Plan Review Notes
Plan Review Notes For Permit 15080415
Permit Number 15080415
Review Stop B
Sequence Number 1
Notes
Date Text
2015-09-29 11:33:36PLAN
 REVIEW COMMENTS
  
 1ST REVIEW: FBC FIFTH EDITION (2014)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY BUILDING
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
  
 1) THE OWNER/AGENT IS REQUIRED TO SIGN THE ENERGY
 COMPLIANCE FORMS. FBC ENERGY CONSERVATION R103.1.1.2
  
 2) THE ENERGY COMPLIANCE FORMS SPECIFY R-20 CEILING
 INSULATION AND PLAN SHEET A-302 HAS R-19 CEILING
 INSULATION. FBC 107.2.1
  
 3) SUBMIT A SITE DRAINAGE PLAN THAT SHOWS COMPLIANCE
 WITH FBC - R401.3 SURFACE DRAINAGE SHALL BE DIVERTED TO
 A STORM SEWER CONVEYANCE OR OTHER APPROVED POINT OF
 COLLECTION THAT DOES NOT CREATE A HAZARD. LOTS SHALL BE
 GRADED TO DRAIN SURFACE WATER AWAY FROM FOUNDATION
 WALLS. THE GRADE SHALL FALL A MINIMUM OF 6 INCHES (152
 MM) WITHIN THE FIRST 10 FEET (3048 MM).
  
 4) FBC - R302.5.1 REQUIRES A SELF-CLOSING DEVICE ON THE
 DOOR FROM THE GARAGE TO THE HABITABLE SPACE.
  
 5) GENERAL NOTE 1 ON SHEET A-100 INCORRECTLY REFERENCES
 THE 2010 FBC. THE FBC FIFTH EDITION (2014) WENT INTO
 EFFECT ON JUNE 30, 2015. ALL NEW PERMITS APPLIED FOR ON
 OR AFTER THAT DATE ARE REQUIRED TO COMPLY WITH AND
 REFERENCE THE FBC FIFTH EDITION.
  
 6) THE STRUCTURAL DESIGN CRITERIA NOTES ON SHEET S-1
 REFERENCE THE 2010 FBC. THE FBC FIFTH EDITION (2014)
 WENT INTO EFFECT ON JUNE 30, 2015. ALL NEW PERMITS
 APPLIED FOR ON OR AFTER THAT DATE ARE REQUIRED TO
 COMPLY WITH AND REFERENCE THE FBC FIFTH EDITION.
  
 7) THE REFERENCES TO THE FOLLOWING STANDARDS ON SHEET
 S-1 ARE INCORRECT, THEY SHOULD BE AS FOLLOWS: ACI
 318-11, ACI 530-11, ACI 530.1-11, ASCE 5-11, ASCE 6-11,
 TMS 402-11 AND TMS 602-11. THE 2011 EDITIONS OF THESE
 STANDARDS ARE THE ONES THAT ARE REFERENCED IN CHAPTER
 46 THE FBC FIFTH EDITION (2014).
  
 8) ON THE LOW ROOF AND HIGH ROOF FRAMING PLANS ON SHEET
 S-3, THE SECTION ID TAGS ARE INCORRECT. THEY DO NOT
 CORRESPOND WITH THE CORRECT SECTION DETAILS ON S-5. FBC
 107.2.1
  
 9) SECTION DETAIL 4 0N S-5 IS BLANK , HOWEVER, THERE IS
 A TAG FOR IT ON S-3. PLEASE CLARIFY. FBC 107.2.1
  
 10) THE WEST ELEVATION DOES NOT MATCH THE FLOOR PLANS.
 THE EXTERIOR DOOR (ED 109) TO THE MASTER BATH IS NOT
 SHOWN. THE SECOND FLOOR PLAN HAS TWO WINDOWS AND THE
 ELEVATION HAS THREE. FBC 107.2.1
  
 11) ADDITIONAL INFORMATION IS REQUIRED FOR THE MASONRY
 FIREPLACE AND CHIMNEY TO SHOW THAT IT WILL COMPLY WITH
 FBC R1001. PROVIDE DIMENSIONS AND DETAILS OF ALL PARTS
 AND COMPONENTS. FBC 107.2.1
  
 12) FBC 107.3.4 - PROVIDE TWO SETS OF PRODUCT APPROVALS
 FOR THOSE PRODUCTS WHICH ARE REGULATED BY DCA RULE 9N-3
 THAT HAVE BEEN REVIEWED AND APPROVED IN WRITING BY THE
 DESIGNER OF RECORD.
  
 13) SPECIFY THE METHOD OF ATTACHMENT THAT WILL BE USED
 TO INSTALL THE BORAL CEMENT ROOF TILE AND RESIST THE
 REQUIRED OVERTURN MOMENT. IF AN ADHESIVE WILL BE USED
 SUBMIT TWO SETS OF ITS PRODUCT APPROVAL. FBC - R
 301.2.1
  
 14) SUBMIT TWO SETS OF THE PRODUCT EVALUATION REPORT
 AND INSTALLATION INSTRUCTIONS FOR THE SPRAY FOAM
 INSULATION. FBC - R 316
  
 15) SUBMIT PRODUCT APPROVALS, MANUFACTURES'
 SPECIFICATIONS WITH INSULATION INSTRUCTIONS FOR THE
 COLONIAL AND BAHAMA SHUTTERS SHOWN ON THE ELEVATION
 DRAWINGS. FBC 107.2.1 & R301.2.1
  
  
  
  
  
  