| 2015-06-08 17:17:24 | 1ST REVIEW: FBC 2010 MECHANICAL |
| | |
| | 1) A COMPLETE REVIEW OF THE PROPOSED PROJECT CANNOT BE |
| | COMPLETED WITHOUT SUBMITTAL OF COMPLETE MANUFACTURER'S |
| | SPECIFICATIONS FOR THE NEW DRYERS AND VENTS. |
| | THE SUBMITTALS SHALL BE REVIEWED AND APPROVED BY THE |
| | DESIGN PROFESSIONAL OF RECORD- SECTION 614 FBC-10 FUEL |
| | GAS. PLEASE NOTE THAT THE CODE CLASSIFIES DRYERS AS |
| | EITHER RESIDIENTIAL OR COMMERCIAL, AND THE |
| | MANUFACTURER'S MAKE THAT DETERMINATION DEPENDING USAGE. |
| | 2) PROVIDE EQUIPMENT SCHEDULES ON THE PLANS FOR THE |
| | DRYERS, AND CLARIFY IF THE DRYERS WILL BE |
| | COIN-OPERATED. |
| | 3) INDICATE THE SOURCE OF, AND THE AMOUNT OF MAKE-UP |
| | AIR REQUIRED BY THE MANUFACTURER FOR EACH DRYER. |
| | 4) PROVIDE A VENTILATION CALCULATION FOR THE LAUNDRY |
| | ROOM IN COMPLIANCE WITH TABLE 403.3 FBC-10 MECHANICAL. |
| | THE DESIGN PROFESSIONAL SHALL VERIFY THE EXISTING |
| | SYSTEMS ARE MEETING THE REQUIRED DEMAND, OR PROVIDE |
| | PLANS AND DETAILS FOR WHATEVER MODIFICATIONS OR |
| | INSTALLATIONS WILL BE NECESSARY. |
| | 5) PROVIDE FRONT AND PLAN VIEWS OF THE EXHAUST VENTS: |
| | INDICATE THE TYPE AND SIZE OF THE DUCTS, LENGTH OF THE |
| | CONNECTORS, HEIGHTS OF RISERS, TOTAL RUN CALCULATIONS |
| | AND TERMINATION LOCATIONS. |
| | |
| | CHRISTOPHER COLE |
| | MECHANICAL PLANS EXAMINER |
| | 561-805-6719 |
| | [email protected] |
| | |