| 2015-07-09 11:49:51 | 1ST REVIEW: FBC 2010 MECHANICAL |
| | 7/9/15 |
| | |
| | 1) CLARIFY THE SCOPE OF WORK FOR HVAC. IT APPEARS THAT |
| | AC SYSTEMS REPLACEMENTS ARE PROPOSED IN EACH OF THE |
| | FOUR UNITS, INCLUDING NEW DUCTWORK IN UNITS 412 AND |
| | 414. PLEASE CONFIRM WITH NOTES ON THE PLAN. PLEASE NOTE |
| | THAT COOLING AND HEATING CALUCLATIONS, AND ENERGY |
| | CALCULATIONS ARE REQUIRED FOR ANY PREVIOUSLY |
| | UNCONDTIONED BUILDINGS THAT ARE NOW BEING CONDITIONED- |
| | TABLE 101.4.1 AND SECTION 403.6.1 FBC-10 ENERGY |
| | CONSERVATION. |
| | 2) PROVIDE AC EQUIPMENT SCHEDULES ON THE PLANS LISTING |
| | MAKES AND MODELS, COOLING AND HEATING CAPACITES, |
| | EFFICIENCY RATINGS, AND ELECTRICAL REQUIEMENTS. |
| | 3) SUBMIT AHRI CERTIFICATES FOR EACH NEW AC SYSTEM- |
| | SECTION 101.4.7 FBC-10 ENERGY CONSERVATION |
| | 4) PROVIDE CONDENSATE DISPOSAL DETAILS FOR EACH SYSTEM- |
| | TYPE AND SIZE OF PIPING, PIPING RUNS, AND DISCHARGE |
| | LOCATIONS. INDICATE HOW SECONDARY OR AUXILIARY DISPOSAL |
| | IS BEING ACCOMPLISHED- SECTION 307.2.3 FBC-10 MECH. |
| | 5) THE PLAN SHOWS AIR HANDLERS IN THE ATTICS OF UNITS |
| | 412 & 414, HOWEVER NO ACCESS IS SHOWN ON THE PLANS- SEE |
| | SECTIONS 306.3 AND 306.3.2 AND PROVIDE DETAILS |
| | INDICATING COMPLIANCE WITH ALL REQUIREMENTS. |
| | 6) SHEET 3.1: THE CU MOUNTING DETAIL HAS INCOMPLETE |
| | DETAILS: PROVIDE THE DEPTH OF ANCHOR EMBEDMENT INTO THE |
| | SLAB, INDICATE WHICH TIE-DOWN CLIP TO BE INSTALLED, AND |
| | THE WIND LOAD DESIGN CRITERIA- SECTION 301.12. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 561-805-6719 |
| | [email protected] |
| | |
| | |