| 2015-05-19 17:25:47 | PLAN |
| | REVIEW COMMENTS |
| | |
| | 1ST REVIEW: FBC 2010 |
| | ROBERT MCDOUGAL, CBO |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | (561) 805-6714 |
| | [email protected] |
| | |
| | DENIED BY BUILDING |
| | PLEASE ADDRESS THE ITEMS NOTED BELOW: |
| | |
| | 1) THE SCOPE OF WORK SHOWN ON THE PLANS IS MORE THAN |
| | THE $2400.00 VALUE FOR REFRAMING DAMAGED WALLS THAT IS |
| | SPECIFIED ON THE PERMIT APPLICATION. PLEASE CLEARLY |
| | SPECIFY THE COMPLETE SCOPE OF WORK ON THE PLANS AND |
| | APPLICATION. INCREASE THE VALUE OF WORK ACCORDINGLY. |
| | FBC 107.2.1 & 109.3 |
| | |
| | 2) SHOW COMPLIANCE WITH FBC-R 704. IN ORDER TO PROVIDE |
| | FOR INSPECTION FOR TERMITE INFESTATION, CLEARANCE |
| | BETWEEN EXTERIOR WALL COVERINGS AND FINAL EARTH GRADE |
| | ON THE EXTERIOR OF A BUILDING SHALL NOT BE LESS THAN 6 |
| | INCHES. INSTALL A STUCCO WEEP SCREED AT OR BELOW THE |
| | FOUNDATION PLATE LINE AS REQUIRED BY ASTM C 1063. |
| | |
| | 3) FBC 107.3.4 - PROVIDE TWO SETS OF PRODUCT APPROVALS |
| | FOR THOSE PRODUCTS WHICH ARE REGULATED BY DCA RULE 9N-3 |
| | THAT HAVE BEEN REVIEWED AND APPROVED IN WRITING BY THE |
| | DESIGNER OF RECORD. PROVIDE TWO COMPLETE PRODUCT |
| | APPROVALS WITH FL OR NOA NUMBERS INCLUDING INSTALLATION |
| | INSTRUCTIONS AND MAXIMUM DESIGN PRESSURES FOR EACH OF |
| | THE DIFFERENT WINDOW/GLASS TYPES, STRUCTURAL MULLIONS |
| | AND EXTERIOR DOOR TYPES. |
| | |
| | 4) IF STORM PANELS WILL BE USED, SUBMIT TWO SETS OF |
| | PRODUCT APPROVALS THAT HAVE BEEN REVIEWED AND APPROVED |
| | IN WRITING BY THE DESIGNER OF RECORD. FBC - R 301.2.1.2 |
| | SUBMIT TWO COPIES OF AN INSTALLATION SCHEDULE AND KEY |
| | PLAN FOR THE STORM PANELS. SPECIFY THE OPENING SIZE, |
| | THE WIND PRESSURES, TYPE OF ANCHOR, ANCHOR SPACING, |
| | EDGE DISTANCE, PANEL LENGTH, PANEL SPAN, SEPARATION |
| | DISTANCE FROM PANEL TO GLASS AND THE APPLICABLE SECTION |
| | NUMBER FROM THE INSTALLATION DRAWINGS. I HAVE INCLUDED |
| | A LINK TO THE CONSTRUCTION SERVICES DEPARTMENT SITE |
| | THAT HAS MANY OF THE RELATED FORMS INCLUDING THE |
| | SCHEDULE FOR INSTALLATION OF OPENING PROTECTIVE |
| | DEVICES. |