Plan Review Notes
Plan Review Notes For Permit 15061181
Permit Number 15061181
Review Stop M
Sequence Number 1
Notes
Date Text
2015-07-08 15:49:341ST REVIEW: FBC 2010 MECHANICAL
  
 1) THE AC SYSTEMS AT 15 TONS OF COOLING CAPACITY ARE
 OVERSIZED PER THE LOAD CALCULATIONS WHICH ARE
 INDICATING A TOTAL LOAD OF 11.3 TONS. HEATING AND
 COOLING EQUIPMENT AND SYSTEMS CAPACITY SHALL NOT EXCEED
 THE CALCULATED LOADS- SECTION 503.2.2 FBC-10 ENERGY
 CONSERVATION.
 2) SHEET M6.1: THE 34.3 SENSIBLE CAPACITY LISTED IN THE
 AC SCHEDULE DOES NOT SEEM TO BE ACCURATE FOR THE NEW
 7.5 TON PACKAGED UNIT- PLEASE SUBMIT MANUFACTURER'S
 PRODUCT SPEC SHEETS FOR VERIFICATION.
 3) M2.1: PROVIDE THE RETURN DUCT SIZES FROM THE OFFICE
 (107) AND CONFERENCE (108) GRILLS, AND SHOW THE ENTIRE
 DUCT RUNS BACK TO THE RTU. IF THE DUCTS SHOWN IN THE
 DRAWING ARE DUCT BOOT SOUND ATTENTUATORS, PLEASE LABEL
 THEM AS SUCH TO CLARIFY HOW THE RETURN AIR SYSTEM IS
 FUNCTIONING.
 4) M2.1: PLEASE CLARIFY WHY TWO 6 INCH TRANSFER DUCTS
 ARE SHOWN CONNECTING THE RETURN GRILLS IN THE OPEN
 SEATING (104) AND THE OFFICE (105) CEILINGS.
 5) M2.1: SHOW THE SIZE OF THE TRANSFER GRILL BETWEEN
 THE FLEX SPACE (113), AND THE HALLWAY (110).
 6) A2.0: THE DETAILS SHOWN FOR INSTALLATION OF THE NEW
 RTU AND CURB ARE INCOMPLETE. ENGINEERED STRUCTURAL
 DETAILS ARE REQUIRED FOR MODIFICATIONS TO THE EXISTING
 ROOF STRUCTURE, AND WINDLOAD ENGINEERING FOR ANCHORING
 OF THE CURB AND MOUNTING THE RTU- SECTION 301.12 FBC-10
 MECHANICAL.
 7) A2.0: SHOW THE CONDENSATE PIPING RUN AND DISCHARGE
 LOCATION. INDICATE THE TYPE AND SIZE OF PIPING, PIPING
 SUPPORTS, AND HOW THE PIPING WILL BE PROTECTED FROM
 WEATHERING AND UV DEGRADATION.
  
 CHRISTOPHER L. COLE
 MECHANICAL PLANS EXAMINER
 561-805-6719
 [email protected]
  
  