| Date |
Text |
| 2015-07-27 09:32:22 | 1ST REVIEW: FBC 2010 MECHANICAL |
| | PERMIT #15060530 |
| | 7/27/15 |
| | |
| | 1) HVAC PLANS FOR THE ELECTRICAL BUILDING SHALL BE |
| | SUBMITTED FOR REVIEW. SHEET E-WAS-05 SHOWS NEW AC-1 & |
| | AC-2. |
| | 2) SUBMIT THE FOLLOWING ENERGY EFFICIENCY COMPLIANCE |
| | DOCUMENTS PREPARED BY THE ENGINEER OF RECORD: A) |
| | COOLING AND HEATING CALCULATIONS FOR AC-1 & AC-2 IN |
| | ACCORDANCE WITH ACCA MANUAL N OR APPROVED ALTERNATE |
| | METHOD- SECTION 503.2.1 FBC-10 ENERGY CONSERVATION . B) |
| | ENERGY EFFICIENCY FORM 502-2010 OR 506-2010- REFERENCE |
| | SECTION 101.3, 103, AND CHAPTER 5 FBC-10 ENERGY |
| | CONSERVATION. THE DESIGN PROFESSIONAL SHALL CHOOSE |
| | EITHER THE PRESCRIPTIVE (502) OR PERFORMANCE BASED |
| | (506) COMPLIANCE PATH FOR THE BUILDING AND BUILDING |
| | SYSTEMS INCLUDING BUT NOT LIMITED TO THE COMPONENTS OF |
| | THE THERMAL ENVELOPE, THE HVAC EQUIPMENT, THE HYDRONIC |
| | PIPING, AND THE ELECTRICAL POWER, LIGHTING, AND |
| | CONTROLS. |
| | 3) PROVIDE EQUIPMENT SCHEDULES ON THE PLAN FOR AC-1 & |
| | AC-2. |
| | 4) PROVIDE INSTALLATION DETAILS FROR THE AIR HANDLERS |
| | INDICATING EITHER VERTICAL OR HORIZONTAL MPOUNTING, |
| | MEANS OF SUPPORT, WORKING CLEARANCES, AND REFRIGERANT |
| | AND CONDENSATE PIPING RUNS AND DETAILS. |
| | 5) DUCT SMOKE DETECTORS MAY BE REQUIRED IN THE SUPPLY |
| | DUCTS OF BOTH AC-1 & 2 IF THE SYSTEMS CAN EACH PRODUCE |
| | OVER 2000 CFM'S OF SUPPLY AIR- SECTION 606.2.1. IF |
| | APPLICABLE, PLEASE PROVIDE A SYMBOL ON THE PLAN TO SHOW |
| | THEIR LOCATIONS, PROVIDE INSTALLATION DETAILS, AND |
| | INDICATE HOW THE DEVICES WILL BE SUPERVISED PER SECTION |
| | 606.4.1. |
| | 6) PROVIDE AN AIR DISTRIBUTION SCHEDULE ON THE PLAN |
| | LISTING MAKES AND MODELS AND SIZES OF ALL COMPONENTS |
| | INCLUDING DUCTS, DIFFUSERS, AND RETURN GRILL |
| | 7) PROVIDE TESTED AND APPROVED FIRE STOPPING SYSTEM |
| | DETAILS FOR ALL PIPES OR DUCTS PENETRATING FIRE-RATED |
| | WALLS. |
| | 8) PROVIDE WIND LOAD DESIGN CRITERIA AND ENGINEERED |
| | STRUCTURAL DETAILS FOR INSTALLATION OF THE AC CONDENSER |
| | PADS, AND ANCHORING OF THE CONDENSERS TO THE PADS- |
| | SECTION 301.12. |
| | 9) PROVIDE EQUIPMENT SCHEDULES ON THE PLAN FOR BLOWER |
| | #1 & #2. INDICATE HOW THE BLOWERS WERE SIZED- SHOW |
| | CALCULATIONS IF APPLICABLE. |
| | 10) PROVIDE DETAILS FOR VENTILATION OF THE BLOWER ROOM |
| | INCLUDING A) EXHAUST VENTILATION CALCULATIONS- SECTION |
| | 403. A) EXHAUST FAN SCHEDULE B) LOUVER DIMENSIONS AND |
| | LOUVER SIZING CALCULATIONS. |
| | 11) PROVIDE ENGINEERED TIE DOWN DETAILS FOR |
| | INSTALLATION OF THE ROOF FAN- SECTION 301.12. |
| | 12) PROVIDE A SUBMITTAL PACKAGE THAT INCLUDES A) |
| | FLORIDA PRODUCT APPROVALS AND/OR MIAMI DADE NOA'S FOR |
| | ALL PRODUCTS REGULATED BY FAC RULE 9N-3 REVIEWED AND |
| | APPROVED IN WRITING BY THE DESIGN PROFESSIONAL OF |
| | RECORD ( EXHAUST FANS AND CURBS, EXHAUST AND INTAKE |
| | LOUVERS, ETC.). B) MANUFACTURER'S PRODUCT DATA SHEETS |
| | FOR THE AC-1 & 2, THE ROOF EXHAUST FAN, DUCT SMOKE |
| | DETECTORS, O/A MOTORIZED DAMPERS, ELECTRONIC CONTROLS, |
| | PIPING AND FITTINGS,AND PIPE INSULATION ETC. |
| | 13) BASED ON THE SOILS REPORT- PIPE BEDDING AND |
| | DEWATERING GUIDELINES, PLEASE PROVIDE PIPE TRENCH |
| | CROSS-SECTION DETAILS FOR TYPICAL INSTALLATIONS AND |
| | HIGH WATER TABLE INSTALLATIONS. INDICATE TRENCH |
| | DIMENSIONS, PIPE EMBEDMENT DEPTHS, BEDDING MATERIALS |
| | AND THICKNESSES, COMPACTION AND BACKFILLING |
| | SPECIFICATIONS. |
| | 14) PROVIDE CIVIL DRAWINGS THAT INCLUDE OVERALL |
| | UNDERGROUND PIPING LAYOUTS, AND ENLARGED AREA DRAWINGS |
| | DEPICTING THE UNDERGROUND PIPES SERVICING EACH TANK, |
| | FACILITY, OR BUILDING. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 561-805-6719 |
| | [email protected] |
| | |