| 2015-11-04 05:23:40 | 1) SUBMIT AN EXISTING FLOOR PLAN FOR THE 1ST & 2ND |
| | FLOORS. WPB AMEND. TO FBC SEC. 107.2.1. |
| | 2) NOTE #13 ON SHT. A.03 REFERS TO THE INSTALLATION OF |
| | A BACKFLOW PREVENTION DEVICE BUT NOTHING IS SHOWN. |
| | CLARIFY. |
| | 3) NOTE #15 ON A.03 REFERS TO A 1 INCH STUB OUT FOR A |
| | FUTURE POOL BUT NOTHING IS SHOWN ON THE PLANS. CLARIFY. |
| | 4)NOTE #18 ON A.03 REFERS TO GAS PIPING/GAS METER BUT |
| | THERE IS NO GAS PIPNG SHOWN. WILL ANY WORK BE DONE ON |
| | THE GAS SYSTEM? CLARIFY. |
| | 5) NOTE #25 ON A.03 REFERS TO THE INSTALLATION OF TWO |
| | TANKLESS WATER HEATERS BUT NOTHING IS SHOWN ON THE |
| | PLANS. IF THE TANKLESS WATER HEATERS ARE BEING |
| | INSTALLED, SUBMIT MANUF. SPECIFICATIONS FOR THE WATER |
| | HEATERS AND RELATED PLUMBING/GAS DRAWINGS. SHOW THE |
| | LOCATION ON THE PLANS. CLARIFY. |
| | 6) NOTE # 26 ON A.03 REFERS TO A RECIRCULATING PUMP. |
| | NOTHING IS ON THE PLANS. CLARIFY. |
| | 7) NOTE # 27 REFERS TO DRAIN PAN & VACUUM RELIEF VALVE |
| | FOR WATER HEATER. IF NEW TANKLESS HEATERS ARE BEING |
| | INSTALLED THIS IS NOT REQD. SHOW THE LOCATION OF THE |
| | EXISTING WATER HEATER ON THE PLANS. |
| | 8) THE SANITARY RISER ON A.03 IS NOT CLOSE TO BEING |
| | CODE COMPLIANT.IF NO CHANGES ARE BEING MADE TO THE |
| | SANITARY SYSTEM, DELETE THE RISER DIAGRAM FROM THE |
| | DRAWING. |
| | 9) INDICATE ON THE PLAN IF ANY OF THE PLUMBING |
| | FIXTURES/GAS APPLIANCES ARE BEING RELOCATED FROM THEIR |
| | PRESENT LOCATION OR ARE BEING REPLACED IN THEIR PRESENT |
| | LOCATION. |
| | |
| | PLUMBING PLAN REVIEW |
| | TIM LARGE |
| | CHIEF PLUMBING INSPECTOR |
| | 561-805-6692 |
| | [email protected] |
| | |
| | |