Plan Review Notes
Plan Review Notes For Permit 15081109
Permit Number 15081109
Review Stop P
Sequence Number 1
Notes
Date Text
2015-09-01 10:13:571) SHT. FP-1 - THE BREAK ROOM SINK SHALL COMPLY WITH
 2014 FBC-ACCESSIBILITY SECS. 212, 212.3, 804. SHOW
 COMPLIANCE ON THE PLANS.
 2) THE RANGE IN THE BREAKROOM SHALL COMPLY WITH 2014
 FBC-ACCESSIBILITY SEC.804.6.4 -804.6.5.3. SHOW
 COMPLIANCE ON THE PLANS.
 3) A DRINKING FOUNTAIN IS REQUIRED IN A BUSINESS
 OCCUPANCY PER THE 2014 FBC-PLUMBIING TABLE 403.1.THIS
 IS NOT A RESTAURANT AND THE EXCEPTION FOR NOT PROVIDING
 A DRINKING FOUNTAIN IS FOR RESTAURANTS ONLY PER 2014
 FBC -PLUMBING SEC.410.3. A MINIMUM OF TWO DRINKING
 FOUNTAINS ARE REQUIRED PER 2014 FPC TABLE 403.1,
 FOOTNOTE # (E) & 2014 FAC SEC.211.2.
 4) A MINIMUM OF 3 WATER CLOSETS FOR THE MALES AND 3
 WATER CLOSETS FOR THE FEMALES ARE REQUIRED FOR AN
 OCCUPANT LOAD OF 200 PER THE 2014 FBC-PLUMBING TABLE
 403.1.
 5) A SERVICE SINK IS REQUIRED PER 2014 FBC-PLUMBING
 TABLE 403.1. SHOW THE LOCATION OF THE SERVICE SINK ON
 THE FLOOR PLAN AND THE SANITARY AND WATER RISERS. WPB
 AMEND. TO FBC SEC. 107.2.1.
 6) SUBMIT AN ENLARGED FLOOR PLAN OF THE TOILET ROOMS
 AND SHOW THE CLEAR INSIDE DIMENSIONS OF THE TOILET
 ROOMS, SHOWER, FIXTURE CLEARANCES, ETC. ALL TOILET
 ROOMS & BATHING ROOMS SHALL COMPLY WITH 2014
 FBC-ACCESSIBILITY SEC.213.604, 606, 608.
 7) SUBMIT ELEVATION DETAILS FOR ALL HANDICAP ACCESSIBLE
 FIXTURES, GRAB BARS, SHOWER CONTROLS, ETC.SHOW ALL
 MEASUREMETS FROM FINISH FLOOR.WPB AMEND. TO 2014 FBC
 SEC. 107.2.1.
 8) SHT. P-2 SHOWS 2 WATER LINES TO A WATER METER.
 INDDICATE ON THE PLANS IF THERE ARE TTWO SEPARATE WATER
 METERS SERVING THIS PROPERTY OR IF THESE TWO LINES ARE
 INTERCONNECTED AND CONTINUE TO CONNECT TO ONE METER. IF
 THEY ARE INTERCONNECTED, SHOW ALL THE PIPING TO THE
 POINT OF INTERCONNECTION.WPB AMEND TO FBC SEC. 107.2.1.
 9) THE FIRST FLOOR SANITARY SYSTEM DESIGN FOR TOILET
 ROOMS #104, 105 AND THE SECOND FLOOR DOES NOT COMPLY
 WITH SEC. 912.1 FOR WET VENTING. WET VENTED FIXTURES IN
 BATHROOM GROUPS SHALL BE LOCATED ON THE SAME FLOOR. AS
 DRAWN, THERE ARE WATER CLOSETS ON THE FIRST FLOOR BEING
 WET VENTED BY FIXTURES ON THE SECOND FLOOR.
 10) THE DISHWASHER SHALL BE INSTALLED IN ACCORDANCE
 WITH THE 2014 FBC-PLUMBING SEC.802.1.6.
 11) SHT. P-3 - SUBMIT 2 COPIES OF THE MANUFACTURER'S
 SPECIFICATIONS FOR ALL GAS
 APPLIANCES/EQUIPMENT.APPLIANCES/EQUIPMENT SHALL BE
 LISTED AND LABELED PER 2014 FBC-GAS CODE, SEC.301.3.
 12) THE GAS GENERATOR SHALL COMPLY WITH NFPA 37 AND
 COMPLY WITH UL 2200. 2010 FGC SEC.616.1.
 13) SUBMIT AN ISOMETRIC DRAWING THAT CLEARLY SHOWS THE
 LENGTH OF ALL CUT SECTIONS OF PIPE PER FBC-2014 FUEL
 GAS, SECS. 402.4.1, 402.4.2.
 14) SHOW TYPE OF PIPING MATERIAL BEING INSTALLED, ALL
 PIPE SIZES, AND THE EHD NUMBER OF CORRUGATED STAINLESS
 STEEL TUBING FOR EACH PIPE SIZE IF BEING USED. WPB
 AMENDMENTS TO FBC SEC. 107.2.1.
 15) SHOW THE BTU LOAD OF EACH APPLIANCE AND THE TOTAL
 BTU LOAD ON THE SYSTEM. REFER TO THE FBC-2014 FUEL GAS
 SECS. 401.8 THRU 402.6.1 AND TABLES 402.4(1) THRU
 402.4(37).
 16) SHOW THE DISTANCE FROM THE POINT OF DELIVERY,
 (METER), TO THE MOST REMOTE OUTLET IN THE BUILDING
 AND/OR SYSTEM PER THE FBC-2014 FUEL GAS APPENDIX A ?
 USE OF CAPACITY SECTION A.3.1(4) & 2014 FUEL GAS CODE
 SEC. 402.4.1.
 17) SUBMIT CALCULATIONS FOR COMBUSTION AIR PER THE
 FBC-2014 FUEL GAS CODE SEC. 304.
 18) INDICATE THE DELIVERY PRESSURE (PSI) PER FBC-2014
 FUEL GAS SEC. 402.2. IF NATURAL GAS SPECIFY .5 PSI OR 2
 PSI.
 19) SUBMIT A DETAIL SHOWING THE TYPE, LOCATION, SIZE
 AND TERMINATION OF THE GAS VENTS PER FBC-2014 FUEL GAS
 CODE SEC. 502 THRU 505.
 20) SHT. P-4 - OVERFLOW SCUPPERS SHALL BE LOCATED NO
 LESS THAN 2 INCHES NOR MORE THAN 4 INCHES ABOVE THE
 FINISHED ROOF SURFACE PER 2014 FBC SEC. 1503.4.2.1.THE
 SCUPPER DETAIL SHOWS THE BOTTOM OF THE SCUPPER LEVEL
 WITH THE ROOF.
 21) INDICATE ON THE PLAN THAT THE ROOF DRAINAGE AREA
 INCLUDES 1/2 OF THE AREA OF ALL VERTICAL WALLS THAT
 DIVERT RAINWATER TO THE ROOF. 2014 FBC-P SEC.1106.4.
 22) CLEANOUTS ARE REQUIRED IN THE BASE OF THE RAINWATER
 LEADERS. FBC-P SEC. 1101.8.
 23) AN OIL SEPARATOR SHALL BE INSTALLED FOR THE
 ELEVATOR PIT IN ACCORDANCE WITH 20144 FPC SEC.1003.4.
  
 PLUMBING PLAN REVIEW
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 561-805-6692
 [email protected]
  
  
  
  
  
  


Account Summary | Usage Policy | Privacy Policy