| Date |
Text |
| 2015-10-24 07:03:54 | 1) SHT. 0386- A - ADF - 08 - FBC 2010 SEC.1503.4.2.1 |
| | OVERFLOW SCUPPERS - OVERFLOW SCUPPERS SHALL BE LOCATED |
| | NO LESS THAN 2 INCHES NOR MORE THAN 4 INCHES ABOVE THE |
| | FINISHED ROOF COVERING AND SHALL BE LOCATED AS CLOSE AS |
| | PRACTICAL TO REQUIRED VERTICAL LEADERS OR DOWNSPOUTS OR |
| | WALL AND PARAPET SCUPPERS. NOTE # 2 STATES THE OVERFLOW |
| | SCUPPER WILL BE 3 INCHES ABOVE THE PRIMARY SCUPPER. |
| | INCLUDE IN THE NOTE THAT THE OVERFLOW SCUPPER SHALL BE |
| | NO LESS THAN 2 INCHES NOR MORE THAN 4 INCHES ABOVE THE |
| | FINISHED ROOF SURFACE.THIS IS THE LANGUAGE IN THE CODE. |
| | NOTE #2 STATES "3 INCHES ABOVE THE PRIMARY SCUPPER". |
| | THIS COULD POSSIBLY BE MISINTERPRETED AS MEANING THE |
| | TOP OF THE SCUPPER. |
| | 2) THE DESIGN TEAM'S RESPONSE NARRATIVE FOR THE LP GAS |
| | REVIEW COMMENTS ARE VAGUE. THE FOLLOWING ITEMS ARE |
| | REQUIRED FOR A COMPREHENSIVE PLAN REVIEW TO BE DONE FOR |
| | THE LP GAS SYSTEM AND SHALL BE SUPPLIED WHEN THE GAS |
| | PERMIT IS APPLIED FOR BY AMERIGAS. |
| | A) SUBMIT AN GAS ISOMETRIC DRAWING THAT CLEARLY SHOWS |
| | THE LENGTH OF ALL CUT SECTIONS OF PIPE PER THE 2010 |
| | FBC- FUEL GAS SEC.402.1.402.3 & NFPA 58. |
| | B) SHOW THE TYPE OF PIPING MATERIAL BEING INSTALLED & |
| | ALL PIPE SIZES. WPB AMEND. TO FBC SEC. 107.2.1. |
| | C) TYPE OF GAS ( LP OR NATURAL ). |
| | D) BTU LOAD OF EACH APPLIANCE OR PIECE OF EQUIPMENT AND |
| | THE TOTAL BTU LOAD ON THE SYSTEM. |
| | E) SHOW THE DISTANCE FROM THE POINT OF DELIVERY,( METER |
| | OR 2 PSI REGULATOR ) TO THE MOST REMOTE OUTLET IN THE |
| | BUILDING AND/OR THE SYSTEM. |
| | F) SUBMIT CALCULATIONS FOR COMBUSTION AIR PER 2010 |
| | FBC-FUEL GAS CODE SEC. 304. |
| | G) INDICATE THE DELIVERY PRESSURE ( PSI ) OF THE GAS. |
| | H) CLEARLY SHOW THE LOCATION AND CAPACITY OF LP |
| | TANK(S), TYPE OF TANK ( DOT OR ASME ), THE DISTANCE OF |
| | THE TANK FROM THE BUILDING, THE DISTANCE OF THE TANK |
| | FROM ALL SOURCES OF IGNITION, AND THE LOCATION OF ANY |
| | BUILDING OPENINGS BELOW THE RELIEF VALVE OF THE TANKPER |
| | NFPA 58, TABLE 3-2.2.2. |
| | I) CLEARLY INDICATE ON THE PLAN IF THE LP TANK IS ABOVE |
| | OR BELOW GROUND AND SHOW THE REQUIRED PROTECTION OF THE |
| | TANK AND APPURTENANCES PER NFPA 58. |
| | 3) IT DOES NOT APPEAR AS THOUGH THE PLUMBING PLAN |
| | REVIEW COMMENTS FROM 10/8/15 HAVE BEEN ADDRESSED. |
| | CLARIFY. |
| | SHT. 0167-M-ADF-34 DOES NOT PROVIDE ALL OF THE REQUIRED |
| | INFORMATION PREVIOUSLY REQUESTED FOR THE GAS RISER |
| | DIAGRAM.NEITHER DOES SHT.0164-M-ADF-31.SINCE THIS |
| | INFORMATION HAS NOT BEEN FULLY SUBMITTED, THE PLAN WILL |
| | BE MARKED THAT A SEPARATE PERMIT WILL BE REQUIRED FOR |
| | THE GAS AND ALL REQUIRED INFO WILL BE SUBMITTED AT TIME |
| | OF PERMIT APPLICATION SUBMITTAL ALONG WITH ALL NEW |
| | DRAWINGS OR SUBMIT ALL THE INFORMATION AS PREVIOUSLY |
| | REQUESTED.WPB AMEND. TO FBC SEC. 107.3.5.1.3. THE |
| | NARRATIVE RESPONSES TO THE GAS COMMENTS DO NOT PROVIDE |
| | SUFFICIENT INFO TO DO A COMPREHENSIVE REVIEW. |
| | 5) THE NARRATIVE RESPONSE FOR PREVIOUS COMMENT # 9 DOES |
| | NOT COMPLY WITH SEC.905.2. THE VENT CONNECTION SHALL BE |
| | SO GRADED AND CONNECTED AS TO DRAIN BACK TO THE |
| | DRAINAGE PIPE BY GRAVITY. AS DRAWN, IT IS INSTALLED TO |
| | DRAIN BACK TO THE FIXTURE TO WHICH IT IS CONNECTED.IT |
| | DOES NOT COMPLY WITH 2010 FBC-PLUMBING SEC.706.3 & |
| | 905.2.THE FITTING SHALL BE INSTALLED IN THE DIRECTION |
| | OF FLOW.AS DRAWN IT IS NOT. |
| | 6) SHT.0696-H-ADF-01 REFERS TO TWO DIFFERENT STANDARDS |
| | FOR CALCULATING COMBUSTION AIR REQUIREMENTS. THE CODE |
| | IN EFFECT IS THE 2010 FBC-FUEL GAS. THE APPROPRIATE |
| | SECTION FOR USING TWO OPENINGS COMMUNICATING DIRECTLY |
| | WITH THE OUTDOORS IS 304.6.1. THE FORMULA IS A MINIMUM |
| | FREE AREA OF 1 SQUARE INCH PER 4000/ BTU OF TOTAL INPUT |
| | RATING OF ALL APPLIANCES IN THE ENCLOSURE. PLEASE |
| | EXPLAIN WHERE THE .47 FREE AREA COMES FROM IN YOUR |
| | EQUATION. SEC.304.10 OF 2010 FBC-FUEL GAS SPECIFIES |
| | METAL LOUVERS AND GRILLS WILL HAVE 75% FREE AREA. THE |
| | DESIGN MEETS THE REQUIRED COMBUSTION AIR BUT NOTES # 3 |
| | & #4 ON SHT 0696-H-ADF-01 NEED TO BE REVISED. |
| | |
| | PLEASE CONTACT ME TO DISCUSS THESE REVIEW COMMENTS OR |
| | TO SET UP A MEETING TO GO OVER THE COMMENTS THANK YOU. |
| | |
| | PLUMBING PLAN REVIEW |
| | TIM LARGE |
| | CHIEF PLUMBING INSPECTOR |
| | 561-805-6692 |
| | [email protected] |
| | |
| | |
| | |
| | |