| 2015-02-18 08:43:16 | PLAN REVIEW COMMENTS |
| | |
| | 1ST REVIEW: FBC 2010 |
| | ROBERT MCDOUGAL, CBO |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | (561) 805-6714 |
| | [email protected] |
| | |
| | DENIED BY MECHANICAL |
| | PLEASE ADDRESS THE ITEMS NOTED BELOW: |
| | |
| | 1) FBC ENERGY CONSERVATION - SECT. 403.6.1 EQUIPMENT |
| | SIZING. |
| | HEATING AND COOLING EQUIPMENT SHALL BE SIZED IN |
| | ACCORDANCE WITH ACCA MANUAL S BASED ON THE EQUIPMENT |
| | LOADS CALCULATED IN ACCORDANCE WITH MANUAL J OR OTHER |
| | APPROVED HEATING AND COOLING CALCULATION METHODOLOGIES, |
| | BASED ON BUILDING LOADS FOR THE DIRECTIONAL ORIENTATION |
| | OF THE BUILDING. THE MANUFACTURER AND MODEL NUMBER OF |
| | THE OUTDOOR AND INDOOR UNITS (IF SPLIT SYSTEM) SHALL BE |
| | SUBMITTED ALONG WITH THE SENSIBLE AND TOTAL COOLING |
| | CAPACITIES AT THE DESIGN CONDITIONS DESCRIBED IN |
| | SECTION 302.1. THIS CODE DOES NOT ALLOW DESIGNER SAFETY |
| | FACTORS, PROVISIONS FOR FUTURE EXPANSION OR OTHER |
| | FACTORS WHICH AFFECT EQUIPMENT SIZING. SYSTEM SIZING |
| | CALCULATIONS SHALL NOT INCLUDE LOADS CREATED BY LOCAL |
| | INTERMITTENT MECHANICAL VENTILATION SUCH AS STANDARD |
| | KITCHEN AND BATHROOM EXHAUST SYSTEMS. PROVIDE EQUIPMENT |
| | SIZING CALCULATIONS. |
| | |
| | 2) FBC - 107.3.5.3 PROVIDE A MECHANICAL PLAN TO SHOW |
| | SUPPLY DUCTS PER FBC-R M16 & BATH EXHAUST PER FBC-R |
| | M15. |
| | |
| | 3) FBC -107.3.5.1.4 MECHANICAL MINIMUM PLAN REVIEW |
| | CRITERIA: SHOW, EXHAUST SYSTEMS, CLOTHES DRYER EXHAUST, |
| | KITCHEN EQUIPMENT EXHAUST, SPECIALTY EXHAUST SYSTEMS, |
| | EQUIPMENT, EQUIPMENT LOCATION, MAKE-UP AIR, |
| | ROOF-MOUNTED EQUIPMENT, DUCT SYSTEMS, VENTILATION, |
| | COMBUSTION AIR, CHIMNEYS, FIREPLACES AND VENTS, |
| | APPLIANCES, BOILERS, REFRIGERATION, BATHROOM |
| | VENTILATION, LABORATORY, DESIGN FLOOD ELEVATION. |
| | |
| | 4) FBC 107.2.1 PROVIDE THE MODEL NUMBERS AND |
| | SPECIFICATIONS OF THE HEATING AND COOLING EQUIPMENT IN |
| | AN EQUIPMENT SCHEDULE ON THE MECHANICAL PLAN THAT |
| | CORRESPONDS WITH THE EQUIPMENT SIZING CALCULATIONS. |
| | |
| | 5) FBC-R - M 1602.4 PROVIDE BALANCED AIR RETURN AT |
| | BEDROOMS. |
| | |
| | 6) M1602.2 PROHIBITED SOURCES. OUTDOOR AND RETURN AIR |
| | FOR A FORCED-AIR HEATING OR COOLING SYSTEM SHALL NOT BE |
| | TAKEN FROM THE FOLLOWING LOCATIONS: |
| | 4. A CLOSET, BATHROOM, TOILET ROOM, KITCHEN, GARAGE, |
| | MECHANICAL ROOM, BOILER ROOM, FURNACE ROOM, |
| | UNCONDITIONED ATTIC OR OTHER DWELLING UNIT. |
| | THE PROPOSED FLOOR PLAN ON SHEET A-1 SHOWS THE NEW AIR |
| | HANDLER LOCATED IN A CLOSET IN THE KITCHEN. |
| | |
| | |
| | |
| | |
| | |