| 2015-05-27 11:00:44 | 1ST REVIEW: FBC 2010 MECHANICAL |
| | |
| | 1) THE AC PLANS FROM CMI SHOW THE AIR HANDLER IN THE |
| | BONUS ROOM ADDITION, HOWEVER THE ELECTRICAL PLANS SHOWS |
| | IT IN THE ATTIC: PLEASE MAKE THESE PLANS AGREE ON |
| | LOCATION. SEE SECTION M1305.1.3.2FBC-RESIDENTIAL FOR |
| | AIR HANDLER IN ATTIC REQUIREMENTS. |
| | 2) SUBMIT MANUAL J AC LOAD WORKSHEETS INDICATING THE |
| | CALCULATIONS PER EACH ROOM OF THE NEW ADDITION. THE |
| | SUBMITTED SUMMARY CALC SHEET DOES NOT INDICATE THE |
| | ADDRESS, DIRECTIONAL ORIENTATION OR AREA CALCULATION- |
| | SECTION 403.6.1 FBC-10 ENERGY. |
| | 3) THE AC PLAN DOESN'T INDICATE A MEANS OF RETURN AIR |
| | FROM THE BONUS ROOM- SECTION M1602.4 FBC-10 |
| | RESIDENTIAL. |
| | 4) PROVIDE A PRIMARY CONDENSATE DISPOSAL PLAN- SHOW |
| | TYPE AND SIZE OF PIPING, PIPING RUN, AND DISCHARGE |
| | LOCATION. PLACE A NOTE OR DETAIL CLARIFYING HOW |
| | SECONDARY DISPOSAL WILL BE ACCOMPLISHED- SECTION |
| | M1411.3 FBC-10 RES. |
| | 5) SHOW THE REFRIGERATION PIPING RUNS ON THE PLAN. |
| | 6) PROVIDE DETAILS FOR INSTALLATION OF THE CONDENSER |
| | PAD AND TIE DOWN OF THE UNIT PER SECTIONS- M1305.1.4.1 |
| | AND M1307.2.1 FBC-10 RES. |
| | 7) ENERGY EFFICIENCY FORM 405-2010: COMPLETE THE CODE |
| | COMPLIANCE CHECKLIST ON PAGE 5. |
| | |
| | CHRISTOPHER COLE |
| | MECHANICAL PLANS EXAMINER |
| | 561-805-6719 |
| | [email protected] |
| | |