| Date |
Text |
| 2015-12-21 13:05:56 | |
| | RESIDENTIAL (R3) ALTERATION, SECOND MECHANICAL REVIEW |
| | CHECKLIST. |
| | CODE: FBC-5TH EDITION (2014). |
| | |
| | NOTE: THE COMMENTS BELOW MAY BE APPROVED WITH PROVISO. |
| | REVISION FEES MAY APPLY. CONTRACTOR TO ADVICE IF |
| | PROVISO OPTION IS PREFERRED OR IF RE-SUBMITTING |
| | REQUIRED INFORMATION BEFORE ISSUING THE PERMIT. |
| | |
| | 1- REVISE THE EQUIPMENT SIZING CALCULATIONS. |
| | A) WINDOW ORIENTATION IS INCORRECT. SEE PLANS AND |
| | SURVEY AND REVISE AS REQUIRED. CALCULATIONS NEED TO BE |
| | DONE FOR THE ACTUAL ORIENTATION OF THE BUILDING AS |
| | REQUIRED BY SEC. R403.6.1 FBC-ENERGY CONSERVATION, 5TH |
| | EDITION (2014). |
| | |
| | B) CENTRAL UNIT SPECIFIED ON PAGE 3 IS OVERSIZED. THIS |
| | IS NOT ALLOWED BY SEC. R403.6.1.1 FBC-ENERGY |
| | CONSERVATION, 5TH EDITION (2014). |
| | |
| | 2- PROVIDE A/C PLAN WITH THE FOLLOWING INFORMATION: |
| | A) NAME AND SIGNATURE OF THE PERSON RESPONSIBLE FOR THE |
| | DESIGN. SEC. 107.2.1 CITY AMENDMENTS. |
| | |
| | B) EQUIPMENT LOCATION, MANUFACTURER AND MODEL NUMBER. |
| | SEC. 107.3.5.3(10) CITY AMENDMENTS. |
| | NOTE: EQUIPMENT TO MATCH EQUIPMENT SIZING CALCULATIONS |
| | AND ENERGY CALCULATIONS SUBMITTED. |
| | |
| | ***PLEASE PROVIDE RESPONSE LETTER ADDRESSIGN EACH |
| | COMMENT TO EXPEDITE THE REVIEW PROCESS. |
| | |
| | IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT |
| | JULIO GOMEZ |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | DEVELOPMENT SERVICES DEPARTMENT |
| | (561)805-6712 |
| | [email protected] |
| | |
| | |
| | |