| 2015-09-09 15:45:42 | 2ND REVIEW: FBC 2010 MECHANICAL |
| | PERMIT #15020937 |
| | 9/9/2015 |
| | |
| | 1) PROVIDE AC COOLING AND HEATING LOAD CALCULATIONS FOR |
| | THE CHILLER, AHU'S, FCU'S, & AHU/CU 1 & 2. REFER TO |
| | SECTION 503.2.1 FBC-10 ENERGY CONSERVATION: CALCULATION |
| | OF HEATING AND COOLING LOADS. |
| | DESIGN LOADS SHALL BE DETERMINED IN ACCORDANCE WITH THE |
| | PROCEDURES DESCRIBED IN THE ASHRAE/ACCA STANDARD 183 OR |
| | ACCA MANUAL N AND SHALL BE ATTACHED TO THE CODE |
| | COMPLIANCE FORM SUBMITTED TO THE BUILDING DEPARTMENT |
| | WHEN THE BUILDING IS PERMITTED OR, IN THE EVENT THE |
| | MECHANICAL PERMIT IS OBTAINED AT A LATER TIME, THE |
| | SIZING CALCULATION SHALL BE SUBMITTED WITH THE |
| | APPLICATION FOR THE MECHANICAL PERMIT. HEATING AND |
| | COOLING LOADS SHALL BE ADJUSTED TO ACCOUNT FOR LOAD |
| | REDUCTIONS THAT ARE ACHIEVED WHEN ENERGY RECOVERY |
| | SYSTEMS ARE UTILIZED IN THE HVAC SYSTEM IN ACCORDANCE |
| | WITH THE ASHRAE HVAC SYSTEMS AND EQUIPMENT HANDBOOK. |
| | ALTERNATIVELY, DESIGN LOADS SHALL BE DETERMINED BY AN |
| | APPROVED EQUIVALENT COMPUTATION PROCEDURE, USING THE |
| | DESIGN PARAMETERS SPECIFIED IN CHAPTER 3. |
| | 2) PROVIDE ENERGY CALCULATIONS IN COMPLIANCE WITH |
| | SECTION 501.2 FBC-10 ENERGY CONSERVATION. SUBMIT TWO |
| | COPIES OF FORM 502 FOR PRESCRIPTIVE COMPLIANCE, OR FORM |
| | 506 FOR PERFORMANCE BASED COMPLIANCE USING COMMISION |
| | APPROVED SOFTWARE PRINTOUT. |
| | 4) SHEET M0.1: APPLICABLE BUILDING CODES SHALL ALSO |
| | INCLUDE THE FBC-10 ENERGY CONSERVATION CODE. PLEASE |
| | REVIEW AND REVISE. |
| | 5) SHEET M0.1: THE VENTILATION CALCULATION TABLE IS NOT |
| | INDICATING ANY O/A CFM'S FOR THE CORRIDOR. PER TABLE |
| | 403.3, VENTILATION SHALL BE PROVIDED AT .06 CFM'S PER |
| | SQ. FT. PLEASE REVISE THE TABLE ACCORDINGLY. |
| | 6) M2.1: DAMPERS MISSING AT THESE LOCATIONS- A) 18"X14" |
| | DUCT PENETRATING RATED WALL BETWEEN CORRIDOR 1-002 AND |
| | ROOM 1-111. B) 8" ROUND DUCT PENETRATING RATED WALL |
| | BETWEEN CORRIDOR 1-002 AND ROOM 1-111A. C) 12"X12" DUCT |
| | PENETRATING RATED WALL BETWEEN CORRIDOR 1-009 & ROOM |
| | 1-201. |
| | 7) M2.2: DAMPERS MISSING AT THESE LOCATIONS- A) 14"X14" |
| | DUCT PENETRATING THE RATED WALL BETWEEN CORRIDOR 1-006 |
| | AND ROOM 1-202. B) 8" ROUND DUCT PENETRATING THE RATED |
| | WALL BETWEEN ROOM 1-202 AND CORRIDOR 1-009. |
| | 8) M2.1 & M2.2: PLEASE CLARIFY WHY ALL OF THE AC DUCTS |
| | PENETRATING THE SMOKE PARTITIONS ON THE PLANS HAVE |
| | SMOKE DAMPERS BUT NONE OF THE EXHAUST DUCTS PENETRATING |
| | THOSE WALLS HAVE DAMPERS. |
| | 9) M2.3: THE CHILLER DETAIL IS REFERENCING THE |
| | STRUCTURAL PLANS FOR ANCHORING THE UNIT, HOWEVER THE |
| | DETAIL ON SHEET S-4.3 DOES NOT INDICATE HOW THE CHILLER |
| | IS TO BE TIED DOWN TO THE CURB. PLEASE REVISE THE |
| | DETAIL. |
| | 10) M2.3: PROVIDE WINDLOAD TIE DOWN ENGINEERING FOR |
| | ANCHORING THE DUCT STANDS- SECTION 301.12 FBC-10 |
| | MECHANICAL. |
| | 11) M6.1: PROVIDE A NARRATIVE TO CLARIFY HOW THE |
| | DIGITAL CONTROL SYSTEM WILL FUNCTION WITH THE HVAC |
| | SYSTEM- REFER TO SECTION 503.2.4 FBC-10 ENERGY |
| | CONSERVATION. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 561-805-6719 |
| | [email protected] |
| | |
| | |