| Plan Review Notes For Permit 15040655 |
| Permit Number |
15040655 |
|
| Review Stop |
G |
| Sequence Number |
1 |
|
| Notes |
| Date |
Text |
| 2015-05-02 09:34:26 | SEPARATE PERMIT AND REVIEW REQUIRED FOR GAS. TKL. | | | A GAS PLAN HAS NOT BEEN INCLUDED IN THIS SUBMITTAL | | | PACKAGE. A GAS PLAN REVIEW HAS NOT BEEN PERFORMED AT | | | THIS TIME. A GAS PERMIT IS REQUIRED FOR A CONTRACTOR TO | | | PERFORM THE RELATED WORK. PROVIDE COMPLETE PLANS AND | | | GAS RISER THAT REFLECTS THE ENTIRE SCOPE OF GAS WORK TO | | | BE DONE. | | | WPB AMEND. TO FBC SEC. 107.2.1. | | | | | | |
|