMBUSTION AIR CALCULATIONS FOR ALL THE GAS |
| | EQUIPMENT.WHERE COMBUSTION AIR IS PROVIDED BY THE |
| | BUILDING'S MECHANICAL VENTILATION SYSTEM, THE SYSTEM |
| | SHALL PROVIDE THE SPECIFIED COMBUSTION AIR RATE IN |
| | ADDITION TO THE REQUIRED VENTILATION AIR. 2014 FBC-FUEL |
| | GAS SEC. 304.9.3, 304.9.1. |
| | 16) CLEANOUTS ARE REQUIRED IN WASTE STACKS PER 2014 |
| | FBC-PLUMBING SEC.708.3.4. |
| | 17) SUBMIT A SITE PLAN SHOWING THE LOCATION OF THE |
| | EXISTING GREASE INTERCEPTORS. |
| | |
| | PLUMBING PLAN REVIEW |
| | TIM LARGE |
| | CHIEF PLUMBING INSPECTOR |
| | 561-805-6692 |
| | [email protected] |
| | |
| | |
| | |
| | |
| | |
| | |
| | |