2015-04-20 15:26:15** FAILED **
  
 PLEASE ADDRESS THE FOLLOWING COMMENTS. RESPOND TO THE
 COMMENTS IN WRITING AND/OR ON THE PLANS WHERE
 APPLICABLE:
  
 1.) FINAL PLAT MUST BE APPROVED AND RECORDED PRIOR TO
 ZONING APPROVAL OF PERMIT.
  
 2.) SUBMITTED PERMIT PLANS DO NOT MATCH THE APPROVED
 PLANS FOR THE RECREATION AREA (REFERENCE ISPR #14-10).
 PLEASE CLARIFY IF CHANGES ARE BEING PROPOSED FROM THE
 APPROVED PLANS.
  
 3.) THE SITE PLAN FOR THE RECREATION AREA MUST ALSO
 INCLUDE SITE AND BUILDING CALCULATIONS; SETBACK
 DIMENSIONS FOR THE CABANA, POOL EQUIPMENT AND POOL
 EQUIPMENT SCREENING IN RELATIONSHIP TO THE PARCEL
 LINES; AND PEDESTRIAN WALKING PATH AND SITE CIRCULATION
 WITHIN THE RECREATION PARCEL.
  
 4.) PLEASE CLARIFY IF THE POOL EQUIPMENT SCREENING WILL
 HAVE A GATE TO PREVENT ACCESS TO THE EQUIPMENT AREA.
  
 5.) SEPARATE REVIEW AND PERMIT APPLICATIONS REQUIRED
 FOR THE FOLLOWING: SWIMMING POOL ENCLOSURE, SWIMMING
 POOL, LANDSCAPING, BICYCLE RACK AND STRIPING.
  
 PLEASE NOTE THAT ANY CHANGES ON THE RESUBMITTED PLANS
 MAY RESULT IN ADDITIONAL COMMENTS. CONTACT LINDA LOUIE
 @ (561) 822-1458 IF YOU HAVE QUESTIONS.
  
  
 ART IN PUBLIC PLACES REQUIREMENT:
  
 PURSUANT TO THE ART IN PUBLIC PLACES ORDINANCE NO.
 4504-14, AN ART ASSESSMENT FOR THE PROJECT IS REQUIRED.
 THE APPLICANT SHALL COMPLETE ONE OF THE FOLLOWING
 WITHIN NINETY (90) DAYS OF THE ISSUANCE OF THE FIRST
 BUILDING PERMIT:
  
 OPTION 1: SUBMIT DOCUMENTATION EVIDENCING THE ESCROW OF
 FUNDS FOR A WORK OF ART OR HISTORIC OR CULTURAL
 ELEMENTS VALUED IN AN AMOUNT OF ONE PERCENT OF THE
 TOTAL VERTICAL CONSTRUCTION COSTS IN COMPLIANCE WITH
 ORDINANCE NO. 4504-14 AND SUBMIT AN APPLICATION FOR
 APPROVAL OF THE WORK OF ART OR HISTORIC OR CULTURAL
 ELEMENTS.
  
 OPTION 2: CONTRIBUTE AN AMOUNT EQUAL TO ONE PERCENT OF
 THE TOTAL VERTICAL CONSTRUCTION COSTS FOR DEPOSIT TO
 THE ART IN PUBLIC PLACES FUND.
  
 *** UNLESS AN ALTERNATIVE DEADLINE IS ESTABLISHED IN A
 DEVELOPMENT ORDER, OR A TIME EXTENSION IS GRANTED BY
 THE DIRECTOR OF DEVELOPMENT SERVICES, NO CERTIFICATE OF
 OCCUPANCY FOR THE PROJECT SHALL BE ISSUED UNTIL THE
 ARTWORK IS INSTALLED, THE FINAL REVISED CONSTRUCTION
 COST AFFIDAVIT AND ACCOUNTING OF THE ESCROWED ART FUNDS
 HAS BEEN PROVIDED; AND/OR THE FULL ART ASSESSMENT HAS
 BEEN PAID TO THE CITY. ***