| 2015-06-18 08:00:06 | 1) SHT. S-1 - ZONING & OCCUPANCY BOX - SHOWS THE |
| | OCCUPANCY TYPE AS MERCANTILE AND THE GENERAL BUILDING |
| | CODE ANALYSIS BOX ON E-1 NOTES THE OCCUPANCY AS |
| | BUSINESS.CLARIFY. ALSO, THE INFORMATION IN THE GENERAL |
| | BUILDING CODE ANALYSIS BOX ON SHT. E-1 DOES NOT APPEAR |
| | TO BE FOR THIS SPACE. THE TENANT SPACE IS LISTED AS |
| | 6300 SQ.FT. AND SHT. S-1 NOTES THIS SPACE AS 1300 SQ. |
| | FT. IF DOES NOT APPLY TO THIS SPACE THEN DELETE IT FROM |
| | THE PLANS. |
| | 2) THIS OCCUPANCY SHALL BE CLASSIFIED PER SEC. 302 OF |
| | THE 2010 - FBC-BUILDING.INDICATE THE CORRECT OCCUPANCY |
| | ON BOTH SHEETS OF BOTH SETS OF PLANS. |
| | 3) THERE IS ALSO A DISCREPANCY IN THE TYPE OF |
| | CONSTRUCTION ON THE PLANS.SHT. S-1 NOTES THE TYPE OF |
| | CONSTRUCTION AS TYPE III ( IN THE ZONING & OCCUPANCY |
| | BOX) & AS TYPE IIB ( IN THE CODE INFORMATION BOX). WHAT |
| | TYPE OF CONSTRUCTION IS IT? SHT. E-1 SHOWS THE TYPE OF |
| | CONSTRUCTION AS IIB IN THE GENERAL BUILDING CODE |
| | ANALYSIS BOX. THE TYPE OF CONSRTUCTION SHALL BE THE |
| | SAME ON ALL SHEETS. REVISE THE INFORMATION ON ALL |
| | SHEETS TO MATCH. |
| | 4) THE NEW P-1 SHEET THAT WAS SUBMITTED SHOWS THE |
| | OCCUPANCY CLASSIFICATION AS "BUSINESS" AND |
| | "MERCANTILE". CLARIFY. THIS DOES NOT APPEAR TO BE A |
| | MIXED OCCUPANCY AND IT IS NOT A MERCANTILE |
| | OCCUPANCY.REVISE ALL THE SHEETS TO REFLECT THE CORRECT |
| | OCCUPANCY OF THIS SPACE AND THE CORRECT TYPE OF |
| | CONSTRUCTION. |
| | 5) THE FLOOR DRAIN SHALL BE EQUIPPED WITH A FLOOR |
| | DRAIN.SHOW THIS ON THE PLAN. |
| | 6) THERE IS NO CONNECTION OF THE HOT WATER LINE SHOWN |
| | AT THE HOT WATER HEATER. CLARIFY. |
| | |
| | NOTE: CORRECTIONS SHALL BE MADE TO ALL THE SHEETS ON |
| | BOTH SETS OF PLANS. |
| | |
| | |
| | PLUMBING PLAN REVIEW |
| | TIM LARGE |
| | CHIEF PLUMBING INSPECTOR |
| | 561-805-6692 |
| | [email protected] |
| | |
| | |