2015-06-02 04:43:44SENT TO ELEC. TO DETERMINE IF ELECTRIC PERMIT IS
 REQUIRED.
2015-06-02 04:41:291) SUBMIT A PIPING DIAGRAM SHOWING THE PIPING, PUMP,
 VALES, TYPE OF PIPE MATERIAL, ETC.FROM THE COLLECTOR TO
 THE WATER STORAGE TANK. WPB AMEND. TO 2010 FBC SEC.
 107.2.1.
 2) THE HAND DRAWN PLANS SHOW THE COLLECTOR LOCATED ON A
 FLAT ROOF BUT DRAWING SL-3C SSHOWS THE PLANS FOR A
 SLOPED ROOF. SUBMIT SIGNED AND SEALED PLANS FOR THE
 COLLECTOR LOCATED PN A FLAT ROOF.
 3) SUBMIT WIND LOAD ENGINEERING FOR THE COLLECTOR
 LOCATED ON A FLAT ROOF. WPB AMEND. TO 2010 FBC SEC.
 107.2.1.
 4) THE CONNECTION FROM THE POTABLE WATER SYSTEM SHALL
 BE EQUIPPED WITH BACKFLOW PROTECTION PER 2010 FBCR,
 SEC.M2301.5, P2902.5.5. (SEE EXCEPTION).
 5) THE PLANS DO NOT SHOW THAT THE PUMP IS A PLUG IN
 UNIT OR AN EXISTING REPTACLE IF IT IS, AND THERE IS
 ALSO A SPEC SHEET FOR A TEMPERATURE CONTROL DEVICE. A
 SEPARATE ELECTRIC PERMIT MAY BE REQUIRED. WPB AMEND. TO
 2010 FBC SEC. 107.2.1.
 6) SECTION 403.4.3.2.3 OF 2010 FL. ENERGY CODE REQUIRES
 THAT THE SOLAR COLLECTORS BE TESTED IN ACCORDANCE WITH
 ISO STANDARD 9806 AND SRCC STANDARD TM-1. SUBMIT
 VERIFICATION.
  
 PLUMBING PLAN REVIEW
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 561-805-6692
 [email protected]
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved