| Plan Review Notes For Permit 15040815 |
| Permit Number |
15040815 |
|
| Review Stop |
B |
| Sequence Number |
2 |
|
| Notes |
| Date |
Text |
| 2015-05-27 09:35:59 | ****PROVISO**** | | | | | | SAMANTHA HILL | | | BUILDING PLANS EXAMINER | | | [email protected] | | | 561-805-6724 | | | | | | ALTHOUGH CONTRACTOR HAS INDICATED THAT THE SUBSTRATE IS | | | BLOCK, CBS STRUCTURES TYPICALLY HAVE CONCRETE TOP | | | SUBSTRATE, BLOCK BOTTOM. THE ANCHOR SPACING PROPOSED | | | COMPLIES FOR ANY OF THE INSTALLATION METHODS WITH THE | | | EXCEPTION OF MANY WHICH DO NOT ALLOW INSTALLATION INTO | | | A BLOCK SUBSTRATE. | | | | | | THIS PERMIT IS ISSUED SUBJECT TO A CONCRETE SUBSTRATE | | | AT THE TOP. IF THIS IS NOT THE JOB CONDITION, | | | CONTRACTOR IS TO REVISE THE INSTALLATION SCHEDULE AND | | | SUBMIT (AS A REVISION IF PERMIT IS ALREADY ISSUED, AS A | | | RESUBMITTAL IF PERMIT HAS NOT YET BEEN ISSUED). | | | | | | |
|