2016-01-15 09:47:05GAS PROVISOS -
 GAS PERMIT APPLICATION REQUIREMENTS
  
 EFFECTIVE IMMEDIATELY THE FOLLOWING INFORMATION SHALL
 BE SHOWN ON ALL GAS DRAWINGS SUBMITTED FOR PERMITTING
 IN THE CITY OF WEST PALM BEACH:
  
 1. SUBMIT AN ISOMETRIC DRAWING THAT CLEARLY SHOWS THE
 LENGTH OF ALL CUT SECTIONS OF PIPE PER 2014 FBC-FUEL
 GAS, SECS. 402.4.1, 402.4.2. OR 2014 FBC-RES SEC.
 G2413.
  
 2. SHOW THE TYPE OF PIPE MATERIAL BEING INSTALLED, ALL
 PIPE SIZES, AND THE CORRESPONDING EHD NUMBER OF THE
 CORRUGATED STAINLESS STEEL TUBING FOR EACH PIPE SIZE.
 WPB AMENDMENTS TO FBC SEC.107.2.1.
  
 3. TYPE OF GAS (LP OR NATURAL).
  
 4. BTU LOAD OF EACH APPLIANCE AND THE TOTAL BTU LOAD ON
 THE SYSTEM. REFER TO THE 2014 FBC-FUEL GAS SECS.401.8
 THRU 402.6.1 AND TABLES 402.4 (1) THRU 402.4 (37) OR
 2014 FBC-RES. SEC. G2413.
  
 5. SHOW THE DISTANCE FROM THE POINT OF DELIVERY, (METER
 OR MP REGULATOR) TO THE MOST REMOTE OUTLET IN THE
 BUILDING AND / OR SYSTEM PER THE 2014 FBC-FUEL GAS
 SEC.402.4.1 OR 2014 FBC-RES. SEC. G 2413.3.
  
 6. SUBMIT CALCULATIONS FOR COMBUSTION AIR PER THE 2014
 FBC-FUEL GAS CODE SEC.304.1 OR 2014 FBC-RES. SEC. G
 2407.
  
 7. INDICATE THE DELIVERY PRESSURE (PSI) OF THE SYSTEM
 ON THE PLAN PER 2014 FBC-FUEL GAS SEC.402.2 OR FBC RES.
 SEC. G2413.2. .
  
 8. SUBMIT A DETAIL SHOWING THE TYPE, LOCATION, SIZE AND
 TERMINATION OF THE GAS VENTS PER 2014 FBC-FUEL GAS
 SECS. 502 THRU 505. OR 2014 FBC-RES. SEC.G2426.
  
 9. SUBMIT MANUFACTURER?S SPECIFICATION SHEETS /
 INSTALLATION MANUAL FOR ALL GAS EQUIPMENT TO VERIFY
 COMPLIANCE WITH STANDARDS NFPA 54, NFPA 58, AND
 FBC-2014 FUEL GAS CODE SEC. 402.2, AND 301.3 OR 2014
 FBC-RES. SEC. G2404.3. GAS APPLIANCES SHALL BE LISTED
 AND LABELED.
  
 10. CLEARLY SHOW THE LOCATION AND CAPACITY OF LP
 TANK(S), TYPE OF TANK ( DOT OR ASME ), THE DISTANCE OF
 THE TANK FROM THE EXTERIOR BUILDING WALL AND ADJACENT
 PROPERTY LINES, THE DISTANCE OF THE TANK FROM ALL
 SOURCES OF IGNITION, OTHER CONTAINERS, BUILDINGS, AND
 THE LOCATION OF ANY BUILDING OPENINGS BELOW THE RELIEF
 VALVE OF THE TANK PER NFPA 58, TABLE 3-2.2.2.
  
 11. CLEARLY INDICATE ON THE PLAN IF THE LP TANK IS
 ABOVE GROUND OR BELOW GROUND, AND SHOW THE METHOD OF
 REQUIRED PROTECTION FOR THE LP TANK AND APPURTENANCES
 PER NFPA 58. IF THE TANK IS BELOW GROUND IT SHALL BE
 ANCHORED PER NFPA 58 SEC.3-2.2.7 (H). IF ABOVE GROUND,
 THE TANK SHALL BE SECURELY ANCHORED TO WITHSTAND 170
 MPH ULT WIND LOAD PER THE FLORIDA BUILDING CODE.
  
 ANY QUESTIONS REGARDING THESE REQUIREMENTS MAY BE
 REFERRED TO THE CHIEF PLUMBING INSPECTOR AT
 561-805-6692.
  
 PLUMBING PLAN REVIEW
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 561-805-6692
 [email protected]
  
  
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved