| 2015-05-19 18:23:56 | FAILED |
| | |
| | 1. THANK YOU FOR PROVIDING THE LANDSCAPE PLANS FOR THE |
| | PROJECT. PLEASE SEE THE COMMENTS BELOW FOR CORRECTIONS |
| | THAT NEED TO BE MADE TO THE PLANS: |
| | |
| | A. MAHOGANY (EXCELLENT CONDITION) TREE NO. 8 SHOWN AS |
| | REMAINING ON THE EXISTING CONDITION/TREE RELOCATION |
| | PLAN SHALL BE INCLUDED ON THE LANDSCAPE PLAN. |
| | |
| | B. LIVE OAK (GOOD CONDITION) TREE NO. 32 IS SHOWN AS |
| | RELOCATED ON THE EXISTING CONDITION/TREE RELOCATION |
| | PLAN, YET IT IS SHOWN REMAINING IN PLACE ON THE |
| | LANDSCAPE PLAN. THIS TREE SEEMS TO BE IN CONFLICT WITH |
| | PROPOSED 8 IN. GV #3, 8 IN. DCDA #1 AND 8 IN. PIV #1. |
| | |
| | C. MAHOGANY (EXCELLENT AND GOOD CONDITION) TREE NOS. |
| | 14, 15, 24, 28, 38 AND 122 AND LIVE OAK (GOOD |
| | CONDITION) TREE NOS. 77 AND 86 ARE SHOWN AS BEING |
| | REMOVED ON THE ON THE EXISTING CONDITION/TREE |
| | RELOCATION PLAN. THESE TREES SHALL BE RELOCATED AND NOT |
| | DESTROYED. THE MAHOGANY TREES SHALL BE USED TO FILL IN |
| | THE MISSING GAPS ALONG THE SOUTH BUFFER AND THE OAK |
| | TREES SHALL BE USED IN LIEU OF PURCHASING NEW OAK |
| | TREES. |
| | |
| | 2. PLEASE SHOW THE LIMITS OF WORK UNDER THE PHASE I |
| | VIBROFLOTATION PERMIT ON THE SUBMITTED LANDSCAPE PLANS |
| | SO IT IS CLEAR WHICH TREES WILL BE FENCED FOR |
| | PRESERVATION AND WHICH TREES WILL BE RELOCATED TO THE |
| | SOUTHERN BUFFER AREA THAT WILL NEED TO BE CONSTRUCTED |
| | PRIOR TO THE COMMENCEMENT OF THE VIBROFLOTATION WORK. |
| | THE LIMITS OF WORK ON THIS PLAN WILL NOT INCLUDE THE |
| | RIGHT-OF-WAY THAT THE PREVIOUSLY SUBMITTED PLANS |
| | SHOWED. PLEASE NOTE THAT ANY PORTIONS OF THE CONVENTION |
| | CENTER PARKING LOT WHICH WILL REMAIN OPEN SHALL INCLUDE |
| | THE REQUIRED LANDSCAPE ISLANDS. |
| | |
| | 3. THE FICUS HEDGE THAT IS LOCATED ALONG THE SOUTH AND |
| | EAST PROPERTY WALLS IS IN BAD HEALTH AND SHALL BE |
| | REMOVED AS PART OF THIS PHASE. IT SHALL BE REPLACED |
| | WITH A NATIVE HEDGE AS PART OF THE LANDSCAPE |
| | INSTALLATION COMPLETION FOR THE SITE. |
| | |
| | 4. PLEASE VERIFY WITH THE CONSTRUCTION SERVICES |
| | DIVISION IF THE SOUTHERN BUFFER AREA MAY BE INCLUDED |
| | WITH THIS PERMIT, REQUIRES A SEPARATE PERMIT, OR IF IT |
| | IS HANDLED VIA THE ENGINEERING PERMIT. |
| | |
| | CONTACT ERIC SCHNEIDER @ (561) 822-1446. |