| 2015-08-18 11:09:40 | 1ST REVIEW: FBC 2014 MECHANICAL |
| | PERMIT #15071040 |
| | |
| | 1) REFER TO SECTION C403.2.1 FBC-14 ENERGY |
| | CONSERVATION- CALCULATION OF HEATING AND COOLING LOADS: |
| | DESIGN LOADS SHALL BE DETERMINED IN ACCORDANCE WITH THE |
| | PROCEDURES DESCRIBED IN THE ASHRAE/ACCA STANDARD 183 OR |
| | ACCA MANUAL N AND SHALL BE ATTACHED TO THE CODE |
| | COMPLIANCE FORM SUBMITTED TO THE BUILDING DEPARTMENT |
| | WHEN THE BUILDING IS PERMITTED OR, IN THE EVENT THE |
| | MECHANICAL PERMIT IS OBTAINED AT A LATER TIME, THE |
| | SIZING CALCULATION SHALL BE SUBMITTED WITH THE |
| | APPLICATION FOR THE MECHANICAL PERMIT. HEATING AND |
| | COOLING LOADS SHALL BE ADJUSTED TO ACCOUNT FOR LOAD |
| | REDUCTIONS THAT ARE ACHIEVED WHEN ENERGY RECOVERY |
| | SYSTEMS ARE UTILIZED IN THE HVAC SYSTEM IN ACCORDANCE |
| | WITH THE ASHRAEHVAC SYSTEMS AND EQUIPMENT HANDBOOK. |
| | ALTERNATIVELY, DESIGN LOADS SHALL BE DETERMINED BY AN |
| | APPROVED EQUIVALENT COMPUTATION PROCEDURE, USING THE |
| | DESIGN PARAMETERS SPECIFIED IN CHAPTER 3. |
| | PLEASE SUBMIT UP TO DATE CALCULATIONS FOR NEW SYSTEM |
| | INSTALLATIONS, OR IF THE UNITS ARE EXISTING, SUBMIT |
| | COPIES OF THE ORIGINAL CALCULATIONS. |
| | 2) REFER TO SECTION C101 AMD SUBMIT ENERGY CALCULATIONS |
| | FOR THE PROPOSED OFFICE TRAILER. PLEASE NOTE THAT |
| | COPIES OF THE ORIGINAL CALCULATIONS MAY BE SUBMITTED IF |
| | NO MODIFICATIONS TO THE MODULAR SINCE THAT TIME HAVE |
| | BEEN DONE. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 561-805-6719 |
| | [email protected] |
| | |