| 2015-12-03 11:37:24 | 1) SHT. A-3 - DETAIL #12 - A MINIMUM OF 8 INCHES DEEP |
| | AT 27 INCHES ABOVE THE FINISH FLOOR IS REQUIRED UNDER |
| | THE LAVATORY IN ACCORDANCE WITH THE 2014 |
| | FBC-ACCESSIBILITY SEC.306.3.3. ALSO, SEE FIGURE 306.3 |
| | (A). |
| | 2) SHT.P2-1 - THE DRY VACUUM DETAIL SHOWS A 2 INCH CPVC |
| | VENT FOR THE VACUUM PUMP AND SHT. M-1 CALLS PVC. |
| | CLARIFY. THE EXHAUST VENT SHALL BE PVC. |
| | 3) SHT. P2-1 - WATER PURIFIER SYSTEM DETAIL SHOWS THE |
| | DRAIN DIRECTLY CONNECTED TO THE DRAIN. COULD THIS BE A |
| | POSSIBLE SOURCE OF CONTAMINATION TO THE WATER IF A |
| | BLOCKAGE OCCURRED IN THE DRAIN TO WHICH IT IS |
| | CONNECTED? CLARIFY. |
| | 4) SUBMIT MANUFACTURER'S INSTALL MANUAL FOR THE DENTAL |
| | CHAIRS (2 COPIES). THE RESSPONSE NARRATIVE STATED SPECS |
| | WERE SUBMITTED BUT THERE WAS NOTHING IN THE SUBMITTAL |
| | PACKAGE. WPB AMEND. TO FBC SEC. 107.2.1. |
| | 5) SUBMIT A LEGEND FOR ALL THE SYMBOLS USED ON THE |
| | PIPING DIAGRAMS. WPB AMEND. TO FBC SEC. 107.2.1. |
| | 6) THE VACUUN UNIT DRAIN SHALL BE DIRECTLY CONNECTED TO |
| | A TRAPPED AND VENTED DRAIN PER 2005 NFPA 99 |
| | SEC.5.3.3.6.3.1. |
| | 7) WHAT ARE THE FUTURE COLD WATER LINES FOR? FUTURE HOT |
| | WATER LINES MAY BE REQUIRED. |
| | 8) PLEASE STAPLE THE LOOSE PLUMBING SHEETS TO THE REST |
| | OF THE PLANS. |
| | 9) BACKFLOW PREVENTION DEVICES ARE REQD. ON THE WATER |
| | SERVICES PER THE CWPB CROSS CONNECTION MANUAL. |
| | |
| | PLUMBING PLAN REVIEW |
| | TIM LARGE |
| | CHIEF PLUMBING INSPECTOR |
| | 561-805-6692 |
| | [email protected] |
| | |