Text |
| 2015-03-14 05:06:55 | 1) SUBMIT A SANITARY AND WATER RISER FOR REVIEW THAT |
| | CLEARLY REFLECTS THE SCOPE OF WORK TO BE DONE. WPB |
| | AMEND. TO 2010 FBC SEC. 107.3.5.1.3. |
| | 2) SUBMIT A PIPNG DIAGRAM FOR THE RELOCATED COMPRESSOR. |
| | SHOW TYPE OF PIPING, ALL DROPS, VALVES, ETC.WPB AMEND. |
| | TO 2010 FBC SEC. 107.2.1. |
| | 3) SHT. M-2,1, - SUBMIT A RISER DIAGRAM FOR THE |
| | CONDENSATE PIPING SYSTEM. SHOW THE TERMINATION POINT OF |
| | THE SYTEM. WPB AMEND. TO 2010 FBC SEC. 107.2.1. |
| | 4) ALL HOSE BIBBS SHALL BE SEPARATELY VALVED PER THE |
| | 2010 FPC SEC.606.2 (2). |
| | 5) INDICATE THE SIZE OF THE ROOF GUTTER ON THE DOCK |
| | CANOPY. GUTTERS SHALL BE SIZED IN ACCORDANCE WITH TABLE |
| | 1106.6 OF THE 2010 FPC. |
| | 6) THE PLANS REFER TO GAS PIPING. SUBMIT A GAS PIPING |
| | RISER DIAGRAM FOR REVIEW.WPB AMEND. TO 2010 FBC SEC. |
| | 107.2.1. |
| | 7) SUBMIT A ROOF DRAINAGE PLAN SHOWING THE SQUARE |
| | FOOTAGE OF THE ROOF DRAINED BY EACH DOWNSPOUT. THE SIZE |
| | OF THE DOWNSPOUTS SHALL COMPLY WITH TABLE 1106.2 (2). |
| | 8) SHOW THE TERMINATION POINT OF THE RAIN WATER SYSTEM. |
| | THE ENGINEERING PLANS APPEAR TO BE INCONCLUSIVE. THE |
| | LEADERS DISCHARGE TO THE CATCH BASINS AND FROM THERE |
| | INTO RCP BUT I CANNOT DETERMINE WHERE THE FINAL |
| | DISCHARGE POINT IS. I ASSUME THE RETENTION BASINS BUT |
| | IT IS NOT CLEAR ON THE ENGINEERING PLAMS. CLARIFY. |
| | 9) IF THERE IS A PARAPET WALL THEN ONE-HALF OF THE AREA |
| | OF ANY VERTICAL WALL THAT DIVERTS RAINWATER TO THE ROOF |
| | SHALL BE ADDED TO THE PROJECTED ROOF AREA FOR INCLUSION |
| | IN CALCULATING THE REQUIRED SIZE OF THE VERTICAL |
| | CONDUCTORS, LEADERS AND HORIZONTAL STORM DRAINAGE |
| | PIPING. 2010 FPC SEC.1106.4. |
| | |
| | PLUMBING PLAN REVIEW |
| | TIM LARGE |
| | CHIEF PLUMBING INSPECTOR |
| | 561-805-6692 |
| | [email protected] |
| | |