Plan Review Notes
Plan Review Notes For Permit 15060549
Permit Number 15060549
Review Stop M
Sequence Number 1
Notes
Date Text
2015-07-06 13:59:211ST REVIEW: FBC 2010 MECHANICAL
 PERMIT #15060549 (T1/T2) SLUDGE PUMPING BUILDING-
 7/6/2015
  
 1) SUBMIT THE FOLLOWING ENERGY EFFICIENCY COMPLIANCE
 DOCUMENTS PREPARED BY THE ENGINEER OF RECORD: A)
 COOLING AND HEATING CALCULATIONS FOR AHU 5 & 6 IN
 ACCORDANCE WITH ACCA MANUAL N OR APPROVED ALTERNATE
 METHOD- SECTION 503.2.1 FBC-10 ENERGY CONSERVATION . B)
 ENERGY EFFICIENCY FORM 502-2010 OR 506-2010- REFERENCE
 SECTION 101.3, 103, AND CHAPTER 5 FBC-10 ENERGY
 CONSERVATION. THE DESIGN PROFESSIONAL SHALL CHOOSE
 EITHER THE PRESCRIPTIVE (502) OR PERFORMANCE BASED
 (506) COMPLIANCE PATH FOR THE BUILDING AND BUILDING
 SYSTEMS INCLUDING BUT NOT LIMITIED TO THE COMPONENTS OF
 THE THERMAL ENVELOPE, THE HVAC EQUIPMENT, THE HYDRONIC
 PIPING, AND THE ELECTRICAL POWER, LIGHTING, AND
 CONTROLS.
 2) PROVIDE A SUBMITTAL PACKAGE THAT INCLUDES A) FLORIDA
 PRODUCT APPROVALS AND/OR MIAMI DADE NOA'S FOR ALL
 PRODUCTS REGULATED BY FAC RULE 9N-3 REVIEWED AND
 APPROVED IN WRITING BY THE DESIGN PROFESSIONAL OF
 RECORD (HVAC ROOF CURBS, EXHAUST FANS AND CURBS,
 EXHAUST AND INTAKE LOUVERS, ETC.). B) MANUFACTURER'S
 PRODUCT DATA SHEETS FOR THE AHU- 5 & 6, EXHAUST FANS,
 FIRE DAMPERS, DUCT SMOKE DETECTORS, O/A MOTORIZED
 DAMPERS, ELECTRONIC CONTROLS, PIPE INSULATION ETC.
 3) PROVIDE EQUIPMENT SCHEDULES ON THE PLAN FOR AHU- 5 &
 6, AND EF- 5 & 6.
 4) PROVIDE A SEQUENCE OF OPERATION FOR THE VENTILATION
 SYSTEM TO CLARIFY HOW IT WILL FUNCTION-
 THERMOSTATICALLY, CONTINUOUSLY?
 5) PROVIDE AN AIR DISTRIBUTION SCHEDULE ON THE PLAN
 LISTING MAKES AND MODELS AND SIZES OF ALL COMPONENTS
 INCLUDING DUCTS, DIFFUSERS, AND RETURN GRILLS.
 6) PROVIDE TYPICAL DUCT HANGING AND CONNECTION DETAILS
 IN ACCORDANCE WITH THE SMACNA 2005 STANDARD.
 7) PROVIDE TESTED AND APPROVED FIRE STOPPING SYSTEM
 DETAILS FOR ALL PIPES OR DUCTS PENETRATING FIRE-RATED
 WALLS.
 8) H-ADF-06: DUCT SMOKE DETECTORS ARE REQUIRED IN THE
 SUPPLY DUCTS OF BOTH AHU- 5 & 6: PLEASE PROVIDE A
 SYMBOL ON THE PLAN TO SHOW THEIR LOCATIONS, PROVIDE AN
 INSTALLATION DETAILS, AND INDICATE HOW THE DEVICES WILL
 BE SUPERVISED PER SECTION 606.4.1.
 9) H-ADF-07: ENGINEERED WIND LOAD TIE-DOWN DETAILS FOR
 MOUNTING THE AHU'S AND CURBS, AND THE EXHAUST FANS AND
 CURBS ON THE ROOF ARE REQUIRED PER SECTION 301.12.
 PLEASE PROVIDE DETAILS, OR PLACE A NOTE INDICATING ON
 WHICH STRUCTURAL OR ARCHITECTURAL SHEET THE DETAILS ARE
 LOCATED. PROVIDE ELEVATION AND PLAN VIEW DRAWINGS
 INDICATING THE STRUCTURAL COMPONENTS OF THE CURBS, AND
 SHOW THE CURB HEIGHTS ABOVE THE FINISHED ROOF.
 10) PROVIDE SECTION VIEWS OF THE ROOF LADDERS TO
 INDICATE COMPLIANCE WITH THE DESIGN CRITERIA LISTED IN
 SECTION 306.5.
 11) BASED ON THE SOILS REPORT- PIPE BEDDING AND
 DEWATERING GUIDELINES, PLEASE PROVIDE PIPE TRENCH
 CROSS-SECTION DETAILS FOR TYPICAL INSTALLATIONS AND
 HIGH WATER TABLE INSTALLATIONS. INDICATE TRENCH
 DIMENSIONS, PIPE EMBEDMENT DEPTHS, BEDDING MATERIALS
 AND THICKNESSES, COMPACTION AND BACKFILLING
 SPECIFICATIONS.
 12) PROVIDE CIVIL DRAWINGS THAT INCLUDE OVERALL
 UNDERGROUND PIPING LAYOUTS, AND ENLARGED AREA DRAWINGS
 DEPICTING THE UNDERGROUND PIPES SERVICING EACH TANK,
 FACILITY, OR BUILDING.
 13) SUBMIT MANUFACTURER'S SPECIFICATIONS FOR PIPINGS
 AND FITTINGS, AND PIPE INSULATION REVIEWED AND APPROVED
 BY THE DESIGN PROFESSIONAL OF RECORD.
  
 CHRISTOPHER L. COLE
 MECHANICAL PLANS EXAMINER
 561-805-6719
 [email protected]
  
  