| Date |
Text |
| 2015-08-28 12:44:37 | 1ST REVIEW: FBC 2014 MECHANICAL |
| | PERMIT #15080635 |
| | 8/28/15 |
| | |
| | 1) SHEET A1 CODE DATA: PROVIDE THE CLASSIFICATION OF |
| | THE PROPOSED WORK IN ACCORDANCE WITH THE FLORIDA |
| | EXISTING BUILDING CODE FIFTH EDITION 2014. REFER TO |
| | CHAPTER 5 AND INDICATE LEVEL 1, 2, 3, OR CHANGE OF |
| | OCCUPANCY ON THE PLANS. |
| | 2) REFER TO SECTION C101.4.4 FBC-14 ENERGY |
| | CONSERVATION: CHANGE IN OCCUPANCY OR USE. |
| | SPACES UNDERGOING A CHANGE IN OCCUPANCY THAT WOULD |
| | RESULT IN AN INCREASE IN DEMAND FOR EITHER FOSSIL FUEL |
| | OR ELECTRICAL ENERGY SHALL COMPLY WITH THIS CODE. WHERE |
| | THE USE IN A SPACE CHANGES FROM ONE USE IN TABLE |
| | C405.5.2(1) OR (2) TO ANOTHER USE IN TABLE C405.5.2(1) |
| | OR (2), THE INSTALLED LIGHTING WATTAGE SHALL COMPLY |
| | WITH SECTION C405.5. |
| | PLEASE PROVIDE ENERGY CALCULATIONS USING COMPLIANCE |
| | MATERIALS SPECIFIED IN SECTION C101.5.1. |
| | 3) REFER TO SECTION 809.1 FBC-14 EXISTING BUILDING AND |
| | PROVIDE AC LOAD CALCULATIONS FOR THE AC SYSTEMS. |
| | C403.2.1 FBC-14 CALCULATION OF HEATING AND COOLING |
| | LOADS. |
| | DESIGN LOADS SHALL BE DETERMINED IN ACCORDANCE WITH THE |
| | PROCEDURES DESCRIBED IN THE ASHRAE/ACCA STANDARD 183 OR |
| | ACCA MANUAL N AND SHALL BE ATTACHED TO THE CODE |
| | COMPLIANCE FORM SUBMITTED TO THE BUILDING DEPARTMENT |
| | WHEN THE BUILDING IS PERMITTED OR, IN THE EVENT THE |
| | MECHANICAL PERMIT IS OBTAINED AT A LATER TIME, THE |
| | SIZING CALCULATION SHALL BE SUBMITTED WITH THE |
| | APPLICATION FOR THE MECHANICAL PERMIT. HEATING AND |
| | COOLING LOADS SHALL BE ADJUSTED TO ACCOUNT FOR LOAD |
| | REDUCTIONS THAT ARE ACHIEVED WHEN ENERGY RECOVERY |
| | SYSTEMS ARE UTILIZED IN THE HVAC SYSTEM IN ACCORDANCE |
| | WITH THE ASHRAEHVAC SYSTEMS AND EQUIPMENT HANDBOOK. |
| | ALTERNATIVELY, DESIGN LOADS SHALL BE DETERMINED BY AN |
| | APPROVED EQUIVALENT COMPUTATION PROCEDURE, USING THE |
| | DESIGN PARAMETERS SPECIFIED IN CHAPTER 3. |
| | 4) M1: INDICATE HOW ACCESS TO AHU-1 & AHU-2 IS BEING |
| | PROVIDED. REFER TO THE FOLLOWING CODE SECTIONS AND |
| | PROVIDE DRAWINGS AND DETAILS VERIFYING COMPLIANCE: |
| | SECTION 306.1, AND 603.1.1 FBC-14 MECHANICAL. |
| | 5) M1: DUCT SMOKE DETECTORS SHALL BE LOCATED IN THE |
| | RETURN AIR SYSTEMS OF AHU-1 AND AHU-2 IN COMPLIANCE |
| | WITH SECTIONS 606.2.1 AND 606.2.2 FBC-14 MECHANICAL. |
| | PROVIDE A NARRATIVE AND DIAGRAM DESCRIBING CONTROLS |
| | OPERATION AND SUPERVISION OF THE DETECTORS PER SECTIONS |
| | 606.4 & 606.4.1. |
| | 6) M1: PROVIDE A MEANS OF RETURN AIR FROM THE |
| | STRETCHING ROOM AND HALLWAY TO AHU-2. SEE SECTION 601.5 |
| | MECHANICAL. |
| | 7) M1: PLEASE CLARIFY WHY AIR FROM THE AHU-1 SUPPLY IN |
| | THE SYNERGY ROOM IS BEING RETURNED TO AHU-2. SEE |
| | SECTION 601.5. |
| | 8) M2: PROVIDE SUPPORT AND HANGER DETAILS FOR THE |
| | FIBROUS DUCTS, THE VAV BOXES, AND THE EXHAUST FANS. |
| | 9) M1 & M2: PROVIDE CONDENSATE DISPOSAL PLANS FOR AHU-1 |
| | & 2, AND THE RTU : SEE SECTION 307.2- 307.2.3 FBC-14 |
| | MECHANICAL. |
| | 10) THE EXHAUST FAN IN THE TOILET/SHOWER ROOM 112 SHALL |
| | BE MINIMUM 100 CFM PER TABLE 403.3 |
| | 11) PROVIDE STRUCTURAL DETAILS, AND THE WIND DESIGN |
| | CRITERIA AND PRESSURES FOR INSTALLATION OF THE NEW RTU |
| | ROOF OPENING, THE RTU CURB, AND MOUNTING OF THE RTU- |
| | REFER TO SECTION 301.15 FBC-14 MECHANICAL. |
| | 12) PROVIDE MANUFACTURER'S SPECIFICATIONS FOR THE TRANE |
| | RTU/O/A UNITS, AND THE VAV BOXES. |
| | 13) PROVIDE A FLORIDA PRODUCT APPROVAL OR MIAMI-DADE |
| | NOA FOR THE EXTERIOR WALL LOUVER- FL. DEPT. OF |
| | COMMUNITY AFFAIRS RULE 9N-3. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 561-805-6719 |
| | [email protected] |
| | |