| Date |
Text |
| 2015-10-21 15:17:31 | ****CORRECTIONS**** |
| | |
| | SAMANTHA HILL |
| | BUILDING PLANS EXAMINER |
| | [email protected] |
| | 561-805-6724 |
| | |
| | 1. PER PLAN, THIS WALL IS TEMPORARY (30 DAY ESTIMATE), |
| | I WAS UNABLE TO LOCATE A PERMIT APPLICATION PENDING TO |
| | RESTORE THE WALL. AS A REMODEL PERMIT WITH STRUCTURAL |
| | WORK (EXTERIOR WALL) HAS A TARGET PLAN REVIEW TIME OF |
| | 30 WORKING DAYS, IF A PLAN IS SUBMITTED TODAY THE |
| | TARGET TURNAROUND TIME COULD BE 6 WEEKS FOR FIRST |
| | REVIEW. A BUILDING PERMIT WITH ONE TRADE HAS A TARGET |
| | OF SEVEN WORKING DAYS. IF INTENT IS TO SUBMIT A |
| | SEPARATE APPLICATION TO RECONSTRUCT THE WALL, PLEASE |
| | INCLUDE THAT DETAIL AT THIS TIME AND INCLUDE IN THE |
| | SCOPE OF THIS PERMIT. IF INTENT IS TO INCLUDE THE WALL |
| | AS A PART OF A RENOVATION PERMIT, THE 30 DAY ESTIMATE |
| | DOES NOT APPEAR TO BE A REASONABLE AMOUNT OF TIME. |
| | |
| | PLEASE CLARIFY WHY PERMANENT CONSTRUCTION CANNOT BE |
| | INSTALLED AT THIS TIME AS A PART OF THIS PERMIT, OR |
| | REVISE THE PERMIT TO INCLUDE A CODE COMPLIANT DETAIL |
| | FOR INFILL (WATER INTRUSION, WIND RESISTANCE, ETC.). |
| | |
| | IF PERMANENT CONSTRUCTION IS NOT POSSIBLE, PROPOSE A |
| | MECHANISM FOR "TEMPORARY CONSTRUCTION" TO BE REMOVED. |
| | HOW WILL REMOVAL OF THE TEMPORARY CONSTRUCTION BE |
| | GUARANTEED? "TEMPORARY CONSTRUCTION" IS TYPICALLY FOR |
| | TEMPORARY STRUCTURES SUCH AS TENTS, WITH A PROPOSED |
| | TAKE DOWN DATE. IT IS NOT TYPICAL TO COMPROMISE THE |
| | BUILDING ENVELOPE WITH NO PLAN TO RESTORE THE BUILDING |
| | ENVELOPE. |
| | |
| | |
| | |
| | |
| | |