| Date |
Text |
| 2015-05-12 08:40:55 | ** FAILED ** |
| | |
| | PLEASE ADDRESS THE FOLLOWING COMMENTS. RESPOND TO THE |
| | COMMENTS IN WRITING AND/OR ON THE PLANS WHERE |
| | APPLICABLE: |
| | |
| | 1.) FREE-STANDING SIGN SHALL BE SETBACK 20 FT. FROM THE |
| | PUBLIC RIGHT-OF-WAY. [ZLDR S.94-407(2)(E.)(2.)] |
| | |
| | 2.) SCREEN WALL CANNOT EXCEED 6 FT. IN HEIGHT. [ZLDR |
| | S.94-302(B)(2)] |
| | |
| | 3.) SHOW CONTENT FOR THE PROPOSED SIGN. |
| | |
| | 4.) APPROVED RE-PLAT OF THE PROPERTY MUST BE RECORDED |
| | PRIOR TO THE SUBMISSION OF ANY BUILDING PERMITS FOR THE |
| | DEVELOPMENT. |
| | |
| | 5.) THE LOCATION AND DIMENSIONS OF THE FREE-STANDING |
| | SIGN AND SCREEN WALL DO NOT MATCH THE PLANS APPROVED BY |
| | STAFF (REFERENCE: ISPR 14-10). |
| | |
| | PLEASE NOTE THAT ANY CHANGES ON THE RESUBMITTED PLANS |
| | MAY RESULT IN ADDITIONAL COMMENTS. CONTACT LINDA LOUIE |
| | @ (561) 822-1458 IF YOU HAVE QUESTIONS. |
| | |
| | |
| | ART IN PUBLIC PLACES REQUIREMENT: |
| | |
| | PURSUANT TO THE ART IN PUBLIC PLACES ORDINANCE NO. |
| | 4504-14, AN ART ASSESSMENT FOR THE PROJECT IS REQUIRED. |
| | THE APPLICANT SHALL COMPLETE ONE OF THE FOLLOWING |
| | WITHIN NINETY (90) DAYS OF THE ISSUANCE OF THE FIRST |
| | BUILDING PERMIT: |
| | |
| | OPTION 1: SUBMIT DOCUMENTATION EVIDENCING THE ESCROW OF |
| | FUNDS FOR A WORK OF ART OR HISTORIC OR CULTURAL |
| | ELEMENTS VALUED IN AN AMOUNT OF ONE PERCENT OF THE |
| | TOTAL VERTICAL CONSTRUCTION COSTS IN COMPLIANCE WITH |
| | ORDINANCE NO. 4504-14 AND SUBMIT AN APPLICATION FOR |
| | APPROVAL OF THE WORK OF ART OR HISTORIC OR CULTURAL |
| | ELEMENTS. |
| | |
| | OPTION 2: CONTRIBUTE AN AMOUNT EQUAL TO ONE PERCENT OF |
| | THE TOTAL VERTICAL CONSTRUCTION COSTS FOR DEPOSIT TO |
| | THE ART IN PUBLIC PLACES FUND. |
| | |
| | *** UNLESS AN ALTERNATIVE DEADLINE IS ESTABLISHED IN A |
| | DEVELOPMENT ORDER, OR A TIME EXTENSION IS GRANTED BY |
| | THE DIRECTOR OF DEVELOPMENT SERVICES, NO CERTIFICATE OF |
| | OCCUPANCY FOR THE PROJECT SHALL BE ISSUED UNTIL THE |
| | ARTWORK IS INSTALLED, THE FINAL REVISED CONSTRUCTION |
| | COST AFFIDAVIT AND ACCOUNTING OF THE ESCROWED ART FUNDS |
| | HAS BEEN PROVIDED; AND/OR THE FULL ART ASSESSMENT HAS |
| | BEEN PAID TO THE CITY. *** |
| | |