| Date |
Text |
| 2015-07-10 06:51:29 | 1) SHT. A-1 - EQUIPMENT SCHEDULE SHOWS ITEM #3 ( WORK |
| | TABLE) AS GAS BUT THERE IS NO BTU LOAD SHOWN. CLARIFY. |
| | 2) THE SMOKEHOUSE IS SHOWN AS 60,000 BTU'S ON THE GAS |
| | RISER BUT THE SCHEDULE ON A-1 SHOWS 75,000 BTU'S. |
| | CLARIFY. |
| | 3) THE RICE COOKER IS SHOWN AS 31,200 BTU'S ON THE |
| | SCHEDULE BUT THE GAS RISER SHOWS 30,000 BTU'S. CLARIFY. |
| | 4) SUBMIT MANUFACTURER'S SPECIFICATIONS FOR ALL GAS |
| | EQUIPMENT. THE SPECIFICATIONS SHALL SHOW THAT THE GAS |
| | EQUIPMENT IS LISTED AND LABELED PER 2010 FBC-FUEL GAS |
| | SEC.301.3. |
| | 5) INDICATE THE DELIVERY PRESSURE OF THE GAS SYSTEM ON |
| | THE PLANS. WPB AMEND. TO 2010 FBC SEC. 107.2.1. |
| | 6) INDICATE ON THE PLANS THE TYPE OF PIPE BEING |
| | INSTALLED. WPB AMEND. TO 2010 FBC SEC. 107.2.1. |
| | 7) SHT. P-1 - SIZE EACH SECTION OF PIPE THAT SUPPLIES |
| | THE DEEP FRYERS. COMPLY WITH FGC SEC. 402. |
| | 8) THE TOTAL BTU LOAD OF THE APPLIANCES SHOWN ON THE |
| | EQUIPMENT SCHEDULE DOES NOT CORRELATE WITH THE BTU LOAD |
| | YOU HAVE SHOWN ON SHT. P-1. CLARIFY. |
| | 9) THERE IS A NOTE ON SHT. P-1 FOR THE GAS THAT READS |
| | "NAT GAS TB 403 <2>. I HAVE NO IDEA WHAT THIS RELATES |
| | TO. CLARIFY. |
| | 10) SUBMIT TWO COPIES OF THE MANUFACTURER'S SPEC SHEETS |
| | FOR THE TANKLESS WATER HEATER. THE PLANS NOTE THIS AS A |
| | RESIDENTIAL UNIT. |
| | 11) SEDIMENT TRAPS SHALL BE INSTALLED IN THE GAS LINE |
| | DOWNSTREAM OF THE APPLIANCE SHUTOFF VALVE PER 2010 FGC |
| | SEC. 408.4. |
| | 12) SHT. A-1 - LOAD CALCULATION TABLE SHOWS A GREASE |
| | INTERCEPTOR CALCULATION THAT MAKES NO SENSE. CLARIFY. |
| | CONCRETE GREASE INTERCEPTORS SHALL COMPLY WITH 2010 |
| | FBC-PLUMBING, TABLE 1003.5.1 FOR SIZING AND |
| | SECS.1003.3.4 OR F.A.C. 64E-6 AND FPC SEC.1003.5.1, |
| | 1003.5.2 & 1003.5.3. SUBMIT COMPLETE DETAILS FOR THE |
| | INTERCEPTOR SHOWING CCOMPLIANCE. SUBMIT SIZING |
| | CALCULATIONS FOR THE GREASE INTERCEPTOR. |
| | 13) SHOW THE LOCATION OF THE GREASE INTERCEPTOR ON THE |
| | PLANS. WPB AMEND. TO 2010 FBC SEC. 107.2.1. |
| | 14) THE INTERCEPTORR SHALL BE EQUIPPED WITH A SAMPLING |
| | PORT ON THE DISCHARGE LINE. CONTACT KELLY CRANFORD AT |
| | 561-494-1040 IN THE ENGINEERING DEPT.FOR DETAILS. |
| | 15) SUBMIT DETAILS FOR MEANS OF CONTROLLING THERMAL |
| | EXPANSION WITHIN THE HOT WATER SYSTEM PER 2010 FPC SEC. |
| | 607.3.L |
| | A THOROUGH REVIEW COULD NOT BE PERFORMED DUE TO THE |
| | LACK OF SUFFICIENT INFORMATION. |
| | |
| | |
| | PLUMBING PLAN REVIEW |
| | TIM LARGE |
| | CHIEF PLUMBING INSPECTOR |
| | 561-805-6692 |
| | [email protected] |
| | |