| Date |
Text |
| 2015-10-29 17:03:41 | PERMIT #15060652 |
| | 10/29/15 |
| | PROVISOS: |
| | |
| | 1) REMOVE THE ENERGY CALCULATION DOCUMENTS DSL17999A & |
| | SMM15096 FROM THE FILE (NOT APPLICABLE TO THIS |
| | PROJECT), AND RELOCATE FORM 502-2010 TO THE DOCUMENT |
| | FILE FOR #15060552 ( DIGESTER ELECTRICAL BUILDING PLANS |
| | ROOM). |
| | 2) DEFERRED SUBMITTAL: 107.3.4.2 DEFERRED SUBMITTALS. |
| | FOR THE PURPOSES OF THIS SECTION, DEFERRED SUBMITTALS |
| | ARE DEFINED AS THOSE PORTIONS OF THE DESIGN THAT ARE |
| | NOT SUBMITTED AT THE TIME OF THE |
| | APPLICATION AND THAT ARE TO BE SUBMITTED TO THE |
| | BUILDING OFFICIAL WITHIN A SPECIFIED PERIOD. DEFERRAL |
| | OF ANY SUBMITTAL ITEMS SHALL HAVE THE PRIOR APPROVAL OF |
| | THE BUILDING OFFICIAL. THE REGISTERED DESIGN |
| | PROFESSIONAL IN RESPONSIBLE CHARGE SHALL LIST THE |
| | DEFERRED SUBMITTALS ON THE CONSTRUCTION DOCUMENTS FOR |
| | REVIEW BY THE BUILDING OFFICIAL. |
| | DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE |
| | SUBMITTED TO THE REGISTERED DESIGN PROFESSIONAL IN |
| | RESPONSIBLE CHARGE WHO SHALL REVIEW THEM AND FORWARD |
| | THEM TO THE BUILDING OFFICIAL WITH A NOTATION |
| | INDICATING THAT THE DEFERRED SUBMITTAL DOCUMENTS HAVE |
| | BEEN REVIEWED AND FOUND TO BE IN GENERAL CONFORMANCE TO |
| | THE DESIGN OF THE BUILDING. THE DEFERRED SUBMITTAL |
| | ITEMS SHALL NOT BE INSTALLED UNTIL THE DEFERRED |
| | DEFERRED SUBMITTAL. 2010 FBC 107.3.4.1 PRODUCT |
| | APPROVALS. THOSE PRODUCTS WHICH ARE REGULATED BY THE |
| | DCA RULE 9N-03 SHALL BE REVIEWED AND APPROVED IN |
| | WRITING BY THE DESIGNER OF RECORD PRIOR TO SUBMITTAL |
| | FOR JURISDICTIONAL APPROVAL. |
| | |